This document is a comprehensive set of contract documents for the City of Scranton's ADA Bathroom Renovations project at City Hall, prepared by Reilly Associates. The project involves renovating a compact 55-square-foot bathroom to maximize space efficiency and ensure ADA compliance, with a full demolition of existing fixtures and updating of plumbing and electrical systems. Sealed bids will be received online via the City's e-Procurement Portal until 10:00 am on Thursday, September 25, 2025, with a bid opening to be conducted in City Council Chambers and livestreamed on YouTube. The contract specifies a substantial completion timeline of 50 days after contract commencement, with a total contract completion period of 60 days, and includes liquidated damages of $500 per day for delays.

The project is funded through the City of Scranton's Department of Economic and Community Development and will be awarded to the lowest responsive bidder. Bidders must register on the city's e-Procurement Portal to access documents and submit proposals, with all bid documents required to be uploaded electronically. The contract includes prevailing wage requirements under the Davis-Bacon Act, with wage rates specified for various labor classifications. Contractors must comply with Pennsylvania state requirements, including the Steel Products Procurement Act, Pennsylvania Human Relations Act, and provide necessary bonds and insurance. The estimated project budget and specific funding sources are not explicitly detailed in the documents, but the project appears to be a municipal infrastructure improvement initiative focused on enhancing accessibility in a public building.

View the file

Other files for this state and local contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents Page 00010-1 of 00010-1

TABLE OF CONTENTS

Section Number

Title

Page Number

INTRODUCTORY INFORMATION

00010 Table of Contents 00010-1 to 00010-1 00015 List of Drawings 00015-1 to 00015-1

BIDDING REQUIREMENTS

00200 Instructions to Bidders 00200-1 to 00200-9 00410 Bid Form (Reference Only) 00410-1 to 00410-1 00430 Bid Bond (Penal Sum Form) 00430-1 to 00430-2

CONTRACT DOCUMENTS

00510 Notice of Award 00510-1 to 00510-1 00520 Form of Agreement 00520-1 to 00520-7 00550 Notice to Proceed 00550-1 to 00550-1 00610 Performance Bond 00610-1 to 00610-3 00615 Payment Bond 00615-1 to 00615-3 00620 Contractor’s Application for Payment 00620-1 to 00620-4 00625 Certificate of Substantial Completion 00625-1 to 00625-1 00650 Consent of Surety to Final Payment Form 00650-1 to 00650-1 00700 Standard General Conditions of the Construction

Contract 00700-1 to 00700-65

00800 Supplementary Conditions 00800-1 to 00800-19 00820 Additional State, Federal or Funding Agency

Requirements 00820-1 to 00820-5

00830 Permits 00830-1 to 00830-1 00840 Wage Rate Requirements 00840-1 to 00840-10 00940 Work Change Directive 00940-1 to 00940-1 00941 Change Order 00941-1 to 00941-2 00942 Field Order 00942-1 to 00942-1

List of Drawings Page 00015- 1 of 00015-1

LIST OF DRAWINGS

SCRANTON CITY HALL ADA BATHROOM RENOVATION

CITY OF SCRANTON

Drawing No. DESCRIPTION

COVER SHEET

G-001 GENERAL NOTES

A-101 DEMOLITION AND PROPOSED ADA BATHROOM PLAN

A-102 PROPOSED FLOORING AND CEILING PLAN

A-103 SCHEDULE, ELEVATIONS AND DETAILS

Instructions to Bidders Page 00200-i

INSTRUCTIONS TO BIDDERS

Page ARTICLE 1 – Defined Terms

ARTICLE 2 – Copies of Bidding Documents

ARTICLE 3 – Qualifications of Bidders

ARTICLE 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

ARTICLE 5 – Bidder’s Representations

ARTICLE 6 – Pre-Bid Conference

ARTICLE 7 – Interpretations and Addenda

ARTICLE 8 – Bid Security

ARTICLE 9 – Contract Times

ARTICLE 10 – Liquidated Damages

ARTICLE 11 – Substitute and “Or-Equal” Items

ARTICLE 12 – Subcontractors, Suppliers, and Others

ARTICLE 13 – Preparation of Bid

ARTICLE 14 – Basis of Bid

ARTICLE 15 – Submittal of Bid

ARTICLE 16 – Modification and Withdrawal of Bid

ARTICLE 17 – Opening of Bids

ARTICLE 18 – Bids to Remain Subject to Acceptance

ARTICLE 19 – Evaluation of Bids and Award of Contract

ARTICLE 20 – Bonds and Insurance

ARTICLE 21 – Signing of Agreement

ARTICLE 22 – Wage Rate Requirements

ARTICLE 23 – Disadvantage Business Enterpirse (DBE) Solicitation Requirements

ARTICLE 24 – Other State, Federal & Funding Agency Requirements

Page 00200-1 of 00200-9

This document was generated from the EJCDC® C-200 (Rev. 1), Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. The original form of this document has been modified herein for this specific project.

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the number and format stated in the invitation or advertisement to bid.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall complete and submit with its Bid the Bidder Qualification Statement included with the Bidding Documents. In addition, within the times indicated in the General Conditions, as may be modified by the Supplementary Conditions, Bidder shall submit a listing of proposed Subcontractors to be utilized on the project along with similar qualifications and responsibility information on all Subcontractors.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

4.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

Page 00200-2 of 00200-9

4.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify:

a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.

b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

c. reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings. Bidder is responsible for all reproduction costs associated with requested reports and drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or adjacent to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.

4.03 Site Visit and Testing by Bidders

A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.

B. Bidder is responsible to obtain such additional or supplementary examinations, investigations, test borings, explorations, tests, studies and data concerning conditions (surface, subsurface and underground facilities) at or contiguous to the Site or otherwise, which may affect (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety

Page 00200-3 of 00200-9 precautions and programs or which the Bidder deems necessary to assume all risks in excavating for the Project and determine its bid for the Work.

C. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.

D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

4.04 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. As the General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.

4.05 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 5 – BIDDER’S REPRESENTATIONS

5.01 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;

B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;

C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;

D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures, if any, at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings;

Page 00200-4 of 00200-9

E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings, if any, identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;

F. obtain such additional or supplementary examinations, investigations, test borings, explorations, tests, studies and data concerning conditions (surface, subsurface and underground facilities) at or contiguous to the Site or otherwise, which may affect (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs or which Bidder deems necessary to assume all risks in excavating for the Project and determine its bid for the Work;

G. agree, based on the information and observations referred to in the preceding paragraphs, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

H. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

I. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;

J. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work;

and

K. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

ARTICLE 6 – PRE-BID CONFERENCE

6.01 Pre-Bid conference requirements and details are stated in the invitation or advertisement to bid.

If a conference is planned and listed as mandatory in the invitation or advertisement to bid, Bids will not be accepted from any Bidder that did not attend the mandatory conference.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 Refer to Project ID on the City of Scranton portal, Procurement Portal (opengov.com), 2. General Information, 3. General Conditions and 5. Proposal Requirements.

7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.

https://procurement.opengov.com/portal/scrantonpa

Page 00200-5 of 00200-9

ARTICLE 8 – BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s total of all Bid prices for each bid (not including bid alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and 6.02 of the General Conditions.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 10 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.

ARTICLE 9 – CONTRACT TIMES

9.01 The number of days within which, or the dates by which, Milestones are to be achieved and the Work is to be substantially completed, and completed and ready for final payment, are set forth in the Agreement.

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.

11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly

Page 00200-6 of 00200-9 in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.

12.03 The apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of the Subcontractors or Suppliers proposed for the various portions of the Work. If requested by Owner, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, without an increase in Bid price.

12.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.

ARTICLE 13 – PREPARATION OF BID

13.01 The Bid Pricing Table shall be uploaded to the City of Scranton portal, Procurement Portal (opengov.com)

13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate seal shall be affixed and attested by the corporate secretary or an assistant corporate secretary.

The corporate address and state of incorporation shall be shown.

13.03 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The partnership’s address for receiving notices shall be shown.

13.04 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the firm’s address for receiving notices shall be shown.

13.05 A Bid by an individual shall show the Bidder’s name and address for receiving notices.

13.06 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture’s address for receiving notices shall be shown.

13.07 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

Page 00200-7 of 00200-9

ARTICLE 14 – BASIS OF BID

14.01 Lump Sum

A. Bidders shall submit a Bid on a lump sum basis as set forth in the online Bid Form.

ARTICLE 15 – SUBMITTAL OF BID

15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 7 of the Bid Form.

15.02 A Bid shall be received no later than the date and time prescribed and at the place indicated in the invitation or advertisement to bid and shall be enclosed in a plainly marked package with the Project title, the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid shall be addressed as described in the invitation or advertisement to bid.

15.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted at least sixty minutes prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.

16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

ARTICLE 17 – OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the invitation or advertisement to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

Page 00200-8 of 00200-9

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.

19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.

19.03 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.

C. In the comparison of Bids, alternates will be applied in an order of priority as established solely by Owner. After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its base Bid and the combination of its additive alternate Bids as established by Owner.

19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 20 – BONDS AND INSURANCE

20.01 Refer to City of Scranton RFP, 3. General Conditions, Q. Proposal Insurance Requirements.

ARTICLE 21 – SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 10 days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner. Within ten days thereafter, Owner shall deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

ARTICLE 22 – WAGE RATE REQUIREMENTS

22.01 Refer to Section 00840 for any wage rate requirements applicable to this contract.

Page 00200-9 of 00200-9

ARTICLE 23 – DISADVANTAGE BUSINESS ENTERPIRSE (DBE) SOLICITATION REQUIREMENTS

23.01 Refer to Project ID on the City of Scranton portal, Procurement Portal (opengov.com), 2. General Information, 3. General Conditions and 5. Proposal Requirements.

ARTICLE 24 – OTHER STATE, FEDERAL & FUNDING AGENCY REQUIREMENTS

24.01 Refer to Section 00820 and to Project ID on the City of Scranton portal, Procurement Portal (opengov.com), 2. General Information, 3. General Conditions and 5. Proposal Requirements, for any other State, Federal or Funding Agency requirements.

ITEM

NO. DESCRIPTION UNIT EST

QUANTITY BID LS PRICE TOTALBID

PRICE

Demolition: Approximate 55 sq.ft. of floor area (8’-0” Ceiling height) The contents of bathroom area to be removed including ceiling and wall tiles.

Existing Bathroom Door to be removed and salvaged for Historical Use (Note: Floor to stay in place)

LS 1

General Construction: New Ceiling Grid to be installed (See Plan A- 102),Epoxy 55 sq.ft. of Bathroom floor, All Areas to be painted (color to owners liking), New Floor drain replacement within existing location ,Install a new bathroom door with ADA hardware, Construction of new walls (drywall/painted)

LS 1

Plumbing: Cap existing sanitary and waterlines that will be abandoned, Install New ADA Water Closet within existing floor location ,Install New ADA sink (location according to plan)

LS 1

4 Electrical: Existing wire to be terminated as noted. Existing lights remain and tie into new sensor upon proposed door entry. LS 1

BASE BID

TOTAL OF BASE BID

Bid Form Page 00410-1 of 00410-1

FOR REFERENCE ONLY - UPLOAD PRICING EXCEL FORM TO THE ONLINE

PROJECT PORTAL, https://procurement.opengov.com/portal/scrantonpa

City Hall Building - ADA Bathroom Renovations

PENAL SUM FORM

EJCDC® C-430, Bid Bond (Penal Sum Form). Published 2013.

Prepared by the Engineers Joint Contract Documents Committee.

Page 00430-1 of 00430-2

BID BOND

Any singular reference to Bidder, Surety, Owner or other party shall be considered plural where applicable.

BIDDER (Name and Address):

SURETY (Name, and Address of Principal Place of Business):

OWNER (Name and Address):

BID

Bid Due Date:

Description (Project Name— Include Location):

BOND

Bond Number:

Date:

Penal sum $ (Words) (Figures) Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

BIDDER SURETY

(Seal) (Seal) Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (Attach Power of Attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

Title Title Note: Addresses are to be used for giving any required notice.

Provide execution by any additional parties, such as joint venturers, if necessary.

PENAL SUM FORM

EJCDC® C-430, Bid Bond (Penal Sum Form). Published 2013.

Prepared by the Engineers Joint Contract Documents Committee.

Page 00430-2 of 00430-2

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond shall be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation shall be null and void if:

3.1 Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2 All Bids are rejected by Owner, or

3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from the Bid due date without Surety’s written consent.

6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after the Bid due date.

7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect.

11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable.

Date:

VIA EMAIL ONLY

Bidder:

Bidder Address:

Re: Notice of Intent to Award Project: ______________________________________________________________

Dear Bidder:

Thank you for submitting your bid on ______________ for the above-mentioned project.

I want to personally congratulate you on being the apparent successful bidder for this project in the amount of _________________________________________________________________.

We will prepare the required contract between ______________________________and the City of Scranton in order for you to begin work on the _______________________________ _______________________________ project. Do not begin work until all parties properly sign all contracts.

We will contact you in order for you to sign the contract for this project to begin in a timely manner. Please be sure to provide a full list of all sub-contractors, if any, that will be working on this project, as well as your Performance and Payment Bonds, Certificate of Insurance, and any other Contract documents.

If you have any questions concerning this project, please do not hesitate to contact us.

Sincerely, Eileen Cipriani Business Administrator City of Scranton

Form of Agreement Between Owner and Contractor for Construction Contract (Stipulated Price) Page 00520-1 of 00520-7

FORM OF AGREEMENT

BETWEEN OWNER AND CONTRACTOR

FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)

THIS AGREEMENT is by and between City of Scranton (“Owner”) and

(“Contractor”).

Owner and Contractor hereby agree as follows:

ARTICLE 1 – WORK

1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The base scope of work for this project includes: Renovation of the compact 55-square-foot bathroom, designed to maximize space efficiency, which will also include the area to be ADA compliant with Baby changing table. The project will consist of a full demolition of the existing fixtures, and outdated finishes. Plumbing and electrical systems will stay in place and be modified according to plan and brought to code.

ARTICLE 2 – THE PROJECT

2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: Renovation of the compact 55-square-foot bathroom, designed to maximize space efficiency, which will also include the area to be ADA compliant with Baby changing table. The project will consist of a full demolition of the existing fixtures, and outdated finishes. Plumbing and electrical systems will stay in place and be modified according to plan and brought to code.

ENGINEER

2.02 The part of the Project that pertains to the Work has been designed by Reilly Associates.

2.03 The Owner has retained Reilly Associates (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents.

ARTICLE 3 – CONTRACT TIMES

3.01 Time of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

3.02 Contract Times: Days

A. The Work will be substantially completed by 50 days after the date when the Contract Times commence to run as provided in Paragraph 4.01 of the General Conditions, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions by 60 days after the date when the Contract Times commence to run.

B. Parts of the Work shall be substantially completed on or before the following Milestone(s):

N/A

Page 00520-2 of 00520-7

3.03 Liquidated Damages

A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with the Contract. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):

1. Substantial Completion: Contractor shall pay Owner $_500______ for each day that expires after the time (as duly adjusted pursuant to the Contract) specified in Paragraph 4.02.A above for Substantial Completion until the Work is substantially complete.

2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $___500____ for each day that expires after such time until the Work is completed and ready for final payment.

3. Liquidated damages for failing to timely attain Substantial Completion and final completion are not additive and will not be imposed concurrently.

ARTICLE 4 – CONTRACT PRICE

4.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents the amounts that follow, subject to adjustment under the Contract:

A. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.

ARTICLE 5 – PAYMENT PROCEDURES

5.01 Submittal and Processing of Payments

A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.

5.02 Progress Payments; Retainage

A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on or about the 2nd Tuesday of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.

1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.

Page 00520-3 of 00520-7

a. 90 percent of Work completed (with the balance being retainage). If the Work has been 50 percent completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, the retainage may be reduced to 5 percent; and

b. 90 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage) provided the quantity of stored material does not exceed the total estimated quantity required to complete the project, the cost is at least $1,000 but does not exceed 90 percent of the contract price of the applicable contract item and/or component item, and the accumulative costs do not exceed 25 percent of the current contract amount. The cost of the material is that amount to be paid by the Contractor as evidenced by invoices. Fabricated structural steel that is to receive a protective coating may be approved for prepayment at 75 percent of the contract price of the applicable contract item, before application of the coating, provided the structure has been fully fabricated and preassembly of field connections has been made.

B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 150 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.

5.03 Final Payment

A. Upon final completion and acceptance of the Work in accordance with Paragraph 15.06 of the General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 15.06.

ARTICLE 6 – INTEREST

6.01 All amounts not paid when due shall bear interest at the rate of 0.5 percent plus the Federal short-term rate as determined under Title 26, Subtitle F, Chapter 67, Subchapter C, § 6621 of the U.S.

Code.

ARTICLE 7 – CONTRACTOR’S REPRESENTATIONS

7.01 In order to induce Owner to enter into this Contract, Contractor makes the following representations:

A. Contractor has examined and carefully studied the Contract Documents, and any data and reference items identified in the Contract Documents.

B. Contractor has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

C. Contractor is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work.

D. Contractor has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures, if any, at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and

Page 00520-4 of 00520-7 drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings.

E. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Site-related reports and drawings, if any, identified in the Contract Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (3) Contractor’s safety precautions and programs.

F. Contractor has obtained such additional or supplementary examinations, investigations, test borings, explorations, tests, studies and data concerning conditions (surface, subsurface and underground facilities) at or contiguous to the Site or otherwise, which may affect (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Contractor Documents; and (3) Contractor’s safety precautions and programs or which Contractor deems necessary to assume all risks in excavating for the Project and determine its bid for the Work.

G. Based on the information and observations referred to in the preceding paragraphs, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

H. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.

I. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

J. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

K. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.

ARTICLE 8 – CONTRACT DOCUMENTS

8.01 Contents

A. The Contract Documents consist of the following:

1. This Agreement (pages 00520-1 to 00520-__7_, inclusive).

2. Performance bond (pages 00610-1 to 00610-3, inclusive).

3. Payment bond (pages 00615-1 to 00615-3, inclusive).

4. Other bonds.

a. None

Page 00520-5 of 00520-7

5. General Conditions (pages 00700-1 to 00700-65, inclusive) (not attached but incorporated by reference).

6. Supplementary Conditions (pages 00800-1 to 00800-_16__, inclusive) (not attached but incorporated by reference).

7. Additional State, Federal or Funding Agency Requirements (pages 00820-1 to 00820- _5__, inclusive) (not attached but incorporated by reference).

8. Permits as listed in the table of contents of the Project Manual (not attached but incorporated by reference).

9. Wage Rate Requirements (pages 00840-1 to 00840-10, inclusive) (not attached but incorporated by reference).

10. Specifications as listed in the table of contents of the Project Manual (not attached but incorporated by reference).

11. The Drawings as listed in the table of contents of the Project Manual (not attached but incorporated by reference).

12. Addenda (numbers ___ to ___, inclusive).

13. Exhibits to this Agreement (enumerated as follows):

a. Contractor’s Bid

14. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto:

a. Notice to Proceed.

b. Contractor’s Application for Payment

c. Certificate of Substantial Completion

d. Consent of Surety to Final Payment

e. Work Change Directives.

f. Change Orders.

g. Field Orders.

B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly noted otherwise above).

C. There are no Contract Documents other than those listed above in this Article 9.

D. The Contract Documents may only be amended, modified, or supplemented as provided in the General Conditions.

ARTICLE 9 – MISCELLANEOUS

9.01 Terms

A. Terms used in this Agreement will have the meanings stated in the General Conditions and the Supplementary Conditions.

9.02 Assignment of Contract

A. Unless expressly agreed to elsewhere in the Contract, no assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without

Page 00520-6 of 00520-7 the written consent of the party sought to be bound; and, specifically but without limitation, money that may become due and money that is due may not be assigned without such consent (except to the extent that…