27 May 2022

Attachment A

Specifications

89503222BWA000055

MONTANA

YELLOWTAIL SWITCHYARD

BREAKER 1662 AND 1862

REPLACEMENT

SECTION C

DESCRIPTION/SPECIFICATIONS

Spec. No. 1041

SECTION C

DESCRIPTION/SPECIFICATIONS

YELLOWTAIL SWITCHYARD BREAKER 1662 AND 1862 REPLACEMENT

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT

B. DESCRIPTION OF WORK

C. DESCRIPTION OF BIDDING SCHEDULE ITEM

1. Bidding Schedule item “Mobilization and preparatory work”

D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

1. Submittal Approval Time

2. Commencement of Control Work

3. Outage Restrictions

4. Construction Schedule Restrictions

5. Protective Ground Leads

6. Maximum Available Fault Current

E. CONSTRUCTION SCHEDULE

1. Submittal Time

2. Format and Detail

F. MATERIAL

1. Points-of-Delivery

G. RIGHTS-OF-WAY

1. General

H. GEOLOGIC INVESTIGATIONS

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES

J. WATER FOR CONSTRUCTION PURPOSES

K. EXPLOSIVES AND BLASTING

L. BURIED UTILITIES

M. ELECTRICAL MINIMUM APPROACH DISTANCES

N. SUBMITTALS AND CORRESPONDENCE

1. General

2. Transmittal

3. Submittal Response

4. Physical Sample Submittals

5. Project Protocol

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Part B Bidding Schedule item “Miscellaneous sitework”

2. Bidding Schedule Does Not Contain Separate Items

DIVISION 3 – CONCRETE

A. GENERAL

1. Material

2. Test for Potential Reactivity of Sand and Coarse Aggregate

3. Mix Design

4. Rebar Development (Ld) and Lap Length

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Part B Bidding Schedule item “Concrete foundations”

DIVISION 9 - SUBSTATION ELECTRICAL

A. GENERAL

1. Bidding Schedule for Government-furnished items

2. Bidding Schedule for items (not furnished by the Government)

3. Support Structures

4. Installation and Painting

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Power circuit breaker, 115-kV, 3,000 amp (Government-furnished)”

2. Bidding Schedule item "Associated electrical equipment and material"

3. Bidding Schedule item “Existing outdoor electrical equipment and material”

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS

DIVISION 15 – DRAWINGS

A. CONSTRUCTION DRAWINGS

1. General

B. AS-BUILT DRAWINGS

1. General

2. Recording Information

3. Drawing Markup

4. Drawing Review

5. As-Built Information to be Recorded

C. REVIEW OF AS-BUILT DRAWINGS

1. As Built Drawing Submittal

2. Review

3. Acceptance

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT:

Construct and complete the Yellowtail Switchyard Breaker 1662 and 1862 Replacement project, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; WAPA’s Construction Standards, including Standard 1 – General Requirements (March 2021), Standard 2 – Sitework (March 2021), Standard 3 – Concrete (March 2021), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (March 2021), Standard 5 – Transmission Line Steel Pole Structures (March 2021), Standard 6 – Light Duty Steel Pole Structures (March 2021), Standard 7 – Wood Poles (March 2021), Standard 8 – Glued Laminated Structures (March 2021), Standard 9 – Substation – Electrical (March 2021), Standard 10 – Transmission Line – Electrical (March 2021), Standard 11 – Buildings (March 2021), Standard 12 – Painting (March 2021), Standard 13 – Environmental Quality Protection (March 2021), Standard 14 – Communication Facilities (March 2021), Standard 15 – Drawings (March 2021); Standard Drawings; and these Project Specifications and Drawings.

If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.

WAPA’s Construction Standards, Standard Drawings and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.

WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.

B. DESCRIPTION OF WORK:

The principal components of work include replacing two (2) 115-kV power circuit breakers and associated equipment, material and foundations.

The summary of “Bidding Schedule Items” are more fully described in the following divisions in this specification and in the Construction Standards listed in Division 1, Section A above”.

The work is located near Fort Smith, Montana as shown on Drawing YT 0015.

C. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Mobilization and preparatory work” includes the following:

a. Performing mobilization and preparatory work in accordance with Section H of the contract clauses.

b. Prepare and submit a Construction Schedule and furnish a Safety and Health Program.

D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK: See FAR 52.211-10 in

Section F of the solicitation/contract.

1. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 20-calendar days for review of drawings or data submitted for approval.

2. COMMENCEMENT OF CONTROL WORK: Do not perform any outdoor equipment wiring until receipt of Government-furnished wiring diagrams. WAPA will furnish outdoor wiring and schematic diagrams no sooner than October 30, 2022. Include these restrictions in the Construction Program.

3. OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:

a. Make all outage requests in writing to the onsite WAPA representative a minimum of 30-days in advance. Meeting the minimum advance notice requirement of 30-days does not guarantee an outage will be approved. To improve the chances of an outage being approved, all outages should be submitted with as much advance notice as practicable.

Weather conditions and other system conditions such as other scheduled and nonscheduled (forced) outages must be evaluated against an outage request before approval can be granted. At any time because of transmission system electrical loads, system configurations, weather conditions or any condition which may cause an adverse effect on the transmission system operation or reliability, WAPA may deny an outage request or direct the Contractor to return facilities to operating conditions and release the applicable Special Work Permit.

b. Concurrent outages will not be granted for power circuit breakers 1662 and 1862 together.

c. A total of (2) main bus outages will be granted for removing the old 1662 breaker and bringing the new 1662 breaker in underneath the 115kV east main bus.

4. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:

a. The Contractor shall not work more than 60-hours in one (1) calendar work week without prior approval from the Contracting Officer’s Representative (COR).

b. The Contractor shall allow four (4) weeks per power circuit breaker for WAPA to complete commissioning.

c. The Contractor shall submit a two (2) week notification to the COR, prior to removal of each power circuit breaker to allow for WAPA to disconnect cables.

d. Dependent upon time of year, if ambient temperatures are less than 32 degrees Fahrenheit during power circuit breaker commissioning, the Contractor shall create an environment to bring local ambient temperatures above 32 degrees Fahrenheit.

5. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General

Requirements”, Section 1.4.14.3(1).

6. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:

a. The maximum available fault current in the 115-kV area is 14,719 amps and the X/R ratio is 18.1.

b. A minimum of 1 (one) 1/0 grounds shall be used in the 115-kV area.

E. CONSTRUCTION SCHEDULE:

1. SUBMITTAL TIME: Prepare and submit a Construction Schedule to the Contracting Officer (CO) within 10-calendar days after date of Notice to Proceed.

2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided.

Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.

F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:

Item Estimated

Weight

(LBS)

Estimated Delivery

Date

Estimated Cost

(2) 3-phase, power circuit breaker, 115-kV, 3000 amp 7,500 ea NST 05-15-2023

NLT 05-26-2023 $92,000 ea

NST – No sooner than.

NLT – No later than.

1. POINTS-OF-DELIVERY: Material furnished by WAPA will be delivered to Yellowtail Switchyard.

The power circuit breakers will be unloaded by the supplier. The Contractor shall inspect the power circuit breakers and report any damage to the COR.

G. RIGHTS-OF-WAY:

1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired by the Contractor shall have prior COR approval. During the contract period, WAPA reserves the right to use contractor-obtained access.

H. GEOLOGIC INVESTIGATIONS:

The 8000-series geologic logs of subsurface explorations included in the “Drawings” Division constitute the information and records of geologic investigations for the work. Locations of subsurface investigations are shown on the Drawings.

Samples and cores of recovered material were not retained. Bidders shall obtain their own samples and perform tests on the material to evaluate properties, which they believe to be significant. WAPA does not guarantee that the geologic information and records show the conditions that will be encountered in performing the work, but only that the geologic information and records show conditions encountered at the particular point and time the information and records were obtained.

The geologic information may not indicate variations, such as those caused by seasonal fluctuations in rainfall and other factors, which may affect the water level. The Contractor shall determine the nature of material to be excavated, the difficulties of making and maintaining required excavations and doing other work affected by geology and ground water elevations at the worksite.

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:

Electric power up to a maximum of approximately 5-kVA for construction purposes will be available without cost. Source of supply is located in the receptacles throughout the substation. Power made available by WAPA will be delivered as single-phase, 60 Hz, AC, at approximately 120-240 V.

Coordinate with the COR for establishing electric power service.

The Contractor may furnish power for his operations by other means at no additional cost to WAPA.

Make arrangements and provide all electric power for construction purposes. Provide necessary transmission lines, distribution circuits, transformers and other electrical equipment for distributing the power to the places of use. At contract completion, remove temporary electrical equipment and distribution lines.

J. WATER FOR CONSTRUCTION PURPOSES:

Furnish water for construction purposes. Make arrangements for obtaining the water and provide for conveying the water to the points of use.

K. EXPLOSIVES AND BLASTING:

Explosives shall not be used.

L. BURIED UTILITIES:

Prior to excavation, examine the area and determine the location of buried utilities. Utilities shall be identified with a marker denoting the type of service.

M. ELECTRICAL MINIMUM APPROACH DISTANCES:

In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects or personnel shall not be brought closer to energized facilities than the electrical minimum approach distances established by OSHA 1926.958(b), “Materials, Handling, and Storage”. The less stringent equipment clearance distances established by OSHA 1926.960, “Working On or Near Exposed Energized Parts”, Table V-5 and Table V-6, may only be used after the Contractor has completed and submitted WAPA’s Electrical Clearance Variance form and has received the signed form in return from the COR.

N. SUBMITTALS AND CORRESPONDENCE:

1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements:

a. Submittals shall be in the following formats, standard PDF, Microsoft Word (docx), Microsoft

Excel (xlsx), Electronic CAD (.dwg) (AutoCAD version 2018). All submittals in .dwg format shall also be submitted in .pdf format.

b. Each submittal shall include label at the top of the first page or drawing with the WAPA

Contract number with the Specification number, if applicable (89503222CWA000XXX- 1041), WAPA project title, Bidding Schedule Contract Line Item Number (CLIN) equipment designation or if a designation is not available applicable division number and applicable division paragraph number.

c. Multiple CLIN’s on a single submittal are not permitted. For Associated Electrical Equipment and Material’s CLIN, which contains multiple equipment types, each type shall be submitted separately with the exception that Phase Identification Signs and Equipment Identification Signs can be submitted together.

d. A cover transmittal letter will be provided by WAPA (in both a Microsoft Word and PDF format) and shall be included with each email submittal. The transmittal shall also contain a contact name, the WAPA Contract number with the 4-digit Specification number, if applicable (89503222CWA000XXX-1041), WAPA project title, CLIN and applicable division number and applicable division paragraph number

2. TRANSMITTAL: The Contractor shall submit all correspondence (Request for Information, Submittals, etc.) to the following email address care of the COR.

Rocky Mountain

ATTN: J5600

Email: RMR-J5600-CS@wapa.gov

3. SUBMITTAL RESPONSE: WAPA will provide a response to all submittals in accordance with

Division 1.D.2 of these specifications with an “Acceptable” or “Not Acceptable” status, with comments as appropriate to the email address where the submittals originated.

4. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e., brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlining the physical sample submittal prior to sending the sample (including tracking data when applicable) and shall deliver physical specimens to:

Western Area Power Administration

ATTN: A7900

12155 W. Alameda Parkway Lakewood, CO 80228-2802

5. PROJECT PROTOCOL:

a. Electronic Correspondence:

EMAIL SUBMITTAL FORMAT:

Subject Line in Email Submittal number, Subject, Applicable Standard Number, Project Name/Number, and Contract Number Example: Submittal 017, Steel Compression Dead Ends-Std 10, Yellowtail Switchyard Breaker

1662 and 1862 Replacement, 89503222CWA000XXXX-1041

b. Payment Requests:

EMAIL PAYMENT REQUEST FORMAT:

Invoice number and Project Name/Number and Contract Number Example: Invoice 01, Yellowtail Switchyard Breaker 1662 and 1862 Replacement, 89503222CWA000XXXX-1041

c. Certified Payrolls-Prime and Subcontractors:

EMAIL CERTIFIED PAYROLL FORMAT:

Certified Payroll (CP), Contractor’s names, Week ending (WE), and Project Name/Number, and Contract Number Example: CP-(Smith Inc., Bob’s Electrical), WE 09/12/18 & 09/19/18, Yellowtail Switchyard

Breaker 1662 and 1862 Replacement, 89503222CWA000XXXX-1041

d. Request for Information:

EMAIL (REQUEST FOR INFORMATION) FORMAT:

Request for Information (RFI), Project Name/Number, and Contract Number Example: RFI-003, Labeling Info, Yellowtail Switchyard Breaker 1662 and 1862 Replacement, 89503222CWA000XXXX-1041 mailto:RMR-J5600-CS@wapa.gov

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Part B Bidding Schedule item “Miscellaneous sitework” includes the following:

a. Replacing and protecting existing gravel surfacing.

b. Providing a soil-applied herbicide where gravel surfacing is placed.

c. Completely removing and disposing of concrete foundations designated on Existing Installation Drawings YT 2001 and YT 2003.

2. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.

a. Excavations for foundations, direct buried cable removal and trenches.

b. Placing and compacting earth material and backfill.

c. Providing clean crushed gravel fills under concrete foundations as shown on the Drawings.

d. Disposing of excavated material. Material from excavations not suitable or required for earthwork shall be removed from the substation. The Contractor shall make arrangements required for disposal of waste material in an approved landfill.

DIVISION 3 – CONCRETE

A. GENERAL:

1. MATERIAL:

a. Cement: Type II cement. Types are according to ASTM C 150.

b. Type A and D water-reducing and retarding admixtures may be used if approved by the

COR.

2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: All fine and coarse aggregates shall be tested in accordance with Standard 3. If the tests determine the aggregate(s) to be unsuitable as a concrete aggregate, a suitable source shall be obtained by the Contractor.

a. Acceptance criteria specified in Standard 3 are based on 14-day readings after the zero reading.

3. MIX DESIGN: Provide a performance based concrete mix design in accordance with ACI

211.1 and Table 3.1 below.

a. Net water-cementitious materials ratio (w/c) is maximum, by weight. Cementitious material weight is portland cement plus supplementary cementitious material (SCM).

b. Air Entrainment: Percent air by volume of concrete as discharge at point of placement.

Table 3.1

Description f’c (psi) Max w/c Nominal Maximum

Size Aggregate

(NMSA)

Slump (inches)

Air Content

Substation, Building and other General Structural Concrete

4500 at 28-days 0.45 No. 467 2 – 5 4 - 7

4. REBAR DEVELOPMENT (LD) AND LAP LENGTH:

a. Class B lap splices apply unless noted otherwise; refer to Table 3 on Standard Drawing

01 2004-1 General Outline and Reinforcement Notes.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Part B Bidding Schedule item “Concrete foundations” includes the following:

a. Earthwork, formwork, reinforcement, material used in concrete, void forming material, anchor bolts, curing, finishing, joints and other related work and material needed to complete the concrete construction.

b. Concrete foundations for electrical equipment.

Measurement for quantities for concrete foundations will be made on the basis of concrete quantities shown on Drawing 2056-2. If separate quantities of formed and auger concrete for each type of foundation are shown on the Drawing, the concrete quantity shall be the total of the formed and auger concrete quantities. Regardless of the concrete quantities actually placed, payment will be based on the quantities of concrete shown on the Drawing.

DIVISION 9 - SUBSTATION ELECTRICAL

A. GENERAL:

Electrical equipment and material shall be as specified in WAPA’s “WAPA ES” standard equipment specifications, as shown on project drawings and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL and Federal specifications and standards as applicable. Applicable requirements shall be met under the following service conditions:

Ambient Temperatures:

Maximum ............................................................................................ +40°C Maximum 24-Hour Average ................................................................ +30°C Minimum .............................................................................................. -50°C

Elevation:

Above Mean Sea Level ............................................................... 3,869-Feet

*ASCE-7 Wind Load Minimum Basic Wind Speed ............................................................ 90-MPH Importance Factor ................................................................................. 1.15

*IEEE 693 Seismic Qualification:

Performance Level......................................................................... Moderate

*May include support structure in accordance with STANDARD 9.1.1.2. Wind and seismic loads are non-simultaneous

1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:

a. Unless otherwise indicated, unloading and inspecting Government-furnished items.

b. Installing Government-furnished items as shown on drawings.

c. Furnishing equipment and material not furnished by WAPA.

2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the

Contractor and shall include the following:

a. Providing (furnishing and installing) bidding schedule items.

b. Furnishing equipment and material not furnished by WAPA.

c. Installing bidding schedule items as shown on drawings.

3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel.

Instrument transformers that are seismically qualified shall be 96-inches in height. If tubular steel supports are furnished, they shall be galvanized internally and externally.

4. Installation and painting of electrical equipment and material shall be provided in accordance with

Standards 9 and 12 respectively.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Power circuit breaker, 115-kV, 3,000 amp (Government-furnished)” includes furnishing equipment and material not furnished by WAPA and installing the following Government-furnished power circuit breakers:

Designation JY6A, JY7A

Manufacturer Mitsubishi

Type SF6 Gas

Nominal Voltage Rating (kV) 115

Maximum Voltage Rating (kV) 123

Amps (Continuous) 3,000

Fault Interrupter Rating 40,000 Multi-ratio Current Transformer, each bushing (Amps) 3-2000:5

Multi-ratio Current Transformer Thermal Rating Factor 2.0

Rated Interrupting Time 3 cycles

Basic Impulse Insulation Level 550 kV

Estimated weight of 3-pole breaker (pounds) 7,500

Approximate SF6 Gas Weight (Pounds per breaker) 61

a. The equipment supplier will unload the power circuit breakers from the truck and Contractor personnel shall inspect the circuit breakers for possible damage during shipment and immediately report any damage to the COR.

b. Special tools and appliances and spare parts will be furnished with the power circuit breakers that will include, but are not limited to the following (a complete list will be included with the breaker instruction books):

(1) The set of special tools and appliances shipping with the breakers will include one (1) mechanism jacking unit and one (1) SF6 gas breaker filling connection assembly (including hose, pressure gauge and the hose end connections to the breaker and SF-6 gas cylinder). The Contractor shall deliver the special tools and appliances furnished with the breakers to WAPA’s on-site representative after the circuit breakers are installed.

(2) The set of spare parts will include two (2) trip coils and two (2) close coils. The

Contractor shall deliver the spare parts furnished with the breakers to WAPA’s on-site representative after the circuit breakers are installed.

c. WAPA personnel will fill the power circuit breakers with SF6 gas during the commissioning of the breakers.

2. Bidding Schedule item "Associated electrical equipment and material" includes providing equipment, material and services required to complete the following substation installations as shown on the Drawings:

a. Electrical Testing: Includes providing electrical testing in accordance with Standard 9, paragraph 9.1.2 Acceptance Tests - Method A.

b. Insulated Conductors: Includes reusing the existing control and power cables for breakers JY6A and JY7A. The Contractor shall disconnect the existing control and power cables from existing breakers JY6A and JY7A and remove the cables from the existing conduit.

The Contractor shall install and terminate the reused control and power cables in the new conduit and breaker installations for JY6A and JY7A.

c. Electrical Conduit System: Includes embedded and exposed conduit. Conduit entering the cable trench with a 90-degree bend is allowed to be Schedule 40 PVC as shown on Standard Drawing 31 1006. All other 90-degree bends shall be rigid metal. A red or yellow detectable polyethylene warning tape shall be installed directly above each conduit run.

Open ends of conduit shall be sealed with plugs or caps.

d. Grounding System: Complete the substation grounding system as shown on the Drawings.

Ground cable risers shall be 19-strand No. 9 copper-clad steel cable and shall have a short circuit fault current rating of 40kA or higher for 30 cycles (500ms). Unless otherwise specified on the drawings, splices, crosses, tees and other fittings used on the grounding system may be compression type (DMC Power Swage system or equal).

e. Outdoor Bus System: Complete the outdoor jumper bus installations as shown on the

Drawings.

f. Identification Signs:

(1) Equipment Identification Signs. Signs shall be in accordance with Standard Drawing 31 1000. Lettering on the signs shall be as follows:

(a) LOVELL NO. 2 LINE

YT 1662

PCB JY6A 115KV

(b) LOVELL NO. 1 LINE

YT 1862

PCB JY7A 115KV

3. Bidding Schedule item “Existing outdoor electrical equipment and material” includes removing and disposing of existing outdoor electrical equipment and material.

a. Material to be removed:

(1) Two (2) 115-kV SF6 gas power circuit breakers designated JY6A and JY7A. The power circuit breakers shall be removed from their foundations and placed on a WAPA provided on-site trailer.

b. Material to be removed and disposed:

(1) Miscellaneous aluminum conductor, rigid conduit and exposed and buried ground cables.

c. The Contractor shall include any credit to the Government for salvage of the equipment and/or materials in this bidding schedule item.

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

Bidding Schedule does not contain a separate item for “Environmental Quality Protection”. The cost of compliance with requirements of Division 13 shall be included in the applicable bidding schedule items.

DIVISION 15 – DRAWINGS

A. CONSTRUCTION DRAWINGS:

1. GENERAL: After award of contract, WAPA will provide the Contractor an electronic copy of all suitable for construction drawings. (No hard copies will be provided).

B. AS-BUILT DRAWINGS:

1. GENERAL: The Contractor shall keep one (1) complete set of full-size construction drawings at the jobsite solely for the purpose of recording as-built conditions. The Drawings shall be marked to show any change or variation in the actual construction, which does not match the construction drawings. The as-built set of drawings shall not be used for construction purposes.

2. RECORDING INFORMATION: Record information on the Drawings concurrently with construction progress. Do not conceal work until the required information is recorded. Mark all drawings affected by the actual work which varies from the construction drawings.

3. DRAWING MARKUP: As-built drawing marking shall be as follows:

a. Additions and notes in red.

b. Deletions in green.

c. Explanation notes in blue.

4. DRAWING REVIEW: The marked set of as-built drawings shall be kept onsite and available for inspection at all times.

5. AS-BUILT INFORMATION TO BE RECORDED: Mark drawings with all actual construction which does not match the construction drawings including:

a. Field changes of dimension and detail.

b. Changes made by modifications.

c. Details not shown on original drawings.

d. Other information required to describe the as-built construction.

C. REVIEW OF AS-BUILT DRAWINGS:

1. AS BUILT DRAWING SUBMITTAL: Upon completion of the project, the Contractor shall electronically submit a complete set of marked as-built drawings to the COR for approval prior to the date of submission of your final invoice. Drawings that require no as-built information or markup shall still be included in the submittal and identified as such.

2. REVIEW: The COR will perform a review of the as-built drawing submittal which may include a site walkdown to compare as-built information against physical installation. The COR will identify any issues that need to be resolved prior to acceptance. The Contractor shall address and resolve all issues identified during review and resubmit the as built drawing submittal for acceptance.

3. ACCEPTANCE: Upon acceptance, the Contractor shall invoice for any outstanding cost retained by WAPA as described by Section H of the contract clauses.

Message from the Administrator

At Western Area Power Administration (WAPA), we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to WAPA. In performing work for WAPA, all contractors must make the right decisions to ensure that the work environment is as safe as possible.

Our safety program is based on four points:

Safety procedures or common sense must be applied by each Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.

Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.

Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.

Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.

By integrating these principles into every task we take, together we can ensure WAPA is a safe place to work.

Tracey A. LeBeau Administrator and CEO

DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
B. DESCRIPTION OF WORK:
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK: See FAR 52.211-10 in Section F of the solicitation/contract.
1. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 20-calendar days for review of drawings or data submitted for approval.
2. COMMENCEMENT OF CONTROL WORK: Do not perform any outdoor equipment wiring until receipt of Government-furnished wiring diagrams. WAPA will furnish outdoor wiring and schematic diagrams no sooner than October 30, 2022. Include these restrictions ...
3. OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:
4. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:
5. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General Requirements”, Section 1.4.14.3(1).
6. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the f...
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME: Prepare and submit a Construction Schedule to the Contracting Officer (CO) within 10-calendar days after date of Notice to Proceed.
2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.
F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:
1. POINTS-OF-DELIVERY: Material furnished by WAPA will be delivered to Yellowtail Switchyard. The power circuit breakers will be unloaded by the supplier. The Contractor shall inspect the power circuit breakers and report any damage to the COR.
G. RIGHTS-OF-WAY:
1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired by the Contractor shall have prior CO...
H. GEOLOGIC INVESTIGATIONS:
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
J. WATER FOR CONSTRUCTION PURPOSES:
K. EXPLOSIVES AND BLASTING:
L. BURIED UTILITIES:
M. ELECTRICAL MINIMUM APPROACH DISTANCES:
N. SUBMITTALS AND CORRESPONDENCE:
1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements:
2. TRANSMITTAL: The Contractor shall submit all correspondence (Request for Information, Submittals, etc.) to the following email address care of the COR.
3. SUBMITTAL RESPONSE: WAPA will provide a response to all submittals in accordance with Division 1.D.2 of these specifications with an “Acceptable” or “Not Acceptable” status, with comments as appropriate to the email address where the submittals or...
4. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e., brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlini...
5. PROJECT PROTOCOL:
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Part B Bidding Schedule item “Miscellaneous sitework” includes the following:
2. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.
DIVISION 3 – CONCRETE
A. GENERAL:
1. MATERIAL:
2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: All fine and coarse aggregates shall be tested in accordance with Standard 3. If the tests determine the aggregate(s) to be unsuitable as a concrete aggregate, a suitable source shall be...
3. MIX DESIGN: Provide a performance based concrete mix design in accordance with ACI 211.1 and Table 3.1 below.
4. REBAR DEVELOPMENT (LD) AND LAP LENGTH:
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Part B Bidding Schedule item “Concrete foundations” includes the following:
DIVISION 9 - SUBSTATION ELECTRICAL
A. GENERAL:
1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:
2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the Contractor and shall include the following:
3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel. Instrument transformers that are seismically qualified shall ...
4. Installation and painting of electrical equipment and material shall be provided in accordance with Standards 9 and 12 respectively.
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Power circuit breaker, 115-kV, 3,000 amp (Government-furnished)” includes furnishing equipment and material not furnished by WAPA and installing the following Government-furnished power circuit breakers:
2. Bidding Schedule item "Associated electrical equipment and material" includes providing equipment, material and services required to complete the following substation installations as shown on the Drawings:
3. Bidding Schedule item “Existing outdoor electrical equipment and material” includes removing and disposing of existing outdoor electrical equipment and material.
DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
DIVISION 15 – DRAWINGS
A. CONSTRUCTION DRAWINGS:
1. GENERAL: After award of contract, WAPA will provide the Contractor an electronic copy of all suitable for construction drawings. (No hard copies will be provided).
B. AS-BUILT DRAWINGS:
1. GENERAL: The Contractor shall keep one (1) complete set of full-size construction drawings at the jobsite solely for the purpose of recording as-built conditions. The Drawings shall be marked to show any change or variation in the actual construc...
2. RECORDING INFORMATION: Record information on the Drawings concurrently with construction progress. Do not conceal work until the required information is recorded. Mark all drawings affected by the actual work which varies from the construction d...
3. DRAWING MARKUP: As-built drawing marking shall be as follows:
4. DRAWING REVIEW: The marked set of as-built drawings shall be kept onsite and available for inspection at all times.
5. AS-BUILT INFORMATION TO BE RECORDED: Mark drawings with all actual construction which does not match the construction drawings including:
C. REVIEW OF AS-BUILT DRAWINGS:
1. AS BUILT DRAWING SUBMITTAL: Upon completion of the project, the Contractor shall electronically submit a complete set of marked as-built drawings to the COR for approval prior to the date of submission of your final invoice. Drawings that require...
2. REVIEW: The COR will perform a review of the as-built drawing submittal which may include a site walkdown to compare as-built information against physical installation. The COR will identify any issues that need to be resolved prior to acceptance...
3. ACCEPTANCE: Upon acceptance, the Contractor shall invoice for any outstanding cost retained by WAPA as described by Section H of the contract clauses.