2026057 Pay Item Worksheet.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- Pavement Marking Continuing Services
- Solicitation number
- IFB 360 2026057 1
- Issued by
- Palm Beach County, Florida
About this file
This is a Pay Item Worksheet for PBC Project #2026057, a Pavement Marking Continuing Services construction contract in Florida. The project encompasses six lots of pavement marking materials and services organized by type: thermoplastic pavement marking lines in various colors and widths (Lot 1), raised reflective pavement markers in amber, white, and red (Lot 2), paint traffic lines in multiple colors and configurations (Lot 3), pavement marking removal services (Lot 4), preformed cold plastic markings (Lot 5), and miscellaneous items including rumble strips, contrast tape, flexible delineators, and foil back tape (Lot 6). The worksheet itemizes 74 pay items with specified quantities in units such as linear feet, square yards, gallons, each, and nautical miles. The scope includes furnishing and installation of all materials, with maintenance of traffic and mobilization costs considered incidental to unit prices.
The Pay Item Worksheet requires bidders to submit unit prices for each pay item, with the total bid calculated by multiplying unit prices by quantities; however, all price fields currently display zero values, indicating this is a blank proposal form awaiting bidder input. All costs for preliminary striping layout, maintenance of traffic, and mobilization are to be included in the unit prices. For reflective pavement marker installation, epoxy is required for concrete surfaces while thermoplastic and bituminous materials are required for asphalt surfaces, with these costs considered incidental to the marker line items. FDOT item numbers are provided for determining eligibility for price adjustment purposes only. The worksheet explicitly notes that item descriptions and quantities in the worksheet shall govern over any conflicting information in the construction plans, and pay item footnotes included in the construction plans are also incorporated into the unit prices.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2026057 Spec.pdf | ||
| Alternate Format Availability.pdf | ||
| RFI Form.docx | DOCX document | |
| Qualifications and Experience Package Form.pdf | ||
| OSBD Schedules and Instructions.pdf | ||
| RFI Form.pdf | ||
| Qualifications and Experience Package Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026057 Proposal Form
| BID PROPOSAL | ||||||
| PAVEMENT MARKING CONTINUING SERVICES CONSTRUCTION | ||||||
| CONTRACT | ||||||
| PBC PROJECT #2026057 | ||||||
| # | FDOT ITEM NUMBER | ITEM DESCRIPTION | QTY | UNITS | UNIT PRICE | AMOUNT |
| LOT 1 - Thermoplastic | ||||||
| Thermoplastic Pavement Marking Lines - Colors & Widths as Indicated | ||||||
| 1 | 711-11-101 | White, 6" | 360 | NM | $ - 0 | |
| 2 | 711-11-201 | Yellow, 6" | 240 | NM | $ - 0 | |
| 3 | 711-11-102 | White, 8" | 24 | NM | $ - 0 | |
| 4 | 711-11-202 | Yellow, 8" | 24,000 | LF | $ - 0 | |
| 5 | 711-11-103 | White, 12" | 19,200 | LF | $ - 0 | |
| 6 | 711-11-104 | White, 18" | 14,400 | LF | $ - 0 | |
| 7 | 711-11-204 | Yellow, 18" | 19,200 | LF | $ - 0 | |
| 8 | 711-11-105 | White, 24" | 24,000 | LF | $ - 0 | |
| 9 | 711-11-141 | White, 6" (2 x 4 Skip) | 120 | GM | $ - 0 | |
| 10 | 711-11-241 | Yellow, 6" (2 x 4 Skip) | 24 | GM | $ - 0 | |
| 11 | 711-11-141 | White, 6" (6 x 10 Skip) | 24 | GM | $ - 0 | |
| 12 | 711-11-241 | Yellow, 6" (6 x 10 Skip) | 26 | GM | $ - 0 | |
| 13 | 711-11-131 | White, 6" (10 x 30 Skip) | 14 | GM | $ - 0 | |
| 14 | 711-11-231 | Yellow, 6" (10 x 30 Skip) | 14 | GM | $ - 0 | |
| 15 | 920-711-2 | Green, Bike Lane Marking, Pre-formed | 1,600 | SY | $ - 0 | |
| Arrows & Messages; as Indicated; White Only | ||||||
| 16 | 711-11-17 | Turn Arrow | 24,000 | EA | $ - 0 | |
| 17 | 711-11-17 | Straight Arrow | 7,200 | EA | $ - 0 | |
| 18 | 711-11-17 | Straight/Turn Arrows; Combination | 4,800 | EA | $ - 0 | |
| 19 | 711-11 | Yield Triangles | 450 | EA | $ - 0 | |
| 20 | 711-11-16 | MERGE Message | 3,600 | EA | $ - 0 | |
| 21 | 711-11-16 | RXR Message | 2,280 | EA | $ - 0 | |
| 22 | 711-11-16 | SCHOOL Message | 4,800 | EA | $ - 0 | |
| 23 | 711-11-16 | ONLY Message | 2,880 | EA | $ - 0 | |
| 24 | 711-11-16 | U-TURN Message | 1,200 | EA | $ - 0 | |
| 25 | 711-11-16 | HANDICAP Message | 600 | EA | $ - 0 | |
| 26 | 711-11-16 | YIELD Message | 150 | EA | $ - 0 | |
| 27 | 711-11 | Bike Lane Symbol with Arrow | 3,600 | EA | $ - 0 | |
| 28 | 711-11-16 | DO NOT BLOCK Message | 250 | EA | $ - 0 | |
| 29 | 711-11-16 | BUS Message | 200 | EA | $ - 0 | |
| 30 | 711-11-16 | SOUTH Message | 500 | EA | $ - 0 | |
| 31 | 711-11-16 | NORTH Message | 500 | EA | $ - 0 | |
| 32 | 711-11-16 | STOP Message | 350 | EA | $ - 0 | |
| 33 | 711-11-16 | RAMP Message | 1,400 | EA | $ - 0 | |
| SUBTOTAL (LOT 1) | $ - 0 | |||||
| LOT 2 - Raised Reflective Pavement Markers (see footnotes for application) - Colors & Types as Indicated | ||||||
| 34 | 706-1-3 | Amber; Bi-Directional | 72,000 | EA | $ - 0 | |
| 35 | 706-1-3 | White & Red; Bi-Directional | 48,000 | EA | $ - 0 | |
| 36 | 706-1-3 | Amber & Red; Bi-Directional | 52,000 | EA | $ - 0 | |
| SUBTOTAL (LOT 2) | $ - 0 | |||||
| LOT 3 - Paint | ||||||
| Traffic Paint Lines - Colors, Types, and Widths as Indicated | ||||||
| 37 | 710-90 | White, 4" | 1,440 | LF | $ - 0 | |
| 38 | 710-90 | Yellow, 4" | 1,440 | LF | $ - 0 | |
| 39 | 710-90 | White, 6" | 144 | NM | $ - 0 | |
| 40 | 710-90 | Blue, 6" | 2,880 | LF | $ - 0 | |
| 41 | 710-90 | Black, 6" | 72,000 | LF | $ - 0 | |
| 42 | 710-90 | Yellow, 6" | 72 | NM | $ - 0 | |
| 43 | 710-90 | White, 8" | 1,440 | LF | $ - 0 | |
| 44 | 710-90 | Yellow, 8" | 23,040 | LF | $ - 0 | |
| 45 | 710-90 | White, 12" | 13,920 | LF | $ - 0 | |
| 46 | 710-90 | White, 18" | 6,624 | LF | $ - 0 | |
| 47 | 710-90 | Yellow, 18" | 3,600 | LF | $ - 0 | |
| 48 | 710-90 | White, 24" | 12,960 | LF | $ - 0 | |
| 49 | 710-90 | White, 6" (2 x 4 Skip) | 5 | GM | $ - 0 | |
| 50 | 710-90 | Yellow, 6" (2 x 4 Skip) | 0.25 | GM | $ - 0 | |
| 51 | 710-90 | White, 6" (6 x 10 Skip) | 3.60 | GM | $ - 0 | |
| 52 | 710-90 | Yellow, 6" (6 x 10 Skip) | 0.25 | GM | $ - 0 | |
| 53 | 710-90 | White, 6" (10 x 30 Skip) | 48 | GM | $ - 0 | |
| 54 | 710-90 | Yellow, 6" (10 x 30 Skip) | 48 | GM | $ - 0 | |
| 55 | 710-90 | Reflective Paint - Island Nose - Yellow | 24 | SY | $ - 0 | |
| Arrows & Messages: White | ||||||
| 56 | 710-90 | Turn Arrow | 1,056 | EA | $ - 0 | |
| 57 | 710-90 | Straight/Combination Arrow | 528 | EA | $ - 0 | |
| 58 | 710-90 | Message (ONLY; SCHOOL; MERGE; YIELD & Straight Arrow) | 750 | EA | $ - 0 | |
| SUBTOTAL (LOT 3) | $ - 0 | |||||
| LOT 4 - Pavement Marking Removal | ||||||
| 59 | N/A | Traffic Paint | 2,880 | SF | $ - 0 | |
| 60 | 711-17 | Thermoplastic | 24,000 | SF | $ - 0 | |
| 61 | N/A | Cold Plastic (Preformed) | 14,400 | LF | $ - 0 | |
| 62 | 713-17 | Construction Tape | 96,000 | LF | $ - 0 | |
| 63 | N/A | Pavement Markers | 21,888 | EA | $ - 0 | |
| SUBTOTAL (LOT 4) | $ - 0 | |||||
| LOT 5 - Preformed Cold Plastic | ||||||
| 64 | N/A | White or Yellow, 6" | 5,760 | LF | $ - 0 | |
| 65 | N/A | White, 8" | 1,440 | LF | $ - 0 | |
| 66 | N/A | White or Yellow, 12" | 288 | LF | $ - 0 | |
| 67 | N/A | White or Yellow, 18" | 288 | LF | $ - 0 | |
| 68 | N/A | White, 24" | 288 | LF | $ - 0 | |
| 69 | N/A | Message, White (ONLY; SCHOOL; MERGE; U-TURN; YIELD; Bike Lane Symbol w/Arrow) | 150 | EA | $ - 0 | |
| 70 | N/A | Turn Arrow, White | 132 | EA | $ - 0 | |
| SUBTOTAL (LOT 5) | $ - 0 | |||||
| LOT 6 - Miscellaneous | ||||||
| 71 | 701-1 | Thermoplastic Rumble Strips (Index 518) | 950 | EA | $ - 0 | |
| 72 | N/A | 9" Contrast Tape | 6,500 | LF | $ - 0 | |
| 73 | 705-11 | Flexible Delineators (All Types) | 10,500 | EA | $ - 0 | |
| 74 | N/A | Foil Back Tape | 25,680 | LF | $ - 0 | |
| SUBTOTAL (LOT 6) | $ - 0 | |||||
| TOTAL BID | $ - 0 |
| THE COUNTY DOES NOT GUARANTEE THE ACCURACY OF THE FORMULAS AND EXTENSIONS USED IN THIS SPREADSHEET. | |
| THE ITEMS AND QUANTITIES ABOVE, SHALL GOVERN OVER THE PLANS. | |
| PAY ITEM FOOTNOTES IN CONSTRUCTION PLANS SHALL ALSO BE INCLUDED IN ITEM UNIT PRICE. | |
| Note # | PAY ITEM FOOTNOTES |
| 1 | All costs for Maintenance of Traffic (MOT) and mobilization shall be considered incidental to, and shall be included in, unit prices for the pay items. |
| 2 | All items shall include cost to furnish and install unless otherwise noted. |
| 3 | FDOT Item numbers are for use in determining eligibility for price adjustment per General Provision 9-2 only. |
| 4 | Epoxy required to install RPM's on concrete, and Thermoplastic and bituminous required to install RPM's on asphalt, are incidental to the Reflective Pavement marker line items. |
| 5 | Preliminary layout of striping locations shall be considered incidental to, and shall be included in, unit prices for the pay items. |
| 6 | All items shall include cost to furnish an install. |
| 7 | Linear Foot (LF) units are net lengths. |
&"Times New Roman,Bold"&14PROPOSAL FORM
&"Times New Roman,Bold"&14P-&P
File details come from the government source that posted it. Updated .