Lee County Utilities Technical Specifications Summary
This document is a comprehensive technical specifications manual prepared by Lee County Utilities for water and wastewater infrastructure projects, establishing standards for construction, materials, equipment, and installation procedures across multiple engineering disciplines. The specifications cover general requirements, concrete work, structural metals, finishes, plumbing, and electrical systems, with detailed guidelines for surface preparation, quality assurance, testing protocols, and operational procedures. The manual encompasses divisions addressing demolition, lead abatement, concrete formwork and reinforcement, precast structures, metal fabrication, painting and coating systems, submersible pump installations, basic electrical materials and methods, low-voltage wiring and cables, grounding and bonding systems, conduit installations, underground ductbanks, equipment identification, wiring devices, short-circuit coordination studies with arc-flash analysis, acceptance testing and performance verification, transformers, panelboards, motors, electrical service connections, circuit breakers, and control panel fabrication. The document references numerous industry standards including NEC (National Electrical Code), NEMA, ASTM, IEEE, ANSI, OSHA, AWWA, and Florida Department of Environmental Protection regulations, with submission requirements for shop drawings, test reports, operation and maintenance manuals, and record documents submitted throughout construction phases. Bidders' meetings, site inspections, and coordination with the Engineer of Record (designated as Bowman Consulting Group, Ltd. in the related Arthrex Shovel Ready Project) are integral to project execution, with substantial completion targeted for July 30, 2027, and final completion by September 17, 2027.
Pricing structures are established through unit pricing for measured quantities and lump-sum compensation for general conditions, with all costs including labor, materials, equipment, and ancillary expenses subject to field adjustments by the Authority. The specifications mandate compliance with Lee County Utilities' approved materials lists for potable water and wastewater infrastructure and FDOT Standard Specifications for Fiscal Year 2025-26, with particular emphasis on corrosion-resistant materials for exterior installations, NSF-61 certification for potable water contact materials, and comprehensive testing and inspection protocols including thermographic surveys, insulation resistance testing, and acceptance testing performed by certified independent firms. Funding sources derive from FAA Airport Improvement Program grants requiring Buy American preferences and Davis-Bacon prevailing wage compliance, with DBE (Disadvantaged Business Enterprise) participation targets established per federal requirements. Contractors must maintain performance and payment bonds equal to 100 percent of contract value, comprehensive insurance coverage including general liability of $1,000,000 per occurrence and pollution/professional liability of $2,000,000 per occurrence, and AOA (Airport Operations Area) security clearance compliance with TSA regulations. Liquidated damages of $1,500 per calendar day apply for delays beyond the final completion date, and the contractor must comply with all South Florida Water Management District Environmental Resource Permit conditions while adhering to specified warranties, typically ranging from one to five years depending on equipment and system components.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REV: 04/2019 Section 00003
TABLE OF CONTENTS
LEE COUNTY UTILITIES
WATER AND WASTEWATER TECHNICAL SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS SECTION
Summary of Work 01 11 00 Measurement and Payment 01 22 13 Change Order and Field Directive 01 26 00 Project Coordination 01 31 13 Project Meetings 01 31 19 Progress Schedule (Simple) 01 32 16 Progress Schedule (Complex) 01 32 17 Submittals 01 33 00 Reference Standards 01 42 00 Abbreviations 01 42 13 Quality Control 01 43 00 Traffic Regulation 01 55 26 Construction Facilities and Temporary Controls 01 57 00 Material and Equipment 01 61 00 Cutting and Patching 01 73 29 Cleaning 01 74 00 Contract Close Out 01 77 00 Operation and Maintenance Manuals 01 78 23 Warranties and Bonds 01 78 36 Training 01 79 00
DIVISION 2 – EXISTING CONDITIONS
Lines and Grades 02 21 13 Demolition 02 40 00 Lead Abatement 02 83 00
DIVISION 3 – CONCRETE
Concrete Formwork 03 11 00 Concrete Accessories 03 15 00 Concrete Reinforcement 03 20 00 Cast-in-Place Concrete for Plant Work 03 30 00 Concrete for Non-Plant Work 03 30 53 Precast Concrete Structures 03 40 00
DIVISION 5 – METALS
Galvanizing 05 50 01 Metal Stairs, Ladders and Walkways 05 51 00 Aluminum Handrails and Railings 05 52 00 Metal Grating, Trench Covers and Floor Plates 05 53 00 Metal Castings 05 56 00
DIVISION 9 – FINISHES
Painting and Coating 09 90 00 IET Coating System 09 96 35
DIVISION 22 – PLUMBING
Submersible Sewage Pumps 22 13 29
DIVISION 26 – ELECTRICAL
Basic Electrical Materials & Methods 26 05 02 Special Electrical Requirements 26 05 11 Low Voltage Wires & Cables 26 05 19 Grounding & Bonding for Electrical Systems 26 05 26 Hangers and Supports for Electrical Systems 26 05 29 Conduit Systems 26 05 33 Underground Ducts and Ductbanks 26 05 43 Identification of Electrical Systems 26 05 53 Wiring Devices 26 05 70 Short Circuit & Coordination Study & Arc Flash Hazard Analysis 26 05 73 Acceptance Testing and Performance Verifications 26 08 00 Low Voltage Transformers 26 22 00 Panelboards 26 24 16 Electric Motors 26 24 20 Electric Service 26 27 13 Circuit Breakers & Fused Switches – Low Voltage 26 28 11 Control Panels 26 29 13 Walk-In Electrical Equipment Enclosures 26 29 17 Variable Frequency Drives 26 29 23 Diesel Engine Driven Generator Sets 26 32 13 Automatic Transfer Switches 26 36 00 Safety Switches and Disconnects 26 36 13 Lightning Protection System 26 41 00 Surge Protective Devices (SPDs) 26 43 00 Lighting Fixture 26 50 00
DIVISION 31 – EARTHWORK
Site Clearing 31 10 00 Excavation – Earth and Rock 31 23 16 Backfilling 31 23 23 Shoring, Sheeting and Bracing 31 40 00
DIVISION 32 – EXTERIOR IMPROVEMENTS
Pavement Repair and Restoration 32 10 01 Sidewalks, Driveways and Curbs 32 16 00 Chain Link Fencing and Gate 32 31 13 Landscaping Work 32 90 01 Lawn Restoration 32 92 00
DIVISION 33 – UTILITIES
Smoke Testing of Wastewater Collection System 33 01 33 Televising and Inspection of Gravity Sewer Systems 33 01 36 Leakage Tests 33 05 01 Roadway Crossings by Open Cut 33 05 02 Laying and Jointing Buried Pipelines 33 05 03 Sewer Manholes 33 05 13 HDPE Concrete Protective Liner 33 05 14 Fiberglass Reinforced Plastic (FRP) Concrete Protective Liner 33 05 15 Jacking, Augering and Mining 33 05 23 Directional Drilling 33 05 24 Polyvinyl Chloride (PVC) Water Main Pipe 33 11 01 High Density Polyethylene (HDPE) Pipe and Fittings 33 11 02 Ductile Iron Pipe and Fittings 33 11 03 Polyvinyl Chloride (PVC) Waterline 33 11 04 Disinfection 33 11 12 Water Valves and Appurtenances 33 12 16 Hydrants 33 12 19 Polyvinyl Chloride (PVC) Gravity Sewer Pipe 33 31 01 Buried Fiberglass Reinforced Plastic (FRP) Gravity Sewer Pipe 33 31 02 Nonreinforced Concrete Sewer Pipe 33 31 03 Reinforced Concrete Sewer Pipe and Pre-Cast Wetwell Sections 33 31 04 Buried Polyvinyl (PVC) Sewer and Pressure Pipe 33 34 00 Polyvinyl Chloride (PVC) Force Main Pipe 33 34 01 Wastewater Valves and Appurtenances 33 34 12
DIVISION 40 – PROCESS INTEGRATION
A-Instrumentation and Control 40 95 13 B-Instrumentation and Control 40 95 13 Fiber Optic Communication System 40 95 33
DIVISION 44 – POLLUTION AND WASTE CONTROL EQUIPMENT
Pre-Engineered Biofiltration Odor Control System 44 31 21
REV: 04/2019 Section 01 11 00
SUMMARY OF WORK
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Description of Work
B. Constraints
C. Work by Others
D. CONTRACTOR's Use of Site
E. Work Sequence
F. Owner Occupancy
NOTE: Fill in the blanks and add additional work items under B as required.
1.2 DESCRIPTION OF WORK
A. General: The Work to be done under this Contract consists of the construction of a facility as shown and specified in Contract Documents entitled
B. The Work includes:
1. Furnishing of all labor, material, superintendence, plant, power, light, heat, fuel, water, tools, appliances, equipment, supplies, services and other means of construction necessary or proper for performing and completing the Work.
2. Sole responsibility for adequacy of plant and equipment.
3. Maintaining the Work area and site in a clean and acceptable manner.
4. Maintaining existing facilities in service at all times except where specifically provided for otherwise herein.
5. Protection of finished and unfinished Work.
6. Repair and restoration of Work damaged during construction.
7. Furnishing as necessary proper equipment and machinery, of a sufficient capacity, to facilitate the Work and to handle all emergencies normally encountered in Work of this character.
8. Furnishing, installing, and protecting all necessary guides, track rails, bearing plates, anchor and attachment bolts, and all other appurtenances needed for the installation of the devices included in the equipment specified. Make anchor bolts of appropriate size, strength and material for the purpose intended.
Furnish substantial templates and shop drawings for installation.
C. Implied and Normally Required Work: It is the intent of these Specifications to provide the OWNER with complete operable systems, subsystems and other items of Work. Any part or item of Work which is reasonably implied or normally required to make each installation satisfactorily and completely operable is deemed to be included in the Work and the Contract Amount. All miscellaneous appurtenances and other items of Work incidental to meeting the intent of these Specifications are included in the Work and the Contract Amount even though these appurtenances may not be specifically called for in these Specifications.
D. Quality of Work: Regard the apparent silence of the Contract Documents as to any detail, or the apparent omission from them of a detailed description concerning any Work to be done and materials to be furnished as meaning that only the best general practice is to prevail and that only materials and workmanship of the best quality are to be used. Interpretation of these specifications will be made upon this basis.
NOTE: Use 1.3 if applicable.
1.3 CONSTRAINTS
A. The Contract Documents are intended to allow the CONTRACTOR flexibility in construction of the Work, however, the following constraints apply:
NOTE: Complete or delete as required.
1.4 WORK BY OTHERS
A. Work on the Project, which may take place concurrently with this CONTRACT and which is excluded from this CONTRACT, is as follows:
1.
2.
3.
4.
1.5 CONTRACTOR'S USE OF SITE
A. In addition to the requirements of the General Conditions, limit use of site and premises for work and storage to allow for the following:
1. Coordination of the Work under this CONTRACT with the work of the other contractors where Work under this CONTRACT encroaches on the Work of other contractors.
2. OWNER occupancy and access to operate existing facilities.
3. Coordination of site use with ENGINEER.
4. Responsibility for protection and safekeeping of products under this
CONTRACT.
5. Providing additional off site storage at no additional cost to OWNER as needed.
1.6 WORK SEQUENCE
A. Construct Work in stages to accommodate OWNER's use of premises during construction period and in accordance with the limitations on the sequence of construction specified. Coordinate construction schedules and operations with
ENGINEER.
B. Coordinate Work of all subcontractors.
NOTE: Modify as necessary
1.7 OWNER OCCUPANCY
A. OWNER will occupy premises during entire period of construction in order to maintain normal operations. Cooperate with OWNER's representative in all construction operations to minimize conflict, and to facilitate OWNER usage.
B. Conduct operations so as to inconvenience the general public in the least.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
A. Starting Work: Start Work within 10 days following the date stated in the Notice to Proceed and execute with such progress as may be required to prevent delay to other contractors or to the general completion of the project. Execute Work at such items and in or on such parts of the project, and with such forces, material and equipment, as to complete the Work in the time established by the Contract. At all times, schedule and direct the Work so that it provides an orderly progression to completion within the specified time for completion.
END OF SECTION
REV: 04/2019 Section 01 22 13
MEASUREMENT AND PAYMENT
SECTION 01 22 13
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Explanation and Definitions
B. Measurement
C. Payment
D. Schedule of Values
1.2 EXPLANATION AND DEFINITIONS
A. The following explanation of the Measurement and Payment for the bid form items is made for information and guidance. The omission of reference to any item in this description shall not, however, alter the intent of the bid form or relieve the CONTRACTOR of the necessity of furnishing such as a part of the Contract.
1.3 MEASUREMENT
A. The quantities set forth in the bid form are approximate and are given to establish a uniform basis for the comparison of bids. The OWNER reserves the right to increase or decrease the quantity of any class or portion of the work during the progress of construction in accord with the terms of the Contract.
1.4 PAYMENT
A. Payment shall be made for the items listed on the Bid Form on the basis of the work actually performed and completed, such work including but not limited to, the furnishing of all necessary labor, materials, equipment, transportation, clean up, restoration of disturbed areas, and all other appurtenances to complete the construction and installation of the work as shown on the drawings and described in the specifications.
B. Unit prices are used as a means of computing the final figures for bid and Contract purposes, for periodic payments for work performed, for determining value of additions or deletions and wherever else reasonable.
1.5 SCHEDULE OF VALUES
A. Approval of Schedule: Submit for approval a preliminary schedule of values, in duplicate, for all of the Work. Prepare preliminary schedule in accordance with the General Conditions. Submit preliminary schedule of values within 10 calendar days after the Effective Date of the Agreement. Submit final schedule of values in accordance with the General Conditions.
B. Format: Utilize a format similar to the Table of Contents of the Project
Specifications. Identify each line item with number and title of the major specification. Identify site mobilization, bonds and insurance. Include within each line item, a direct proportional amount of CONTRACTOR’s overhead profit.
C. Revisions: With each Application for Payment, revise schedule to list approved
Change Orders.
1.6 APPLICATION FOR PAYMENT
A. Required Copies: Submit three copies of each application on EJCDC Form No.
1910-8-E (1990) or approved equal. Present required information in typewritten form or on electronic media printout.
B. Execute certification by signature of authorized officer.
C. Use data from approved Schedule of Values.
D. Stored Materials: When payment for materials stored is permitted, submit a separate schedule for Materials Stored showing line item, description, previous value received, value incorporated into the Work and present value.
E. Change Orders: List each authorized Change Order as an extension on continuation sheet, listing Change Order number and dollar amount as for an original item of work.
F. Final Payment: Prepare Application for Final Payment as required in the General
Conditions.
G. Submit an updated construction schedule for each Application for Payment.
PART 2 EXECUTION
2.1 MEASUREMENT AND PAYMENT
A. Payment shall be made on the basis of work actually performed completing each item in the Bid, such work including, but not limited to, the furnishing of all necessary labor, materials, equipment, transportation, cleanup, and all other appurtenances to complete the construction and installation of the work to the configuration and extent as shown on the drawings and described in the specifications. Payment for each item includes compensation for cleanup and restorations. Cleanup and surface restorations (including pavement replacement) will be considered as ten percent (10%) of each pay item and complete payment will not be made until cleanup, restorations and as-builts are completed.
NOTE: Edit as required.
1. Mobilization: Payment for mobilization will be made at the Contract lump sum price for the contractor’s cost for mobilization, demolition, survey, insurance, audio-video tape of existing conditions, preparing a field office, identifying and securing a staging area and other applicable administrative charges as outlined in the Contract Documents and specified herein. Mobilization lump sum price shall not exceed two percent (2%) of the total Bid Amount. Payment for mobilization will be twenty-five percent (25%) of the lump sum amount to be included with the final payment request.
2. Performance and Payment Bond Premiums and Insurance: Performance and
Payment Bond Premiums and Insurance lump sum price shall not exceed three percent (3%) of the total Bid Amount. Payment shall be divided equally over the number of pay request anticipated from the Notice to Proceed. No additional payments shall be made due to time extension.
3. Furnish and Install Utility Pipelines: Payment for furnishing and installing utility pipelines (various sizes and types) will be made at the Contract unit price per lineal foot for the pipe in place. This item includes all necessary fittings, connections to existing mains, labor, equipment and materials for the furnishing and laying of the pipe, signs, maintenance of traffic, dewatering, compaction, pipe bedding, backfilling, sheeting, restrained joint piping, mylar detectable tape, polyethylene sleeve, clamps, harnessing, plugs and caps, adapters, excavation of all material encountered including rock, backfill, replacement of grass, sod, clearing and grubbing, pavement, driveways, sidewalks, mailboxes, culverts, storm sewers, and other surface materials not specifically designated in the Bid, clean-up, sterilization, and tests. Measurement of the pipe shall be to the nearest foot along the centerline including the lengths of manholes, valves and fittings. Lineal footage measurement shall be horizontal. Cuts shall be measured from existing grade to the invert elevation of the sewer.
4. Furnish and Install Standard Precast Concrete Sanitary Sewer Manholes:
Payment for furnishing and installing standard precast concrete sanitary manholes will be made at the unit price per manhole acceptably installed. This item includes all excavation, backfilling, compacted gravel or crushed stone bedding, sheeting, shoring, dewatering, concrete work and reinforcing, protection of adjacent facilities, manhole frames and covers, coatings and linings, manhole joints, bottom channels and sanitary sewer connections. All manholes shall conform to the Standard Sanitary Sewer Precast Manhole detail shown on the Plans. This item does not include outside drop manholes or standard precast shallow manholes. Cuts shall be measured from existing grade to the invert elevation of the exiting sewer.
5. Furnish and Install Outside Drop Manholes: Payment for furnishing and installing outside drop manholes will be made at the unit price per drop manhole acceptably installed. This item includes all excavation, backfilling, compacted gravel or crushed stone bedding, sheeting. shoring, dewatering, concrete work and reinforcing, drop pipes and pipe connections, plugs for future connections, protection of adjacent facilities, manhole frames and covers, coatings and linings, manhole joints, bottom channels and sanitary sewer connections. All outside drop manholes shall conform to the Drop Manhole detail shown on the Plans. Cuts shall be measured from existing grade to the invert elevation of the exiting sewer.
6. Furnish and Install Valves and Boxes: Payment for furnishing and installing valves will be made at the appropriate Contract unit price per valve acceptably installed. This item includes the valve, box and all necessary labor, materials and equipment for installation, including valve stem and valve box extensions.
This item also includes the installation of base material below the valve in accordance with the detail shown in the Plans.
7. Furnish and Install Fire Hydrant Assemblies: Payment for the furnishing and installing of fire hydrant assemblies will be made at the Contract unit price for each fire hydrant assembly acceptably installed. This item includes the tee installed on the utility main, all necessary fittings, joint restraint from the valve to the tee and necessary piping from the tee to the hydrant location with the installation of barrel section to meet finished grade. All piping shall be six-inch (6") ductile iron pipe from the tee to hydrant. The CONTRACTOR shall be responsible to set the hydrant to grade in accordance with the detail shown on the Plans.
8. Furnish and Install Permanent Blow-offs: Payment for furnishing and installing permanent blow-offs will be made at the appropriate Contract unit price per blow-off acceptably installed. This item includes the reinforced concrete thrust collar, piping, making pipe connections, valves, meter box, tie rods and all other work for a complete installation. All permanent blow-offs shall conform to the detail shown on the Plans.
9. Furnish and Install Tapping Sleeve and Valve: Payment for furnishing and installing tapping sleeves and valves will be made at the appropriate Contract unit price per tapping sleeve and valve acceptably installed. This item includes all piping, making pipe connections, tapping sleeve, valve and valve box, restrained joints, and all other work for a complete installation.
10. Furnish and Install Pump Station: Payment for the furnishing and installing the pump station will be made for at the Contract lump sum price for the pump station acceptably installed. This item includes pumps, wet well structure, valve vault structure, fence, stainless steel hardware, aluminum wet well cover, aluminum valve vault cover, coatings, valves, pipe, fittings, water service, panel, electrical hardware, electrical connection, driveway, culvert, and all necessary materials and labor to complete the pump station in accordance with the project plans. Also included is the cost to connect electrical power to the pump station.
The CONTRACTOR shall schedule with the local electrical company to place the pump station into service.
11. Furnish and Install 6-Inch Diameter Sanitary Sewer Services: Payment for furnishing and installing 6-inch diameter sanitary sewer services will be made at the appropriate Contract unit price per linear foot for P.V.C. and ductile iron pipe sewer service acceptably installed. This item includes all labor, equipment and materials for furnishing and installing all necessary pipe, fittings, connections, solids sleeves and adapters, protection of existing utilities and facilities, excavation, pipe bedding, sheeting, shoring, dewatering, compaction, cleanouts, service markers, plugs, detectable tape, removal and replacement of grass, sod, shrubs, pavement, driveways, culverts and storm sewers, mailboxes, sidewalks and other surface materials not specifically designated in the Bid, cleanup, testing, and all other work for a complete installation.
12. Furnish and Install 1-Inch Diameter Water Services: Payment for furnishing and installing 1-inch diameter water services will be made at the appropriate Contract unit price for each P.E. short side and long side service acceptably installed. This item includes all labor, equipment and materials for furnishing and installing all necessary pipe, fittings, connections, casing pipes, meter stops, meter box, tapping sleeves, protection of existing utilities and facilities, excavation, pipe bedding, dewatering, compaction, removal and replacement of grass, sod, shrubs, pavement, driveways, culverts and storm sewers, mailboxes, sidewalks and other surface materials not specifically designated in the Bid, cleanup, testing and all other work for a complete installation.
13. Remove and Replace Driveway: Payment for removing and replacing driveway will be made at the appropriate Contract Unit price per lineal foot of concrete or asphalt driveway shown on the Plans to be removed and replaced for water main construction. Driveways shall be replaced to match existing elevations and materials of construction. Surface restoration required for driveway removal and replacement shall be included in this item.
14. Remove and Replace Street Pavement Surface and Base: Payment for removing and replacing street pavement surface and base will be made at the appropriate Contract unit price per square yard for pavement surface and base installed in the work. All pavement surface and base shall be replaced in accordance with the detail shown on the Plans.
15. Furnish and Install Force Main Interconnection: Payment for furnishing and installing the force main interconnection will be made at the Contract lump sum price for the interconnection acceptably installed. This item includes all labor, equipment and materials to install all necessary pipe, fittings, connections, tapping sleeve and valve with valve box, field measurements, protection of existing facilities, excavation, pipe bedding, dewatering, compaction, surface restoration, testing, cleanup and all other work for a complete installation.
16. Furnish and Install Unreinforced Concrete: Payment for furnishing and installing unreinforced concrete will be made at the Contract unit price per cubic yard for all unreinforced concrete installed as ordered in writing by the ENGINEER. All unreinforced concrete shall conform to the technical specifications. All unreinforced concrete installed in the work not shown on the Plans and not ordered by the ENGINEER in writing will not be measured for payment.
17. Special Pipe Bedding: Payment for special pipe bedding will be made at the
Contract unit price per cubic yard of washed shell, gravel, or other acceptable material used in trench bottoms for pipe bedding where ordered in writing by the ENGINEER. If earth or sand is used for stabilizing the subgrade, no payment will be made under this item. Payment for earth or sand materials used in stabilizing the subgrade shall be included in the price for installing pipe.
18. Jack and Bore Crossing: Payment for furnishing and installing jack and bore in crossing will be made at the Contract unit price per lineal foot for the crossing place.
19. Maintenance of Traffic: Payment for maintenance of traffic will be made for at the Contract lump sum price.
REV: 04/2019 Section 01 26 00
CHANGE ORDER AND FIELD DIRECTIVE
CHANGE PROCEDURES
SECTION 01 26 00
CHANGE ORDER AND FIELD DIRECTIVE CHANGE PROCEDURES
PART 1 GENERAL
A. Definitions
B. Change Orders
C. Field Directive Change
1.2 DEFINITIONS
A. Change Order: Refer to the Change Order definition in Article 2 of the General
B. Field Directive Change: Field Directive Change is a written directive to the
CONTRACTOR issued on or after the effective date of the agreement; signed by the OWNER, recommended by the ENGINEER ordering an addition, deletion, or revision in the Work. A Field Directive Change will subsequently be followed by the issuance of a Change Order.
C. Overhead: Overhead is defined as the cost of administration, field office and home office costs, general superintendence, office engineering and estimating costs, other required insurance, materials used in temporary structures (not including form work), additional premiums on the performance bond of the CONTRACTOR, the use of small tools, scheduling costs, and all other costs incidental to the performance of the change or the cost of doing business.
1.3 CHANGE ORDERS
A. Initiation of Proposals:
1. From time to time, the OWNER or the ENGINEER may issue a Request for a Change Order Proposal. The Request will contain a description of the intended change with supplementary or revised Drawings and Specifications as applicable, and the projected time for accomplishing the change.
2. The CONTRACTOR may propose a change in the Work by submittal of a
Change Order Request to the ENGINEER describing the proposed change with a statement of the reason for the change and the effect on the Contract time and price, along with supporting documentation.
CHANGE PROCEDURES
B. Execution of Change Order Proposal:
1. When a Proposal is requested for changed work, submit proposal within 15 days following receipt of the Request from OWNER or ENGINEER. State the increase or decrease, if any, in Contract Completion time and Contract Price.
2. Explain proposal in sufficient detail to permit review by OWNER.
3. For Omitted Work the decrease in the Contract Price will be determined by the
ENGINEER and will include appropriate amounts for profit and overhead.
4. The OWNER and ENGINEER will review the Proposal and may request additional information and documentation. Provide these items upon request.
5. If the OWNER decides to proceed with the change, the OWNER will issue a
Change Order for signature first by the CONTRACTOR and then by the
OWNER.
6. The CONTRACTOR will promptly complete the approved change in the Work on receipt of the executed Change Order.
a. Failure to sign the Change Order does not relieve the CONTRACTOR from performing the Work if the Change Order is signed by the OWNER.
C. Compute the cost of both additive and deductive changes in the Work in accordance with Article 11 of the General Conditions and as follows:
1. Include, the costs of labor, crew foreman and general foreman performing or directly supervising the changed Work on the site. Include travel and subsistence, but only to the extent incurred.
2. To the labor cost add all net premium for Workman's Compensation, taxes pursuant to the Federal Social Security Act, and payments required under State and Federal unemployment laws.
3. Add necessary extra materials, delivered at the site.
NOTE: In Items 5 and 6 confirm percentages and edit as required.
4. Include Subcontractor's costs, determined by items 1 through 4 in the preceding subparagraphs, including a maximum of 10 percent overhead and 10 percent profit for the first $20,000; 7-1/2 percent overhead and 7-1/2 percent profit on the next $30,000; and 5 percent overhead and 5 percent profit on balance over $50,000.
CHANGE PROCEDURES
5. For all subcontract work add 5 percent overhead and 5 percent profit to the subcontractor's costs as determined in paragraph 5. For work performed by the CONTRACTOR's own forces add a maximum of 10 percent overhead and 10 percent profit for the first $20,000; 7-1/2 percent overhead and 7-1/2 percent profit on the next $30,000; and 5 percent overhead and 5 percent profit on balance over $50,000.
1.4 FIELD DIRECTIVE CHANGE
A. Initiation by OWNER: OWNER may issue a Field Directive Change with a Notice to Proceed without a prior Request for a Change Order Proposal or the CONTRACTOR's signature.
B. Payment Determination: The OWNER will designate the method of determining the amount of compensation or credit, if any, based on one of the methods contained in Article 11 of the General Conditions.
C. Timing: Proceed with the change in the Work immediately upon receipt of the Field
Directive Change.
D. Addition to Contract: The Field Directive Change will be incorporated into the Contract Documents via a Change Order at a later date.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
CHANGE PROCEDURES
(NO TEXT FOR THIS PAGE)
REV: 04/2019 Section 01 31 13
PROJECT COORDINATION
SECTION 01 31 13
PART 1 GENERAL
A. Work Progress
B. Private Land
C. Work Locations
D. Open Excavations
E. Test Pits
F. Maintenance of Traffic
G. Maintenance of Flow
1.2 WORK PROGRESS
A. Furnish personnel and equipment which will be efficient, appropriate and large enough to secure a satisfactory quality of work and a rate of progress which will allow the completion of the work within the time stipulated in the Bid of these Specifications.
If at any time such personnel appears to the ENGINEER to be inefficient, inappropriate or insufficient for securing the quality of work required or for producing the rate of progress aforesaid, he may order the CONTRACTOR to increase the efficiency, change the character or increase the personnel and equipment, and the CONTRACTOR shall conform to such order. Failure of the ENGINEER to give such order shall in no way relieve the CONTRACTOR of his obligations to secure the quality of the work and rate of progress.
1.3 PRIVATE LAND
A. Do not enter or occupy private land outside of easements, except by permission of OWNER. Construction operations shall be conducted in accordance with Section 01 57 00.
1.4 WORK LOCATIONS
A. Structures and pipelines shall be located substantially as indicated on the Drawings, but the ENGINEER reserves the right to make such modifications in locations as may be found desirable to avoid interference noted on the Drawings, such notation is for the CONTRACTOR's convenience and does not relieve him from laying and jointing different or additional items where required.
1.5 OPEN EXCAVATIONS
A. All open excavations shall be adequately safeguarded by providing temporary barricades, caution signs, lights and other means to prevent accidents to persons, and damage to property. The CONTRACTOR shall, at his own expense, provide suitable and safe bridges and other crossings for accommodating travel by the public and workmen.
1.6 TEST PITS
A. Test pits for the purpose of locating underground pipeline or structures in advance of the construction shall be excavated and backfilled by the CONTRACTOR. Test pits shall be backfilled immediately after their purpose has been satisfied and maintained in a manner satisfactory to the ENGINEER. The costs for such test pits shall be borne by the CONTRACTOR.
1.7 MAINTENANCE OF TRAFFIC
A. Maintenance of traffic shall be in accordance with Sections 01 55 26 and 33 05 02.
B. All projects and work on highways, roads, and streets, shall have a traffic control plan, (TCP), as required by Florida Statute and Federal regulations. All work shall be executed under the established plan and Department approved procedures. The TCP is the result of considerations and investigations made in the development of a comprehensive plan for accommodating vehicular and pedestrian traffic through the construction zone.
C. The complexity of the TCP varies with the complexity of the traffic problems associated with a project. Many situations can be covered adequately with reference to specific sections from the Manual on Uniform Traffic Control Devices (MUTCD), the Traffic Control Devices Handbook (TCDH), or Roadway and Traffic Design Standard Series 600.
1.8 MAINTENANCE OF FLOW
A. Provide for the flow of sewers, drains, courses interrupted during the progress of the work, and shall immediately cart away and remove all offensive matter. The entire procedure of maintaining existing flow shall be fully discussed with the ENGINEER well in advance of the interruption of any flow.
PART 2 PRODUCTS
2.1 PROTECTION OF CONSTRUCTION AND EQUIPMENT
A. All newly constructed work shall be carefully protected from damage in any way. No wheeling or walking or placing of heavy loads on it shall be allowed and all portions damaged shall be reconstructed by the CONTRACTOR at his own expense.
B. All structures shall be protected in a manner approved by the ENGINEER. Should any of the floors or other parts of the structures become heaved, cracked or otherwise damaged, all such damaged portions of the work shall be completely repaired and made good by the CONTRACTOR at his own expense and to the satisfaction of the ENGINEER. Special attention is directed to substructure bracing requirements, described in Section 31 40 00. If, in the final inspection of the work, any defects, faults or omissions are found, the CONTRACTOR shall cause the same to be repaired or removed and replaced by proper materials and workmanship without extra compensation for the materials and labor required. The CONTRACTOR shall be fully responsible for the satisfactory maintenance and repair of the construction and other work undertaken herein, for at least the guarantee period described in the contract.
C. Take all necessary precautions to prevent damage to any structure due to water pressure during and after construction and until such structure is accepted and taken over by the OWNER.
PART 3 EXECUTION
3.1 PROTECTION OF CONSTRUCTION AND EQUIPMENT
A. Sequence and schedule work in a manner to preclude delays and conflicts between the work of various trades and contractors. Each trade shall keep informed as to the work of other trades on the project and shall execute their work in a manner that will not interfere with the work of other trades.
3.2 DIAGRAMMATIC NATURE OF DRAWINGS
A. Where layout is diagrammatic, such as pipelines, conduits, ductwork, etc., it shall be followed as closely as other work will permit. Changes from diagrams shall be made as required to conform to the construction requirements.
B. Before running lines, carefully verify locations, depths and sizes and confirm that lines can be run as contemplated without interfering with other construction. Any deviation shall be referred to the ENGINEER for approval before lines are run. Minor changes in location of the equipment, fixtures, piping, etc., from those shown on the Drawings, shall be made without extra charge if so directed by the ENGINEER before installation.
C. Determine the locations and sizes of equipment, fixtures, conduit, ducts, openings, etc., in order that there will be no interference in the installation of the work or delay in the progress of other work. In the event that interferences develop, the ENGINEER’s decision regarding relocation of work will be final.
D. Any changes made necessary through failure to make proper arrangements to avoid interference shall not be considered as extras. Cooperate with those performing other work in preparation of interference drawings, to the extent that the location of piping, ductwork, etc., with respect to the installations of other trades shall be mutually agreed upon by those performing the work.
3.3 PROVISIONS FOR LATER INSTALLATION
A. Where any work cannot be installed as the construction is progressing, provide for boxes, sleeves, inserts, fixtures or devices as necessary to permit installation of the omitted work during later phases of construction. Arrange for chases, holes, and other openings in the masonry, concrete or other work and provide for subsequent closure after placing equipment. Arrangement for and closure of openings shall be subject to the approval of the ENGINEER and all costs therefor shall be included in the contract price for the work.
3.4 COORDINATION
A. The CONTRACTOR shall be fully responsible for the coordination of his work and the wok of his employees, subcontractors, and suppliers with the OWNER, and regulatory agencies, and assure compliance with schedules.
REV: 04/2019 Section 01 31 19
PROJECT MEETINGS
SECTION 01 31 19
PROJECT MEETINGS
PART 1 GENERAL
A. Coordination
B. Preconstruction Conference
C. Progress Meetings
1.2 COORDINATION
A. General: Coordinate scheduling, submittals, and Contract work to assure efficient and orderly sequence of installation of interdependent construction elements.
1.3 PRECONSTRUCTION CONFERENCE
A. General: Prior to commencement of the Work, in accordance with the General Conditions, the OWNER will conduct a preconstruction conference to be held at a predetermined time and place.
B. Delineation of Responsibilities: The purpose of the conference is to designate responsible personnel, to establish a working relationship among the parties and to identify the responsibilities of the OWNER, plant personnel and the CONTRACTOR/VENDOR. Matters requiring coordination will be discussed and procedures for handling such matters, established. The agenda will include:
1. Submittal procedures
2. Partial Payment procedures
3. Maintenance of Records
4. Schedules, sequences and maintenance of facility operations
5. Safety and First Aid responsibilities
6. Change Orders and Field Directive Changes
7. Use of site
8. Housekeeping
9. Equipment delivery
C. Attendees: The preconstruction conference is to be attended by the representatives of the CONTRACTOR/VENDOR, the OWNER and plant personnel that will be associated with the project. Representatives of regulatory agencies, subcontractors, and principal suppliers may also attend when appropriate.
REV: 04/2019 Section 01 31 19
PROJECT MEETINGS
D. Chair and Minutes: The preconstruction conference will be chaired by the Owner who will also arrange for the keeping and distribution of minutes to all attendees.
1.4 PROGRESS MEETINGS
A. Meeting Frequency and Format: Schedule progress meetings on at least a basis or more frequently as warranted by the complexity of the Project, to review the Work, discuss changes in schedules, maintain coordination and resolve potential problems.
Invite OWNER, ENGINEER and all subCONTRACTOR/VENDORs. Suppliers may be invited as appropriate. Minutes of the meeting will be maintained by CONTRACTOR/VENDOR and reviewed by ENGINEER prior to distribution by the CONTRACTOR/VENDOR. Distribute reviewed minutes to attendees within ___ calendar days after each meeting.
PART 2 PRODUCTS
Not Used
REV: 04/2019 Section 01 32 16
PROGRESS SCHEDULE
NOTE: Review this section carefully. If Project Scope is relatively simple and straightforward this Specification is to be used. If Project is complex use Section 01 32 17.
SECTION 01 32 16
PART 1 GENERAL
A. Form of Schedules
B. Content of Schedules: Submit for approval, a preliminary progress schedule in accordance with the General Conditions.
C. Schedule Revisions
D. Submittal Requirements
1.2 FORM OF SCHEDULES
A. Prepare schedules in form of a horizontal bar chart.
1. Provide separate horizontal bar for each trade or operation.
2. Utilize a horizontal time scale and identify first work day of each week.
3. Utilize scale and spacings to allow space for notations and future revisions.
B. Utilize a listing format which chronologically indicates the order of start of each item of work.
C. Identify each listing by major specification section numbers.
1.3 CONTENT OF SCHEDULES
A. Completion Dates: Show the beginning and ending contract dates stated in documents. Schedules showing completion prior to the contract completion date will be accepted but in no event will they be considered basis for a claim for delay against the OWNER by the CONTRACTOR for the period between the early completion date and the completion date provided in the Contract Documents.
B. Show complete sequence of construction by activity.
C. Show dates for beginning and completion of each major element of construction and installation dates for major items of equipment. Elements shall include, but not be limited to, the following:
1. Shop drawing receipt from supplier/manufacturer submitted to ENGINEER, review and return to supplier/manufacturer
2. Material and equipment order, manufacturer, delivery, installation, and checkouts
3. Performance tests and supervisory services activity
4. Construction of various facilities
5. Demolition
6. Excavation, sheeting, shoring, dewatering
7. Concrete placement sequence
8. Structural steel erection
9. Wall and roof construction
10. Piping and equipment installation
11. Electrical work activity
12. Heating, ventilating, and air conditioning work activity
13. Plumbing work activity
14. Sewer installation
15. Connection to existing sewers
16. Water main installation
17. Miscellaneous concrete placement
18. Subcontractor's items of work
19. Backfilling, grading, seeding, sodding, landscaping, fence construction, and paving
20. Final cleanup
21. Allowance for inclement weather
22. Coordination with concurrent Work on site
D. Show projected percentage of completion for each item as of first day of each month.
1.4 SCHEDULE REVISIONS
A. As a minimum, revise construction schedule every 30 calendar days to reflect changes in progress of Work for duration of Contract.
B. Indicate progress of each activity at date of submittal.
C. Show changes occurring since previous submittal of schedule.
1. Major change in scope
2. Activities modified since previous submittal
3. Revised projections of progress and completion
4. Other identifiable changes
D. Provide a written report as needed to define:
1. Problem areas, anticipated delays, and impact on schedule
2. Corrective action recommended and its effect
3. Effect of changes on schedules of other Contractors
1.5 SUBMITTAL REQUIREMENTS
A. Schedule: Submit final progress schedule in accordance with the General Conditions.
B. For preliminary and final submittal of construction progress schedule and subsequent revisions thereof furnish three copies to ENGINEER.
PART 2 PRODUCTS
Not Used
(NO TEXT FOR THIS SECTION)
REV: 04/2019 Section 01 32 17
NOTE: Review this section carefully. If Project Scope is complex this Specification is to be used. If project is relatively simple and straightforward use Section 01 32 16.
SECTION 01 32 17
PART 1 GENERAL
A. Scheduling Responsibilities
B. Submittals
C. Network Requirement
D. Cost Loading
E. Progress of the Work
F. Schedule Updates
1.2 SCHEDULING RESPONSIBILITIES
A. Format: Use the Critical Path Method to schedule and monitor job progress. Provide all information concerning sequencing logic and duration of all activities as well as the initial CPM logic network diagram and tabulated report data.
B. Initial Submittal: Within 30 days after the Notice to Proceed, submit the initial logic network diagram to the ENGINEER for review. Within 60 days submit final network diagram.
C. Updates: On a monthly basis, furnish to the ENGINEER updated information on logic, percent complete, actual start and finish date and direction changes. Distribute copies at Progress Meetings.
D. Adherence: Schedule and direct forces in a manner that will allow for completion of the Work within the Contract time specified.
E. Accuracy: Provide initial schedule and subsequent update information to reflect the best efforts of the CONTRACTOR and all subcontractors as to how they envision the Work to be accomplished. Similarly, all progress information must be an accurate representation of the CONTRACTOR's and subcontractor's actual performance.
Complete Work under this Contract in accordance with the established CPM schedule.
F. Cost of Revisions: At no additional cost to the OWNER, revise schedule when in the judgement of the ENGINEER, it does not accurately reflect the actual prosecution of the Work.
1.3 SUBMITTALS
A. General: Provide all submittals, including the following, as specified in Division 1 and the General Conditions.
B. CPM Schedule:
1. Within 30 days after the date stated in the Notice to Proceed, submit to the
ENGINEER prints of a proposed CPM network diagram and tabular reports for the first 90 days of the Work. Draw initial logic diagram as described herein and submit on sheets 24 inches by 36 inches. Include both procurement and construction activities. Schedule a review meeting with the ENGINEER and the OWNER (or OWNER's Consultants) within 2 weeks of its submission. Revise and resubmit the 90 day schedule until it is acceptable to the ENGINEER.
2. Within 60 Days after the Notice to Proceed, submit to the ENGINEER 3 sets of the proposed CPM logic diagram and tabular reports for the entire Contract duration. Include both procurement and construction activities. Sort these tabular reports by total float and activity number. Provide a predecessor/successor report, resource loading report, and project calendar.
Draw logic diagram as described.
3. Schedule review meeting with the ENGINEER and the OWNER within 2 weeks of its submission. If a review of the submitted CPM Schedule indicates a work plan which will not complete the Work within the time requirements stated in the Contract, reallocate resources, revise the CPM Schedule and resubmit it until it is acceptable. Failure by the CONTRACTOR to submit an acceptable schedule may, at the OWNER's sole discretion, be cause for the withholding of any partial payment otherwise due under the Contract.
4. Review of the Schedule by the ENGINEER will not constitute ENGINEER's representation that the Work can be completed as shown on the Schedule.
C. Submittals Schedule: In addition to the above scheduling requirements, submit a complete and detailed listing of anticipated submittals during the course of the Contract. Coordinate these submittals with those of subcontractors and suppliers.
Identify each submittal by Contract drawing number and Specification section number. Show the anticipated submission due date for each submittal along with the date on which its return is required. For planning purposes, average turn-around time for shop drawings will be 14 Calendar Days after receipt. Longer durations for review may be required and will not be considered a basis for a claim for additional time or compensation. For submittals on the critical path, at the time of submission mark transmittal in red with the words "Critical Path".
1. Submit Submittal schedule within 10 Days from the Notice to Proceed. Revise as required and incorporate the dates and review durations into the CPM Schedule.
1.4 NETWORK REQUIREMENTS
A. Diagram: Show in the network diagram the order and interdependence of activities and the sequence in which the Work is to be accomplished. The purpose of the network analysis diagram is to show how the start of a given activity is dependent on the completion of preceding activities and its completion restricts the start of succeeding activities. Follow a time scaled precedence format. Time scale the detailed network diagram showing a continuous flow from left to right.
B. Develop the schedule activities into two major groups; procurement activities; and construction activities:
1. Include the following procurement activities as a minimum:
a. Permits
b. Easements
c. Submittal items
d. Approval of submittal items
e. Fabrication and delivery of submittal items.
Tie each of the above procurement items logically to the correct construction activity in the overall CPM construction schedule.
2. Under construction activities section utilize physical work activities to describe how the job will be constructed.
C. Activity Durations: Break the work into activities with durations of 1 to 20 Days each, except for nonconstruction activities, such as procurement of materials and delivery of equipment, and other activities which may require longer durations. To the extent feasible, group activities related to a specific physical area of the project on the network for ease of understanding and simplification. The ENGINEER and OWNER will review the selection and number of activities.
1. For each activity on the network indicate the following:
a. A single duration, no longer than 20 Days (i.e., the single best estimate of the expected elapsed time considering the scope of work involved in the activity) expressed in Days. Include normal holidays and weather delay.
Show critical path for the schedule.
b. Assign an activity I.D. number to each activity. The I.D. number will be numeric with a maximum of 5 digits.
c. Include a brief description of the activity. If this description is not definitive, a separate listing of each activity and a descriptive narrative may be required.
d. Cost load each activity, except for procurement activities, to indicate the total estimated costs of the activity. No activity shall exceed $60,000 except for equipment items. Assign material costs to delivery activities.
e. Load each activity with the estimated work hours to be expended on each activity.
D. Incomplete Schedule: Failure to include on the network any element of work required for the performance of this Contract does not excuse the CONTRACTOR from completing all Work required within the applicable completion time, notwithstanding the network review by the ENGINEER or the OWNER and OWNER's Authorized Representative.
1.5 COST LOADING
A. Schedule of Values: Allocate a dollar value to each activity on the construction schedule as specified. Include in dollar value the cost of labor, equipment, and material, and a pro rata contribution to overhead and profit. The sum of the activities cost shall be equal to the total contract price. In submitting cost data the CONTRACTOR certifies that it is not unbalanced and that the value assigned to each activity represents the CONTRACTOR's estimate of the actual costs of performing that activity.
B. Documentation: If, in the opinion of the ENGINEER, the cost data does not meet the requirements for a balanced Contract Price breakdown, present documentation to the ENGINEER substantiating any cost allocation. If an activity on the construction schedule has been assigned a disproportionate allocation of direct costs, overhead and profit the cost allocations will be considered unbalanced.
1.6 PROGRESS OF THE WORK
A. Delays to Critical Path: Whenever it becomes apparent from the current monthly CPM Schedule update that delays to the critical path have resulted and these delays are through no fault of the OWNER, and hence, that the Contract completion date will not be met, or when so directed by the OWNER, take one or more of the following actions to improve the Completion Date at no additional cost to the OWNER.
1. Increase construction labor in such quantities…