SOW.pdf

PDF 8 KB Posted

Attached to
Aerobic Wastewater Systems Project Federal contract opportunity
Solicitation number
246-17-Q-0004
Issued by
Department of Health and Human Services Indian Health Service

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Aerobic Wastewater Systems Project, newest first.
File Type Posted
Questions_12-21-16.pdf PDF
Bid_schedule_updated_12-21-16.pdf PDF
Bid_schedule_updated_12-14-16.pdf PDF
Creeknationaerobics_Questions.pdf PDF
Salem_Soil_Test.pdf PDF
Hanna_Soil_Test.pdf PDF
Misty_valley_soil_test.pdf PDF
Creek_Aerobic_Systems_Spec.pdf PDF
General_Decision_Number_OK160033_10-07-2016__OK33.pdf PDF
Creek_Aerobic_Systems_Spec.docx DOCX document
Bid_schedule.pdf PDF
SF24-16.pdf PDF
ok10-s14-16_Drawings.pdf PDF
Aerobic_Project_OEH_Okmulgee_SF18_R1.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Muscogee (Creek) Nation Housing

Aerobic Systems Okmulgee OEHE

September 13, 2016

Hanna - OK 10-S14 Misty Valley - OK 10-S15 Salem - OK 10-S16

Location;

Hanna, Misty Valley and Salem in McIntosh County, Oklahoma.

Statement of Work:

Pump and inspect the existing septic tanks. If they are in good condition connect the aerobic system to the septic tank outlet. If they are not in good condition crush the tank and abandon in place.

Install individual aerobic spray wastewater treatment systems:

Hanna 7 systems, Misty Valley 3 systems and Salem 6 systems.

Install individual septic tank/chambered drain fields Misty Valley 2 systems.

Abandon manholes:

Hanna 3 manholes, Misty Valley 3 manholes and Salem 3 manholes.

Abandon lift station at Misty Valley.