23-9-20 Time Line Deliverable Optical Comparator LC (3).pdf
PDF 127 KB Posted
- Attached to
- Optical Comparators
- Solicitation number
- W519TC-24-Q-2222
About this file
This document is a timeline of deliverables for an Optical Comparator contract (Project RIPD E4000-23-9-20) at the Rock Island Arsenal. The contract was awarded on the contract award date, with equipment delivery required within 90 days, manuals within 30 days, installation within 120 days, training within 150 days, and final acceptance within 165 days of award. The related federal contract opportunity is Solicitation Number W519TC-24-Q-2222 for Optical Comparators, a firm fixed price (FFP) award to the lowest priced, responsive, responsible vendor. Quotes are due by 6 PM on April 11, 2024 and must include a Certificate of Conformance. The contracting agency is the Department of the Army Materiel Command Contracting Command Rock Island Arsenal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROCK ISLAND ARSENAL DATE: 28 March 2024
PROJECT: RIPD E4000-23-9-20
TIMELINE OF DELIVERIES
OPTICAL COMPARATORS
The following proposed timeline for Project RIPD E4000-23-9-20 is based upon the contract award date and the number of calendar days between events. Time allocations are maximums for each stage. It is acceptable to complete a stage in fewer days than shown on the timeline and move on to the next stage.
The timeline for this project is as follows:
• Contract Award Contract Award
• Equipment Delivery Contract Award + 90 Days
• Manuals Contract Award + 30 Days
• Equipment Installation Contract Award + 120 Days
• Training (Operator, Maintenance) Contract Award + 150 Days
• Final Acceptance Contract Award + 165 Days
Total Maximum Time from Award to Acceptance Contract Award + 165-days
Metallographic Cut Saw for Lab in support of AM