About this file

This is a proposal and contract forms document for Pierce County Planning & Public Works in Washington, regarding the replacement of Bridge #PRT27195-E located on the Foothills Trail near Ski Park. The project involves the construction of a 200-foot long, two-span precast concrete girder bridge to replace the existing structure, along with associated work including clearing and grubbing, grading, replanting, erosion control, and construction of a mitigation channel connecting an unnamed stream to an adjacent wetland. The bid opening is scheduled for Wednesday, August 26, 2026, at 1:00 p.m. The proposal includes 50 line items covering preparation, grading, drainage, structure, surfacing, hot mix asphalt, erosion control, roadside planting, traffic management, and miscellaneous work. Key quantities include 140 cubic yards of roadway excavation, 148 linear feet of 5-foot diameter shaft construction, 65 tons of hot mix asphalt, 720 square yards of seeding and fertilizing, and various plantings including 21 Western Red Cedar trees, 87 Sitka Spruce trees, and over 1,000 additional native plants and plugs for habitat restoration.

Bidders must submit a proposal guaranty equivalent to five percent of the total bid amount in the form of cash, cashier's check, certified check, or proposal bond payable to Pierce County. The contract requires compliance with prevailing wage requirements and includes certifications regarding nonsegregated facilities, non-collusion and debarment status, and wage law compliance. Bidders must submit a local agency subcontractor list identifying any direct subcontractors for structural steel, rebar, HVAC, plumbing, and electrical work as required by RCW 39.30.060. The proposal form requires the contractor's license number, UBI number, industrial insurance account number, excise tax number, and employment security account number. Bidders are permitted to propose recycled materials percentages for construction aggregate and concrete, though this does not affect award determination unless bids are tied. The document indicates that addenda may be issued prior to bid opening, which must be acknowledged by the bidder at the time of proposal submission.

View the file

Other files

File Type Posted
2026-MPW-171_-_Contract.pdf PDF
2026-MPW-171_-_ConstructionPlans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPOSAL AND CONTRACT FORMS

FOR

BRIDGE# PRT27195-E

FOOTHILLS TRAIL / SKI PARK (FORESTED DRAINAGE)

P-111399

BID OPENING DATE:

Date: WEDNESDAY, AUGUST 26, 2026 Bid Delivery Time: 1:00 p.m.

Bid Opening Time: 1:00 p.m., or as soon thereafter as possible.

PROPOSAL

TO THE PIERCE COUNTY DIRECTOR OF PLANNING & PUBLIC WORKS

TACOMA, WASHINGTON

This certifies that the undersigned has examined the location of

ITEM ITEM DESCRIPTION

NO. at $ . ct $ . ct

PREPARATION

1 Mobilization at .

2 Clearing and Grubbing at .

3 25,000$ DOLLAR Removing Shaft Obstructions at 1 . 00 per EST 25,000$ . 00

4 Removing Existing Bridge NO. PRT27195-E at .

GRADING

5 Roadway Excavation Incl. Haul at . per C.Y. .

6 Embankment Compaction at . per C.Y. .

DRAINAGE

7 Channel Excavation Incl. Haul at . per C.Y. .

8 Temporary Stream Diversion at .

9 Fish Exclusion at .

STRUCTURE

10 Structure Excavation Class A. Incl. Haul at . per C.Y. .

11 Shoring or Extra Excavation Cl. A at .

12 Gravel Backfill for Wall at . per C.Y. .

13 Constructing 5 FT. Diam Shaft at . per L.F. .

14 St. Reinf. Bar for Substructure at . per L.B. .

LUMP SUM L.S. LUMP SUM

10197 L.B.

LUMP SUM LUMP SUM

LUMP SUM LUMP SUM

10 C.Y.

55 C.Y.

100 C.Y.

BRIDGE #PRT27195-E

FOOTHILLS TRAIL / SKI PARK (FORESTED DRAINAGE)

P-111399

QUANTITY UNIT PRICE UNIT TOTAL AMOUNT

LUMP SUM

LUMP SUM LUMP SUM

140 C.Y.

LUMP SUM

LUMP SUM LUMP SUM

40 C.Y.

148 L.F.

L.S.

L.S.

L.S.

L.S.

L.S.

and that the plans, specifications and contract governing the work embraced in this improvement, and the method by which payment will be made for said work is understood. The undersigned hereby proposes to undertake and complete the work embraced in this improvement, or as much thereof as can be completed with the material available in accordance with the said plans, specifications and contract, and the following schedule of rates and prices.

Note: Unit price(s) for all item(s), all extensions, and total amount of bid shall be shown. All entries must be typed or entered in ink.

Show price per unit in figures only. Figures written to the right of the dot (decimal) in the price per unit column shall be interpreted as cents.

P-111399 Proposal.xlsx

P 1 7/23/2026

ITEM ITEM DESCRIPTIONQUANTITY UNIT PRICE UNIT TOTAL AMOUNT

15 Conc. Class 4000 for Substructure at . per C.Y. .

16 QA Shaft Test at . per EACH .

17 Superstructure No. PRT27195-E at .

Expansion Joint System Compression Seal - Superstr. at . per L.F. .

19 Waterproof Membrane BR. No. PRT27195-E at . per S.Y. .

20 Bridge Railing at . per L.F. .

21 Precast Conc. Curb at . per L.F. .

SURFACING

22 Crushed Surfacing Base Course at . per TON .

HOT MIX ASPHALT

23 HMA Joint Seal at Bridge End at . per L.F. .

24 HMA CL. 1/2 in. PG 58H-22 at . per TON .

25 ESC Lead at . per DAY .

26 Stabilized Construction Entrance at . per S.Y. .

27 Silt Fence at . per L.F. .

28 5,000$ DOLLAR Erosion/Water Pollution Control at 1 . 00 per EST 5,000$ . 00

29 Seeding and Fertilizing by Hand at . per S.Y. .

30 Topsoil Type A at . per S.Y. .

31 PSIPE Western Red Cedar (THUJA PLICATA) 2 GAL. at . per EACH .

32 PSIPE Sitka Spruce (PICEA SITCHENSIS) 2 GAL. at . per EACH .

33 PSIPE Salmonberry (RUBUS SPECTABILIS) 1 GAL. at . per EACH .

34 PSIPE Red Osier Dogwood (CORNUS SERICEA) 1 GAL. at . per EACH .

35 PSIPE Pacific Willow (SALIX LASIANDRA) 1 GAL. at . per EACH .

36 PSIPE Slough Sledge (CAREX OBNUPTA) PLUG at . per EACH .

37 Bark or Wood Chip Mulch Rings at . per EACH .

15 TON

63 L.F.

65 TON

EROSION CONTROL AND ROADSIDE

PLANTING

20 DAY

45 C.Y.

3 EACH

LUMP SUM LUMP SUM

720 S.Y.

650 L.F

39 L.F.

277 S.Y.

410 L.F.

410 L.F.

21 EACH

87 EACH

87 EACH

100 S.Y.

150 S.Y.

21 EACH

87 EACH

1044 EACH

303 EACH

L.S.

Show price per unit in figures only. Figures written to the right of the dot (decimal) in the price per unit column shall be interpreted as cents.

P 2 7/23/2026

ITEM ITEM DESCRIPTIONQUANTITY UNIT PRICE UNIT TOTAL AMOUNT

38 Straw Mulch at . per S.Y. .

TRAFFIC

39 Permanent Signing at .

40 Project Temporary Traffic Control at .

41 1,250$ DOLLAR Work Zone Safety Contingency at 1 . 00 per EST 1,250$ . 00

OTHER ITEMS

42 Utility Coordination at .

43 Structure Surveying at .

44 Roadway Surveying at .

45 Gravity Block Wall at .

46 Trimming and Cleanup at .

47 5,000$ DOLLAR Reimbursement for Third Party Damage at 1 . 00 per EST 5,000$ . 00

48 5,000$ DOLLAR Minor Change at 1 . 00 per EST 5,000$ . 00

49 SPCC PLAN at .

50 FDC PLAN at .

Contract Total $ .

LUMP SUM L.S. LUMP SUM

LUMP SUM L.S. LUMP SUM

LUMP SUM

LUMP SUM

LUMP SUM

LUMP SUM

LUMP SUM

LUMP SUM

LUMP SUM

LUMP SUM L.S. LUMP SUM

LUMP SUM

LUMP SUM

LUMP SUM

LUMP SUM

1200 S.Y.

LUMP SUM

L.S.

L.S.

L.S.

L.S.

L.S.

L.S.

Show price per unit in figures only. Figures written to the right of the dot (decimal) in the price per unit column shall be interpreted as cents.

P 3 7/23/2026

Bridge# PRT27195-E Foothills Trail / Ski Park (Forested Drainage) P-111399 _25WORD.SPC\_P-111399 Local Pack.docx P 4 7/7/26

Proposal--Continued

The bidder is hereby advised that by signature of this proposal he/she is deemed to have acknowledged all requirements and signed all certificates contained herein.

The undersigned hereby agrees to pay not less than the prevailing rates of wages in accordance with the requirements of the special provisions for this project.

A proposal guaranty in an amount of five percent (5%) of the total bid, based upon the approximate estimate of quantities at the above prices and in the form as indicated below, is attached hereto:

CASH IN THE AMOUNT OF

CASHIER’S CHECK

CERTIFIED CHECK ($_________) PAYABLE TO PIERCE COUNTY

PROPOSAL BOND TREASURER IN THE AMOUNT OF 5% OF THE BID

Receipt is hereby acknowledged of addendum(s) No.(s) _____, _____, and _____.

PROPOSAL MUST BE SIGNED

SIGNATURE OF AUTHORIZED OFFICIAL(S)

By: By:

(Print Name) (Print Name)

FIRM NAME

ADDRESS

Street City State Zip

PHONE FAX E-MAIL

The following information is required per RCW 39.04.350

Contractor’s License No. Contractor’s UBI No.

Industrial Insurance Account No. Excise Tax No.

Employment Security Account No.

Signed and sworn to (or affirmed) before me this day of , 20____.

Notary Public in and for the State of Washington

Residing at My Appointment Expires

Note: (1) This proposal form is not transferable, and any alteration of the firm’s name entered hereon without prior permission from the County will be cause for considering the proposal irregular and subsequent rejection of the bid.

(2) Please refer to Section 1-02.6 of the Standard Specifications, re: “Preparation of Proposal.”

P-111399 _25WORD.SPC\_P-111399 Local Pack.docx P 5 7/7/26

PIERCE COUNTY PLANNING & PUBLIC WORKS

PROPOSAL BOND

KNOW ALL MEN BY THESE PRESENTS, That we of as principal, and the a corporation duly organized under the laws of the State of and authorized to do business in the State of Washington, as surety, are held and firmly bound unto Pierce County, State of Washington, in the full and penal sum of five (5) percent of the total amount of the bid proposal of said principal for the work hereinafter described, pursuant to and in compliance with the provisions of RCW 36.77.030, for the payment of which, well and truly to be made, we bind our heirs, executors, administrators and assigns, and successors and assigns, firmly by these presents.

The conditions of this bond are such, that whereas the principal herein is hereby submitting his/her or its sealed proposal for the following public works construction, to wit:

said bid and proposal, by reference thereto, being made a part hereof.

NOW, THEREFORE, if said proposal bid by said principal be accepted, and the contract be awarded to said principal, said principal shall duly make and enter into and execute said contract and shall furnish bond as required by RCW 36.77.040 within ten (10) days after notice of the award, exclusive of the day of notice, then this obligation shall be null and void, otherwise it shall remain and be in full force and effect.

IN TESTIMONY WHEREOF, the principal and the surety have caused these presents to be signed and sealed this __________________ day of __________________________, 20___.

Principal

Surety

Attorney-in-fact

P 6

Local Agency Subcontractor List Prepared in compliance with RCW 39.30.060 as amended.

To Be Submitted with the Bid Proposal Project Name ____________________________________________________________________________________________

Failure to list subcontractors with whom the bidder, if awarded the contract, will directly subcontract for performance of the work of structural steel installation, rebar installation, heating, ventilation and air conditioning, plumbing, as described in Chapter 18.106 RCW, and electrical, as described in Chapter 19.28 RCW or naming more than one subcontractor to perform the same work will result in your bid being non-responsive and therefore void.

Subcontractor(s) with whom the bidder will directly subcontract that are proposed to perform the work of structural steel installation, rebar installation, heating, ventilation and air conditioning, plumbing, as described in Chapter 18.106 RCW, and electrical as described in Chapter 19.28 RCW must be listed below. The work to be performed is to be listed below the subcontractor(s) name.

If RCW 39.30.060 requires a proof of license, the license number of that Subcontractor is required. To the extent the Project includes one or more categories of work referenced in RCW 39.30.060, and no subcontractor is listed below to perform such work, the bidder certifies that the work will either (i) be performed by the bidder itself, or (ii) be performed by a lower tier subcontractor who will not contract directly with the bidder.

Subcontractor Name ____________________________________________________________________________________ (and License Number if required)

Work to be performed ____________________________________________________________________________________

Subcontractor Name ____________________________________________________________________________________ (and License Number if required)

Work to be performed ____________________________________________________________________________________

Subcontractor Name ____________________________________________________________________________________ (and License Number if required)

Work to be performed ____________________________________________________________________________________

Subcontractor Name ____________________________________________________________________________________ (and License Number if required)

Work to be performed ____________________________________________________________________________________

Subcontractor Name ____________________________________________________________________________________ (and License Number if required)

Work to be performed ____________________________________________________________________________________

*Bidders are notified that it is the opinion of the enforcement agency that PVC or metal conduit, junction boxes, etc., are considered electrical equipment and therefore considered part of electrical work, even if the installation is for future use and no wiring or electrical current is connected during the project.

Tacoma Mall Plaza 2702 South 42nd Street Suite 109 Tacoma, WA 98409

Pierce County Planning & Public Works

P-111399 _25WORD.SPC\_P-111399 Local Pack.docx P 7 7/7/2026

CERTIFICATION OF NONSEGREGATED FACILITIES

The contractor certifies that no segregated facilities are maintained and will not be maintained during the execution of this contract at any of contractor’s establishments.

The contractor further certifies that none of the contractor’s employees are permitted to perform their services at any location under the contractor’s control during the life of this contract where segregated facilities are maintained. The contractor certifies further segregated facilities will not be maintained or provided for employees at any of the contractor’s establishments, and that employees will not be permitted to perform their services at any location, under the contractor’s control, where segregated facilities are maintained.

The contractor agrees that a breach of this certification is a violation of the Equal Opportunity clause in this contract. As used in this certification, the term “segregated facilities” means any waiting rooms, work area, rest rooms and wash rooms, restaurants and other eating areas, time clocks, locker rooms and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing facilities provided for employees which are segregated by explicit directive or are in fact segregated on the basis of race, creed, color or national origin, because of habit, local custom, or otherwise.

The contractor agrees that identical certifications from proposed contractors will be obtained prior to the award of any subcontracts. Contractor will retain a copy of any subcontractor’s certification and will send original to Contract Compliance Division.

NON-COLLUSION AND DEBARMENT AFFIDAVIT

State of Washington, County of

As an authorized representative of the firm of , I do hereby certify that said person(s), firm, association or corporation has (have) not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with the project for which this proposal is submitted.

I further certify that, except as noted below, the firm, association or corporation or any person in a controlling capacity associated therewith or any position involving the administration of federal funds; is not currently under suspension, debarment, voluntary exclusion, or determination of eligibility by any federal agency; has not been suspended, debarred, voluntarily excluded or determined ineligible by any federal agency within the past three (3) years; does not have a proposed debarment pending; and has not been indicted, convicted or had a civil judgment rendered against said person, firm, association or corporation by a court of competent jurisdiction in any matter involving fraud or official misconduct within the past three years.

I further acknowledge that by signing the signature page of the proposal, I am deemed to have signed and have agreed to the provisions of this affidavit.

Note: Exceptions will not necessarily result in denial of award but will be considered in determining bidder responsibility. For any exception noted, indicate above to whom it applies, initiating agency, and dates of action. Providing false information may result in criminal prosecution or administrative sanctions.

“A suspending or debarring official may grant an exception permitting a debarred, suspended, or excluded person to participate in a particular transaction upon a written determination by such official stating the reason(s) for deviating from the Presidential policy established by Executive Order 12549...” (49CFR Part 29 Section 29.215).

P-111399 _25WORD.SPC\_P-111399 Local Pack.docx P 8 7/7/2026

Proposal for Incorporating Recycled Materials into the Project

In compliance with a new law that went into effect January 1, 2016 (SHB1695), the Bidder shall propose below, the total percent of construction aggregate and concrete materials to be incorporated into the Project that are recycled materials. Calculated percentages must be within the amounts allowed in Section 9-03.21(1)F, Table on Maximum Allowable Percent (By Weight) of Recycled Material, of the Standard Specifications.

Proposed total percentage: _____________________________ percent.

Note: Use of recycled materials is highly encouraged within the limits shown above, but does not constitute a Bidder Preference, and will not affect the determination of award, unless two or more lowest responsive Bid totals are exactly equal, in which case proposed recycling percentages will be used as a tiebreaker, per the APWA GSP in Section 1-02.6 of the Special Provisions. Regardless, the Bidder’s stated proposed percentages will become a goal the Contractor should do its best to accomplish. Bidders will be required to report on recycled materials actually incorporated into the Project, in accordance with the APWA GSP in Section 1-06.6 of the Special Provisions.

Bidder Name:

Signature of Authorized Official:

Date:

P-111399 _25WORD.SPC\_P-111399 Local Pack.docx P 9 7/7/2026

CONTRACTOR CERTIFICATION WAGE LAW COMPLIANCE

The bidder hereby certifies that, within the three-year period immediately preceding the bid solicitation date (August 26, 2026), the bidder is not a “willful” violator, as defined in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction.

I declare under penalty of perjury under the laws of the State of Washington that the foregoing is true and correct.

Bidder’s Business Name

Signature of Authorized Official*

Printed Name

Title

Date City State

Check One:

Sole Proprietorship ☐ Partnership ☐ Joint Venture ☐ Corporation ☐

State of Incorporation, or if not a corporation, State where business entity was formed:

If a co-partnership, give firm name under which business is transacted:

* If a corporation, proposal must be executed in the corporate name by the president or vice-president (or any other corporate officer accompanied by evidence of authority to sign). If a co-partnership, proposal must be executed by a partner.

File details come from the government source that posted it. Updated .