2025 0124 BHS District-wide Roofing Addendum #1.pdf
PDF 7 MB Posted
- Attached to
- RFP #1050 2025 Roofing BHHS, Conant and Eastover
- Solicitation number
- RFP #1050
- Issued by
- Berrien County, Blissfield Village, Michigan
About this file
This document is an Addendum #1 for the Bloomfield Hills Schools District-Wide Roofing Replacement project (Project No. 6524, RFP #1050), issued by Ehresman Architects on January 24, 2025. The project involves comprehensive roof replacements at three district schools: Bloomfield Hills High School (roof sections O, S, T, V, totaling approximately 9,618 sq ft), Conant Elementary School (roof sections D1, E, F, G, H, I, J, totaling approximately 23,067 sq ft), and Eastover Elementary School (roof section B, approximately 23,235 sq ft). The roofing work includes complete removal down to existing roof decks, installing new insulation, and applying EPDM roofing (with the exception of a shingle roof section at Conant). The bid due date is February 4, 2025, at 1:00 p.m. local time, with an anticipated project award date of February 24, 2025, and on-site operations scheduled to start June 16, 2025, with substantial completion by August 15, 2025.
The addendum introduces an alternate bid item for floor protection at Conant Elementary School, specifically requiring plastic sheeting (Visqueen) for roof areas G and I due to acoustical metal decks. Each base bid includes a specific allowance: $25,000 for Bloomfield Hills High School, $50,000 for Conant Elementary School, and $25,000 for Eastover Elementary School. Bidders are requested to provide unit pricing for various potential additional work, such as deck replacement, repairs, and material additions. The project requires a 5% bid bond, and performance and labor & material payment bonds for 100% of the contract amount. The bid is a fixed stipulated sum, with separate costs requested for each building and potential deductions if the contractor is awarded two or three buildings.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
e h r e s m a n a r c h i t e c t s . c o m
801 W. Big Beaver Road, Suite 250, Troy, MI 48084 | 248.244.9710 | (f ) 248.244.9712
ADDENDUM
Project: Bloomfield Hills Schools District-Wide Roofing Replacement
Project No.: 6524 (RFP #1050)
Date: January 24, 2025
Addendum Number: 1
Each Bidder's proposal amount shall include the work described herein.
This Addendum is hereby made a part of the Contract Documents. Unless otherwise indicated, the work described herein shall comply with, and be equal in all respects to the original Specification and Drawings accompanying same. Include incidental work required to properly complete the work, whether stated herein or not.
DRAWING REVISIONS
TTL – Title Sheet ADD: List Alternates provisions
LIST OF ALTERNATES:
Alternate #1: Plastic Sheeting Floor Protection Add to the Base Bid #2 (Conant Elementary School) to provide plastic sheeting (Visqueen) to protect floor below from dust and debris. Contractor to place sheeting and remove after roofing operations. Owner will provide the final construction cleaning. Contractor to refer to specifications for further information.
B2.51 – Bloomfield Hills High School Enlarged Roof Plan ADD: General Note G24
G24. Contractor to protect owner's existing asphalt / concrete paving and/or lawn areas from construction traffic. If damage should occur, contractor is responsible to coordinate and pay for all repairs to bring the item back to the condition before construction commenced. It shall be the owner’s option to have their vendor make any repairs, and the contractor's contract will be reduced via change order to cover such repairs.
ADD: Work Note #35
35. Prefinished metal gutter and downspout to grade. Slope gutter to downspout location and provide concrete splash block on grade.
ADD: Work Note #36
36. At acoustical metal deck locations, contractor to provide plastic sheeting (visqueen) to protect floor below from dust and debris. Contractor to place sheeting and remove after roofing operations. Owner will provide the final construction cleaning. Refer to alternate #1 for further information.
C2.51 – Conant Elementary School Enlarged Roof Plan ADD: General Note G24
G24. Contractor to protect owner's existing asphalt / concrete paving and/or lawn areas from construction traffic. If damage should occur, contractor is responsible to coordinate and pay for all repairs to bring the item back to the condition before construction commenced. It shall be the owner’s option to have their vendor make any repairs, and the contractor's contract will be reduced via change order to cover such repairs.
ADD: Work Note #35
35. Prefinished metal gutter and downspout to grade. Slope gutter to downspout location and provide concrete splash block on grade.
ADD: Work Note #36
36. At acoustical metal deck locations, contractor to provide plastic sheeting (visqueen) to protect floor below from dust and debris. Contractor to place sheeting and remove after roofing operations. Owner will provide the final construction cleaning. Refer to alternate #1 for further information.
ADD: Work Note #36 to roof area G
C2.52 – Conant Elementary School Enlarged Roof Plan ADD: General Note G24
G24. Contractor to protect owner's existing asphalt / concrete paving and/or lawn areas from construction traffic. If damage should occur, contractor is responsible to coordinate and pay for all repairs to bring the item back to the condition before construction commenced. It shall be the owner’s option to have their vendor make any repairs, and the contractor's contract will be reduced via change order to cover such repairs.
ADD: Work Note #35
35. Prefinished metal gutter and downspout to grade. Slope gutter to downspout location and provide concrete splash block on grade.
ADD: Work Note #36
36. At acoustical metal deck locations, contractor to provide plastic sheeting (visqueen) to protect floor below from dust and debris. Contractor to place sheeting and remove after roofing operations. Owner will provide the final construction cleaning. Refer to alternate #1 for further information.
ADD: Work Note #36 at several locations to roof area I REVISE: Drawing 2/C2.52 (Roof Area D.1) and notes as indicated.
E2.51 – Eastover Elementary School Enlarged Roof Plan ADD: General Note G24
G24. Contractor to protect owner's existing asphalt / concrete paving and/or lawn areas from construction traffic. If damage should occur, contractor is responsible to coordinate and pay for all repairs to bring the item back to the condition before construction commenced. It shall be the owner’s option to have their vendor make any repairs, and the contractor's contract will be reduced via change order to cover such repairs.
ADD: Work Note #35
35. Prefinished metal gutter and downspout to grade. Slope gutter to downspout location and provide concrete splash block on grade.
ADD: Work Note #36
36. At acoustical metal deck locations, contractor to provide plastic sheeting (visqueen) to protect floor below from dust and debris. Contractor to place sheeting and remove after roofing operations. Owner will provide the final construction cleaning. Refer to alternate #1 for further information.
SPECIFICATION REVISIONS
Attachment A – Proposal Form ADD: Item C under section 1.02 – Bid Documents C. Requirements for Alternate Bids:
1. The Bidder is required to provide a bid price for each Alternate Work Item that includes any change in cost that may be incurred, or adjustment that may be required, if Alternate Work items are added to the scope of the project. No subsequent “extras” will be considered for coordination or incidentals required to complete Alternate Bid Work items.
2. Award of this contract will be based upon the Base Bid or Base Bid and Alternate Work Items as selected by the Owner.
3. All selected Alternate Work Items must be completed within the contract schedule included in Part E of this Section.
ADD: Item D under section 1.02 – Bid Documents D. Lump Sum Pricing for Alternate Work Items Alternate Bid – Item #C1 – Add to the Base Bid #2 (Conant Elementary School) to provide plastic sheeting (Visqueen) to protect floor below from dust and debris. Contractor to place sheeting and remove after roofing operations. Owner will provide the final construction cleaning. Approximate floor area to be covered is 1,590 sf (Roof Area G) and 4,386 sf (Roof Area I)
CLARIFY: Subsequent sections under 1.02 previously included have been re-numbered accordingly due to the above insertions.
CLARIFY: Item F under section 1.02 – Bid Documents to add a line for each Base Bid to indicate the cost of the bonds that has been included within the Base Bid amounts for each building.
Section 00 0110 – Table of Contents ADD: Item F under section 2.01 Division 01 – General Requirements F. 01 2300 – Alternates
Section 01 2300 - Alternates ADD: Entire specification section as new (previously not included)
Section 07 5323 - EPDM Thermoset Single-Ply Roofing – Carlisle CHANGE: Section 1.01, Part A FROM: The Bloomfield Hills School District Roof Replacement Project includes two different schools. Schools included are: Way Elementary and Eastover Elementary.
Jacob McDermott will act as the Owner’s Representative and may be contacted regarding any questions or for a pre-bid job site inspection.
TO: The Bloomfield Hills School District Roof Replacement Project includes three different schools. Schools included are: Bloomfield Hills High School, Conant Elementary School, and Eastover Elementary School. Jacob McDermott will act as the Owner’s Representative and may be contacted regarding any questions or for a pre-bid job site inspection.
GENERAL
Non-Mandatory Pre-Bid Meeting Bidders sign-in list is attached for reference for those that attended the non-mandatory pre-bid meeting.
Pre-Bid Meeting Agenda Agenda is attached for reference only as an outline of our meeting. No information in the agenda should be considered binding. Refer to drawings and specifications for contractual conditions.
Pre-bid Meeting Questions and Answers Question 1: On Roof Area “I” at Conant, is that phenolic insulation?
Answer 1: It appears that it might be, but this has not been confirmed. It would be up to the contractor to perform its own roof cores to verify. Refer to General Note G9 on the enlarged roof plans for note relating to this.
Question 2: Are there site improvement projects (i.e. parking lots, playgrounds) that will be occurring at these schools this summer?
Answer 2: No, there are no site improvements being done at any schools, just interior work.
Clarifications Item 1: Contractor will coordinate and work with Owner’s separate mechanical and electrical contractors for rooftop items that are required to be raised, modified, abandoned, etc. These companies will be paid by the contractor from the allowances included. A coordination meeting will occur after contract-award for all parties to identify each component that needs to be raised, modified, abandoned, etc. Any unused and/or abandoned items that are identified will be removed by the roofing contractor.
Item 2: Any existing abandoned equipment rail, capped curb, sanitary vents, etc. should be removed if possible (whether particularly indicated on the drawings or not).
Item 3: Contractor is responsible to infill the roof deck at all removed caps, removed skylights, etc. as specified on the documents.
Item 4: Due to the inclement weather, site visits are going to be scheduled for Monday. The plan will be to start at Conant Elementary School at 10:00 a.m., then follow to Bloomfield Hills High School then Eastover Elementary School. It is anticipated that we will spend approximately 30-minutes at each building.
© Ehresman Architects
TTLProject No. 6524
Bloomfield Hills Schools District-Wide Roofing Replacement
Title Sheet
Addendum #1: 24 January 2025
Permits & Bidding: 21 January 2024
Bloomfield Hills Schools 281 Enterprise Court, Suite 300 Bloomfield Hills, MI 48303 Contact Name: Mr. Jacob McDermott
Director of Physical Plant Services Contact Phone: (248) 420-7504
ARCHITECT:
LOCATION PLAN
NOT TO SCALE
LOCATION PLAN
NOT TO SCALE
APPLICABLE CODES:
MICHIGAN REHABILITATION CODE FOR EXISTING BUILDINGS: 2015 EDITION
MICHIGAN ENERGY CODE: 2015 EDITION
ASHRAE 90.1-2013:
USE GROUP:
GROUP E: EDUCATIONAL
LIST OF DRAWINGS
ARCHITECTURAL DRAWINGS:
TTL TITLE SHEET
A0.00 GENERAL INFORMATION
A0.50 MANUFACTURER'S ROOFING DETAILS
A0.51 MANUFACTURER'S ROOFING DETAILS
A0.52 MANUFACTURER'S ROOFING DETAILS
B0.01 BLOOMFIELD HILLS HIGH SCHOOL REPRESENTATIVE PHOTOGRAPHS
B0.02 BLOOMFIELD HILLS HIGH SCHOOL REPRESENTATIVE PHOTOGRAPHS
B2.50 BLOOMFIELD HILLS HIGH SCHOOL ROOF PLAN
B2.51 BLOOMFIELD HILLS HIGH SCHOOL ENLARGED ROOF PLAN
B2.52 BLOOMFIELD HILLS HIGH SCHOOL INSULATION LAYOUT PLAN (FOR REFERENCE ONLY)
C0.01 CONANT ELEMENTARY SCHOOL REPRESENTATIVE PHOTOGRAPHS
C0.02 CONANT ELEMENTARY SCHOOL REPRESENTATIVE PHOTOGRAPHS
C0.03 CONANT ELEMENTARY SCHOOL REPRESENTATIVE PHOTOGRAPHS
C2.50 CONANT ELEMENTARY SCHOOL ROOF PLAN
C2.51 CONANT ELEMENTARY SCHOOL ENLARGED ROOF PLAN
C2.52 CONANT ELEMENTARY SCHOOL ENLARGED ROOF PLAN
C2.53 CONANT ELEMENTARY SCHOOL INSULATION LAYOUT PLAN (FOR REFERENCE ONLY)
E0.01 EASTOVER ELEMENTARY SCHOOL REPRESENTATIVE PHOTOGRAPHS
E2.50 EASTOVER ELEMENTARY SCHOOL ROOF PLAN
E2.51 EASTOVER ELEMENTARY SCHOOL ENLARGED ROOF PLAN
E2.52 EASTOVER ELEMENTARY SCHOOL INSULATION LAYOUT PLAN (FOR REFERENCE ONLY)
Conant Elementary School 4100 West Quarton Road Bloomfield Hills, MI 48302
ROOF PLAN
NOT TO SCALE
Eastover Elementary School 2800 Kensington Road Bloomfield Hills, MI 48304
ROOF PLAN
NOT TO SCALE
BLOOMFIELD HILLS SCHOOLS
District-Wide Roofing Replacement
LOCATION PLAN
NOT TO SCALE
Bloomfield Hills High School 4200 Andover Road Bloomfield Hills, MI 48302
ROOF PLAN
NOT TO SCALE
LIST OF ALTERNATES:
ALTERNATE #1: PLASTIC SHEETING FLOOR PROTECTION
ADD TO THE BASE BID #2 (CONANT ELEMENTARY SCHOOL) TO PROVIDE PLASTIC SHEETING
(VISQUEEN) TO PROTECT FLOOR BELOW FROM DUST AND DEBRIS. CONTRACTOR TO PLACE
SHEETING AND REMOVE AFTER ROOFING OPERATIONS. OWNER WILL PROVIDE THE FINAL
CONSTRUCTION CLEANING. CONTRACTOR TO REFER TO SPECIFICATIONS FOR FURTHER
INFORMATION.
GASGASGASGAS
GAS
GAS
GA
S
GA
S
GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS
GAS
WORK NOTES:
1.
GENERAL NOTES:
DO NOT SCALE DRAWING. DRAWING SCALE IS SHOWN FOR GENERAL REFERENCE ONLY.G1.
G2. FIELD VERIFY ALL DIMENSIONS, ROOF SUMP LOCATIONS, EQUIPMENT CURBS, ETC. PRIOR TO
COMMENCING WITH CONSTRUCTION OPERATIONS.
THE ROOFING SHALL BE A TWENTY-FIVE (25) YEAR MANUF. ROOFING SYSTEM WARRANTY
ALONG WITH A FIVE (5) YEAR LABOR WARRANTY. EDGE METAL TO BE INCLUDED IN FULL
SYSTEM WARRANTY.
G3.
G4. REFER TO ROOF DETAILS AND MANUFACTURER'S STANDARD DETAILS FOR ADDITIONAL
INFORMATION.
G5. EXISTING ROOF DECK THICKNESS AND SLOPE IS UNKNOWN. CONTRACTOR TO VERIFY AFTER
THE ROOFING HAS BEEN REMOVED AND REPORT ANY DISCREPANCIES THAT MAY BE
DISCOVERED TO THE ARCHITECT / ROOFING SYSTEM REPRESENTATIVE FOR FURTHER
DIRECTION.
G6. ALL MECHANICAL EQUIPMENT CURBS SHALL HAVE NEW BASE FLASHING A MINIMUM OF 8"
ABOVE THE ROOFING MEMBRANE, UNLESS MORE STRINGENT REQUIREMENTS ARE NEEDED
TO MEET THE ROOFING MANUFACTURER SPECIFICATIONS. CONTRACTOR TO FIELD VERIFY
HEIGHT -- ASSUME THE EXISTING HVAC CURBS WILL NEED TO BE RAISED.
G7. INSTALL CRICKETS AT ALL EQUIPMENT CURBS HIGH SIDE, WHETHER SHOWN OR NOT.
G8. EXISTING EQUIPMENT, PENETRATIONS, ROOF DRAINS, CURBS, ETC. IDENTIFIED SHALL BE
FIELD VERIFIED BY THE CONTRACTOR WHOM WILL BE RESPONSIBLE FOR THE QUANTITIES,
CONDITIONS, HEIGHTS, ETC.
G9.
ANY EXISTING WOOD BLOCKING FOR ELECTRICAL CONDUIT AND/OR GAS PIPING SHALL BE
REPLACED WITH PROPER PREFABRICATED SUPPORT WHETHER PARTICULARLY INDICATED OR
NOT (NO WOOD BLOCKING IS PERMITTED).
G10.
CONTRACTOR TO VISIT THE SITE AND VERIFY ALL MEASUREMENTS, CONDITIONS, ETC. THAT
MAY AFFECT THE SPECIFIED WARRANTY.
G11.
AN ON-SITE PRE-CONSTRUCTION MEETING WITH THE ARCHITECT, ROOFING SYSTEM
REPRESENTATIVE, OWNER, AND CONTRACTOR SHALL BE CONDUCTED PRIOR TO THE START
OF CONSTRUCTION AND PRIOR TO ORDERING OF MATERIAL. REFER TO SPECIFICATIONS FOR
FURTHER INFORMATION.
G12.
CRICKET SLOPE TO BE 14" PER FOOT UNLESS NOTED OTHERWISE.
G13.
DRAINAGE SADDLES TO SLOPE 14" PER FOOT UNLESS NOTED OTHERWISE. CONTRACTOR TO
ASSURE POSITIVE DRAINAGE TO ROOF DRAINS / GUTTER EDGE.
RAISED MECHANICAL EXHAUST FAN UNIT / RELIEF HOOD AS REQUIRED TO MEET SYSTEM
WARRANTY REQUIREMENTS.
2.
PREFINISHED METAL CAP FLASHING (PRE-SLOPED)--REFER TO GENERAL NOTE G12.
3.
CRICKET AS REQUIRED TO PROVIDE DRAINAGE AT MECHANICAL ITEM, ETC. REFER TO
GENERAL NOTES G7 AND G19 FOR FURTHER INFORMATION.
4.
5.
6.
7.
PLUMBING VENT BOOT FLASHING (AND EXTENSION WHERE REQUIRED-C.F.V.).
8.
9.
HVAC STACK FLASHING TO SUIT CONDITIONS (C.F.V.).
10.
11.
12.
13.
14.
REMOVE EXISTING ROOFING SYSTEMS COMPETE DOWN TO EXISTING ROOF DECK.
INFORMATION ABOUT EXISTING ROOFING COMPOSITION IS FOR REFERENCE ONLY AND
SHOULD BE FIELD VERIFIED BY THE CONTRACTOR.
ROOFTOP DUCTWORK, GAS LINES, ELECTRICAL CONDUITS, ETC. MAY NOT BE INDICATED FOR
DRAWING CLARITY, BUT WILL REQUIRE RE-WORK AND MODIFICATIONS DUE TO THE WORK.
CONTRACTOR TO FIELD VERIFY ALL EXISTING CONDITIONS AND COORDINATE WITH OWNER.
PROVIDE PROPER SUPPORTS (ROLLER SUPPORTS, UNISTRUT PADS, ETC.).
CONTRACTOR WILL BE REQUIRED TO BUILD UP THE ROOF EDGE (PARAPET) AT MOST
LOCATIONS DUE TO INCREASED INSULATION HEIGHT. CONTRACTOR TO FIELD VERIFY AND
PROVIDE THE NECESSARY BLOCKING.
NEW EDGE FLASHING (PARAPET) MATERIAL IS TO BE FIELD VERIFIED WITH EXISTING WALL
CONDITIONS. WHERE ALUMINUM WALL PANELS EXIST, CONTRACTOR TO INSTALL ALUMINUM
CAP / FLASHINGS TO BE COMPATIBLE WITH WALL MATERIALS.
G14.
G15.
G16.
G17.
POLYISOCYANURATE HINGED TARGET SUMP AT EXISTING ROOF DRAIN LOCATION.
ROOF TO ROOF EXPANSION JOINT / AREA DIVIDER.
PATE EQUIPMENT SUPPORT RAILS FOR ROOFTOP HVAC ITEM (ROOFTOP CONDENSER).
PATE PIPE CURB ASSEMBLY FOR ROOFTOP HVAC ITEM (ROOFTOP CONDENSER LINESETS).
REMOVE EXISTING CURB AND COVER (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING
SYSTEM). CONTRACTOR TO CONFIRM WITH OWNER THAT ITEM IS ABANDONED PRIOR TO
REMOVAL.
ROOF EXPANSION JOINT / AREA DIVIDER.
REPLACE EXISTING ROOF HATCH WITH GALVANIZED ROOF HATCH WITH SAFETY RAILS AND
EASY-UP LADDER (IN EXISTING LOCATION). CONTRACTOR TO FIELD VERIFY EXISTING HATCH
SIZE AND REPLACE WITH SAME SIZE.
REPLACEMENT OF THE ROOF SHALL BE DONE SO-AS TO NOT REMOVE ANY MORE OF THE
ROOFING THAN CAN BE REPLACED IN A GIVEN DAY. AT NO TIME SHALL THE ROOF BE LEFT
OPEN AND SUBJECT TO WEATHER CONDITIONS. CONTRACTOR SHALL BE RESPONSIBLE FOR
ANY DAMAGE THAT OCCURS.
ANY UTILITY SHUT-DOWNS THAT ARE REQUIRED IN ORDER TO PERFORM THE RE-ROOFING
OPERATIONS SHALL BE SCHEDULED IN ADVANCE WITH THE OWNER.
CONTRACTOR TO ASSURE THAT ALL ROOF DRAINS ARE IN PROPER WORKING CONDITION
PRIOR TO COMPLETING THE RE-ROOFING OPERATIONS. REPORT ANY DISCREPANCIES TO THE
OWNER / ARCHITECT FOR FURTHER DIRECTION.
PROVIDE WALKWAY PADS / SLIP SHEETS UNDER ALL PIPE SUPPORTS.
G18.
G19.
G20.
G21.
REMOVE EXISTING PLUMBING VENT AND CAP BELOW ROOF PER CODE REQUIREMENTS
(ASSUMED ABANDONED). CONTRACTOR TO CONFIRM WITH OWNER THAT ITEM IS ABANDONED
PRIOR TO REMOVAL.
PITCH POCKET FOR EXISTING PENETRATION.
EXISTING PATE PIPE CURB TO REMAIN.
COUNTERFLASHING (MINIMUM 12" ABOVE MEMBRANE SURFACE).17.
CONTRACTOR TO PROVIDE SLIP FLASHING AT ALL UNITS AND AS REQUIRED.G22.
NOT ALL NOTES MAY APPLY TO THIS SHEET.G23.
15.
16.
WRAP ROOFING MEMBRANE UP FACE OF WALL AND UNDER EXISTING CAP FLASHING.
REMOVE AND REINSTALL FLASHING AS REQUIRED.
REMOVE EXISTING WOOD GUARDRAIL AROUND EXISTING SKYLIGHT.18.
REMOVE EXISTING SKYLIGHT (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING SYSTEM).19.
CONTRACTOR TO PROTECT OWNER'S EXISTING ASPHALT / CONCRETE PAVING AND/OR LAWN
AREAS FROM CONSTRUCTION TRAFFIC. IF DAMAGE SHOULD OCCUR, CONTRACTOR IS
RESPONSIBLE TO COORDINATE AND PAY FOR ALL REPAIRS TO BRING THE ITEM BACK TO THE
CONDITION BEFORE CONSTRUCTION COMMENCED. IT SHALL BE THE OWNER'S OPTION TO
HAVE THEIR VENDOR MAKE ANY REPAIRS, AND THE CONTRACTOR'S CONTRACT WILL BE
REDUCED VIA CHANGE ORDER TO COVER SUCH REPAIRS.
G24.
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· ADHESIVE APPLIED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER START)
· MECHANICALLY FASTENED ASPHALT BASE SHEET WITH IMPACT BASE SHEET FASTENERS
· EXISTING TECTUM ROOF DECK (ASSUMED FLAT)
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· MECHANICALLY FASTENED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER
START)
· SELF-ADHERING VAPOR BARRIER (AT ACOUSTICAL METAL DECK ONLY)
· EXISTING METAL / ACOUSTICAL METAL ROOF DECK (ASSUMED FLAT)
29.
REMOVE EXISTING SKYLIGHT (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING SYSTEM).
DRAINAGE SCUPPER THROUGH WALL.20.
19.
PREFINISHED METAL EDGE FLASHING--REFER TO GENERAL NOTE G12.21.
REMOVE AND REINSTALL EXISTING GUTTER SYSTEM AS NEEDED FOR ROOFING OPERATIONS.22.
EXISTING COPPER / METAL CAP AND RIDGE CAP TO REMAIN.23.
CONTRACTOR TO PROVIDE PRESERVATIVE TREATED WOOD BLOCKING AT LOCATION OF
ALUMINUM WALL PANELS DUE TO RAISED PARAPET HEIGHT (BASED ON PREVIOUS ROOF
REPLACEMENT, ALUMINUM WALL PANELS STOP SHORT AND REQUIRES ADDITIONAL
BLOCKING).
EXISTING ROOF EXPANSION JOINT METAL TO BE REMOVED AND REINSTALLED TO COMPLETE
ROOFING OPERATIONS.
25.
24.
26.
ROOFING SYSTEM COMPOSITION:
· ASPHALT SHINGLES
· ROOF DECK PROTECTION OVER ENTIRE ROOF AREA (ICE & WATER SHIELD)
· EXISTING ROOF DECK (UNKNOWN)
27.
PREFINISHED RIDGE / CAP FLASHING OVER EXISTING SLOPED METAL ROOF / WALL PANELS.28.
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· ADHESIVE APPLIED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER START)
· MECHANICALLY FASTENED ASPHALT BASE SHEET WITH IMPACT BASE SHEET FASTENERS
· EXISTING GYPSUM ROOF DECK (ASSUMED FLAT)
30.
EXISTING ELECTRICAL JUNCTION BOX TO REMAIN--INSTALL ROOF WALKWAY PAD / SLIP
SHEET UNDER JUNCTION BOX.
EXISTING WALL-MOUNTED LADDER TO BE REMOVED AND RELOCATED PER OWNER DIRECTED
LOCATION. CONTRACTOR TO MODIFY BRACKET(S) AS REQUIRED TO SUIT BUILDING
CONDITIONS. PATCH / REPAIR FASTENER HOLES IN EXISTING WALL PANELS / FLASHINGS,
ETC.
32.
31.
EXISTING STRUCTURAL COLUMN PENETRATION--PROVIDE MANUFACTURER'S TYPICAL I-BEAM
PENETRATION DETAIL.
33.
REMOVE AND REPLACE EXISTING ROOFING, BASE FLASHING, INSULATION, ETC. IN AREA
BETWEEN ROOF EDGE AND PARAPET.
34.
PREFINISHED METAL GUTTER AND DOWNSPOUT TO GRADE. SLOPE GUTTER TO DOWNSPOUT
LOCATION AND PROVIDE CONCRETE SPLASH BLOCK ON GRADE.
35.
AT ACOUSTICAL METAL DECK LOCATIONS, CONTRACTOR TO PROVIDE PLASTIC SHEETING
(VISQUEEN) TO PROTECT FLOOR BELOW FROM DUST AND DEBRIS. CONTRACTOR TO PLACE
SHEETING AND REMOVE AFTER ROOFING OPERATIONS. OWNER WILL PROVIDE THE FINAL
CONSTRUCTION CLEANING. REFER TO ALTERNATE #1 FOR FURTHER INFORMATION.
36.
30" x 30" WALKWAY PAD INSTALLED PER MANUFACTURER'S REQUIREMENTS. INTENT IS
FOR WALKWAY PADS TO BE INSTALLED AT ROOF HATCHES AND AROUND ALL HVAC
ROOFTOP UNITS.
LEGEND:
© Ehresman Architects
B2.51Project No. 6524
Bloomfield Hills Schools District-Wide Roofing Replacement
Enlarged Roof Plan
Addendum #1: 24 January 2025
Permits & Bidding: 21 January 2025
Bloomfield Hills High School
Scale: 1/8"=1'-0" Enlarged Roof Plan (Bloomfield Hills HS)
B2.51
ROOFTOP
HVAC
8" PER FOOT
TAPER INSULATION
8" PER FOOT
TAPER INSULATION
ROOF AREA "T" ROOF AREA "S"
ROOF AREA "V"
Scale: 1/8"=1'-0" Enlarged Roof Plan (Bloomfield Hills HS)
B2.51
ROOF AREA "O"
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 1" PERLITE INSULATION
· 2" POLYISOCYANURATE INSULATION
· EXISTING GYPSUM ROOF DECK
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 1" PERLITE INSULATION
· 2" POLYISOCYANURATE INSULATION
· EXISTING METAL ROOF DECK
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 1" PERLITE INSULATION
· 2" POLYISOCYANURATE INSULATION
· EXISTING GYPSUM ROOF DECK
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 1" PERLITE INSULATION
· 2" POLYISOCYANURATE INSULATION
· EXISTING GYPSUM ROOF DECK
REFER TO WORK NOTE #21
ROOFTOP
HVAC
8" PER
FOOT
TAPER
INSULATION
1 8" P
ER
FO
OT
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
FO
OT
TA
PE
R
IN
SU
LA
TI
ON
H
IG
H P
OI
N
T
HIGH POINT
8" PER FOOT
TAPER INSULATION
8" PER FOOT
TAPER INSULATION
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
REFER TO WORK NOTE #21
REFER TO WORK NOTE #34 IN THIS AREA
REFER TO NOTE #34
IN THIS AREA
GASGASGASGASGASGASGASGAS
GAS
GAS
GAS
GAS
GASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGAS
WORK NOTES:
1.
GENERAL NOTES:
DO NOT SCALE DRAWING. DRAWING SCALE IS SHOWN FOR GENERAL REFERENCE ONLY.G1.
G2. FIELD VERIFY ALL DIMENSIONS, ROOF SUMP LOCATIONS, EQUIPMENT CURBS, ETC. PRIOR TO
COMMENCING WITH CONSTRUCTION OPERATIONS.
THE ROOFING SHALL BE A TWENTY-FIVE (25) YEAR MANUF. ROOFING SYSTEM WARRANTY
ALONG WITH A FIVE (5) YEAR LABOR WARRANTY. EDGE METAL TO BE INCLUDED IN FULL
SYSTEM WARRANTY.
G3.
G4. REFER TO ROOF DETAILS AND MANUFACTURER'S STANDARD DETAILS FOR ADDITIONAL
INFORMATION.
G5. EXISTING ROOF DECK THICKNESS AND SLOPE IS UNKNOWN. CONTRACTOR TO VERIFY AFTER
THE ROOFING HAS BEEN REMOVED AND REPORT ANY DISCREPANCIES THAT MAY BE
DISCOVERED TO THE ARCHITECT / ROOFING SYSTEM REPRESENTATIVE FOR FURTHER
DIRECTION.
G6. ALL MECHANICAL EQUIPMENT CURBS SHALL HAVE NEW BASE FLASHING A MINIMUM OF 8"
ABOVE THE ROOFING MEMBRANE, UNLESS MORE STRINGENT REQUIREMENTS ARE NEEDED
TO MEET THE ROOFING MANUFACTURER SPECIFICATIONS. CONTRACTOR TO FIELD VERIFY
HEIGHT -- ASSUME THE EXISTING HVAC CURBS WILL NEED TO BE RAISED.
G7. INSTALL CRICKETS AT ALL EQUIPMENT CURBS HIGH SIDE, WHETHER SHOWN OR NOT.
G8. EXISTING EQUIPMENT, PENETRATIONS, ROOF DRAINS, CURBS, ETC. IDENTIFIED SHALL BE
FIELD VERIFIED BY THE CONTRACTOR WHOM WILL BE RESPONSIBLE FOR THE QUANTITIES,
CONDITIONS, HEIGHTS, ETC.
G9.
ANY EXISTING WOOD BLOCKING FOR ELECTRICAL CONDUIT AND/OR GAS PIPING SHALL BE
REPLACED WITH PROPER PREFABRICATED SUPPORT WHETHER PARTICULARLY INDICATED OR
NOT (NO WOOD BLOCKING IS PERMITTED).
G10.
CONTRACTOR TO VISIT THE SITE AND VERIFY ALL MEASUREMENTS, CONDITIONS, ETC. THAT
MAY AFFECT THE SPECIFIED WARRANTY.
G11.
AN ON-SITE PRE-CONSTRUCTION MEETING WITH THE ARCHITECT, ROOFING SYSTEM
REPRESENTATIVE, OWNER, AND CONTRACTOR SHALL BE CONDUCTED PRIOR TO THE START
OF CONSTRUCTION AND PRIOR TO ORDERING OF MATERIAL. REFER TO SPECIFICATIONS FOR
FURTHER INFORMATION.
G12.
CRICKET SLOPE TO BE 14" PER FOOT UNLESS NOTED OTHERWISE.
G13.
DRAINAGE SADDLES TO SLOPE 14" PER FOOT UNLESS NOTED OTHERWISE. CONTRACTOR TO
ASSURE POSITIVE DRAINAGE TO ROOF DRAINS / GUTTER EDGE.
RAISED MECHANICAL EXHAUST FAN UNIT / RELIEF HOOD AS REQUIRED TO MEET SYSTEM
WARRANTY REQUIREMENTS.
2.
PREFINISHED METAL CAP FLASHING (PRE-SLOPED)--REFER TO GENERAL NOTE G12.
3.
CRICKET AS REQUIRED TO PROVIDE DRAINAGE AT MECHANICAL ITEM, ETC. REFER TO
GENERAL NOTES G7 AND G19 FOR FURTHER INFORMATION.
4.
5.
6.
7.
PLUMBING VENT BOOT FLASHING (AND EXTENSION WHERE REQUIRED-C.F.V.).
8.
9.
HVAC STACK FLASHING TO SUIT CONDITIONS (C.F.V.).
10.
11.
12.
13.
14.
REMOVE EXISTING ROOFING SYSTEMS COMPETE DOWN TO EXISTING ROOF DECK.
INFORMATION ABOUT EXISTING ROOFING COMPOSITION IS FOR REFERENCE ONLY AND
SHOULD BE FIELD VERIFIED BY THE CONTRACTOR.
ROOFTOP DUCTWORK, GAS LINES, ELECTRICAL CONDUITS, ETC. MAY NOT BE INDICATED FOR
DRAWING CLARITY, BUT WILL REQUIRE RE-WORK AND MODIFICATIONS DUE TO THE WORK.
CONTRACTOR TO FIELD VERIFY ALL EXISTING CONDITIONS AND COORDINATE WITH OWNER.
PROVIDE PROPER SUPPORTS (ROLLER SUPPORTS, UNISTRUT PADS, ETC.).
CONTRACTOR WILL BE REQUIRED TO BUILD UP THE ROOF EDGE (PARAPET) AT MOST
LOCATIONS DUE TO INCREASED INSULATION HEIGHT. CONTRACTOR TO FIELD VERIFY AND
PROVIDE THE NECESSARY BLOCKING.
NEW EDGE FLASHING (PARAPET) MATERIAL IS TO BE FIELD VERIFIED WITH EXISTING WALL
CONDITIONS. WHERE ALUMINUM WALL PANELS EXIST, CONTRACTOR TO INSTALL ALUMINUM
CAP / FLASHINGS TO BE COMPATIBLE WITH WALL MATERIALS.
G14.
G15.
G16.
G17.
POLYISOCYANURATE HINGED TARGET SUMP AT EXISTING ROOF DRAIN LOCATION.
ROOF TO ROOF EXPANSION JOINT / AREA DIVIDER.
PATE EQUIPMENT SUPPORT RAILS FOR ROOFTOP HVAC ITEM (ROOFTOP CONDENSER).
PATE PIPE CURB ASSEMBLY FOR ROOFTOP HVAC ITEM (ROOFTOP CONDENSER LINESETS).
REMOVE EXISTING CURB AND COVER (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING
SYSTEM). CONTRACTOR TO CONFIRM WITH OWNER THAT ITEM IS ABANDONED PRIOR TO
REMOVAL.
ROOF EXPANSION JOINT / AREA DIVIDER.
REPLACE EXISTING ROOF HATCH WITH GALVANIZED ROOF HATCH WITH SAFETY RAILS AND
EASY-UP LADDER (IN EXISTING LOCATION). CONTRACTOR TO FIELD VERIFY EXISTING HATCH
SIZE AND REPLACE WITH SAME SIZE.
REPLACEMENT OF THE ROOF SHALL BE DONE SO-AS TO NOT REMOVE ANY MORE OF THE
ROOFING THAN CAN BE REPLACED IN A GIVEN DAY. AT NO TIME SHALL THE ROOF BE LEFT
OPEN AND SUBJECT TO WEATHER CONDITIONS. CONTRACTOR SHALL BE RESPONSIBLE FOR
ANY DAMAGE THAT OCCURS.
ANY UTILITY SHUT-DOWNS THAT ARE REQUIRED IN ORDER TO PERFORM THE RE-ROOFING
OPERATIONS SHALL BE SCHEDULED IN ADVANCE WITH THE OWNER.
CONTRACTOR TO ASSURE THAT ALL ROOF DRAINS ARE IN PROPER WORKING CONDITION
PRIOR TO COMPLETING THE RE-ROOFING OPERATIONS. REPORT ANY DISCREPANCIES TO THE
OWNER / ARCHITECT FOR FURTHER DIRECTION.
PROVIDE WALKWAY PADS / SLIP SHEETS UNDER ALL PIPE SUPPORTS.
G18.
G19.
G20.
G21.
REMOVE EXISTING PLUMBING VENT AND CAP BELOW ROOF PER CODE REQUIREMENTS
(ASSUMED ABANDONED). CONTRACTOR TO CONFIRM WITH OWNER THAT ITEM IS ABANDONED
PRIOR TO REMOVAL.
PITCH POCKET FOR EXISTING PENETRATION.
EXISTING PATE PIPE CURB TO REMAIN.
COUNTERFLASHING (MINIMUM 12" ABOVE MEMBRANE SURFACE).17.
CONTRACTOR TO PROVIDE SLIP FLASHING AT ALL UNITS AND AS REQUIRED.G22.
NOT ALL NOTES MAY APPLY TO THIS SHEET.G23.
15.
16.
WRAP ROOFING MEMBRANE UP FACE OF WALL AND UNDER EXISTING CAP FLASHING.
REMOVE AND REINSTALL FLASHING AS REQUIRED.
REMOVE EXISTING WOOD GUARDRAIL AROUND EXISTING SKYLIGHT.
CONTRACTOR TO PROTECT OWNER'S EXISTING ASPHALT / CONCRETE PAVING AND/OR LAWN
AREAS FROM CONSTRUCTION TRAFFIC. IF DAMAGE SHOULD OCCUR, CONTRACTOR IS
RESPONSIBLE TO COORDINATE AND PAY FOR ALL REPAIRS TO BRING THE ITEM BACK TO THE
CONDITION BEFORE CONSTRUCTION COMMENCED. IT SHALL BE THE OWNER'S OPTION TO
HAVE THEIR VENDOR MAKE ANY REPAIRS, AND THE CONTRACTOR'S CONTRACT WILL BE
REDUCED VIA CHANGE ORDER TO COVER SUCH REPAIRS.
G24.
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· ADHESIVE APPLIED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER START)
· MECHANICALLY FASTENED ASPHALT BASE SHEET WITH IMPACT BASE SHEET FASTENERS
· EXISTING TECTUM ROOF DECK (ASSUMED FLAT)
30" x 30" WALKWAY PAD INSTALLED PER MANUFACTURER'S REQUIREMENTS. INTENT IS
FOR WALKWAY PADS TO BE INSTALLED AT ROOF HATCHES AND AROUND ALL HVAC
ROOFTOP UNITS.
COUNTERFLASHING (MINIMUM 12" ABOVE MEMBRANE SURFACE).
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· MECHANICALLY FASTENED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER
START)
· SELF-ADHERING VAPOR BARRIER (AT ACOUSTICAL METAL DECK ONLY)
· EXISTING METAL / ACOUSTICAL METAL ROOF DECK (ASSUMED FLAT)
29.
LEGEND:
REMOVE EXISTING WOOD GUARDRAIL AROUND EXISTING SKYLIGHT.18.
REMOVE EXISTING SKYLIGHT (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING SYSTEM).
DRAINAGE SCUPPER THROUGH WALL.20.
19.
PREFINISHED METAL EDGE FLASHING--REFER TO GENERAL NOTE G12.21.
REMOVE AND REINSTALL EXISTING GUTTER SYSTEM AS NEEDED FOR ROOFING OPERATIONS.22.
EXISTING COPPER / METAL CAP AND RIDGE CAP TO REMAIN.23.
CONTRACTOR TO PROVIDE PRESERVATIVE TREATED WOOD BLOCKING AT LOCATION OF
ALUMINUM WALL PANELS DUE TO RAISED PARAPET HEIGHT (BASED ON PREVIOUS ROOF
REPLACEMENT, ALUMINUM WALL PANELS STOP SHORT AND REQUIRES ADDITIONAL
BLOCKING).
EXISTING ROOF EXPANSION JOINT METAL TO BE REMOVED AND REINSTALLED TO COMPLETE
ROOFING OPERATIONS.
25.
24.
26.
ROOFING SYSTEM COMPOSITION:
· ASPHALT SHINGLES
· ROOF DECK PROTECTION OVER ENTIRE ROOF AREA (ICE & WATER SHIELD)
· EXISTING ROOF DECK (UNKNOWN)
27.
PREFINISHED RIDGE / CAP FLASHING OVER EXISTING SLOPED METAL ROOF / WALL PANELS.28.
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· ADHESIVE APPLIED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER START)
· MECHANICALLY FASTENED ASPHALT BASE SHEET WITH IMPACT BASE SHEET FASTENERS
· EXISTING GYPSUM ROOF DECK (ASSUMED FLAT)
30.
EXISTING ELECTRICAL JUNCTION BOX TO REMAIN--INSTALL ROOF WALKWAY PAD / SLIP
SHEET UNDER JUNCTION BOX.
EXISTING WALL-MOUNTED LADDER TO BE REMOVED AND RELOCATED PER OWNER DIRECTED
LOCATION. CONTRACTOR TO MODIFY BRACKET(S) AS REQUIRED TO SUIT BUILDING
CONDITIONS. PATCH / REPAIR FASTENER HOLES IN EXISTING WALL PANELS / FLASHINGS,
ETC.
32.
31.
EXISTING STRUCTURAL COLUMN PENETRATION--PROVIDE MANUFACTURER'S TYPICAL I-BEAM
PENETRATION DETAIL.
33.
REMOVE AND REPLACE EXISTING ROOFING, BASE FLASHING, INSULATION, ETC. IN AREA
BETWEEN ROOF EDGE AND PARAPET.
34.
PREFINISHED METAL GUTTER AND DOWNSPOUT TO GRADE. SLOPE GUTTER TO DOWNSPOUT
LOCATION AND PROVIDE CONCRETE SPLASH BLOCK ON GRADE.
35.
AT ACOUSTICAL METAL DECK LOCATIONS, CONTRACTOR TO PROVIDE PLASTIC SHEETING
(VISQUEEN) TO PROTECT FLOOR BELOW FROM DUST AND DEBRIS. CONTRACTOR TO PLACE
SHEETING AND REMOVE AFTER ROOFING OPERATIONS. OWNER WILL PROVIDE THE FINAL
CONSTRUCTION CLEANING. REFER TO ALTERNATE #1 FOR FURTHER INFORMATION.
36.
© Ehresman Architects
C2.51Project No. 6524
Bloomfield Hills Schools District-Wide Roofing Replacement
Enlarged Roof Plan
Addendum #1: 24 January 2025
Permits & Bidding: 21 January 2025
Conant Elementary School
Scale: 1/8"=1'-0" Enlarged Roof Plan (Conant Elementary)
C2.51
HIGH POINT
ROOF AREA "F"
ROOF AREA "H"
ROOF AREA "G"
RE
FE
R
TO
W
OR
K
N
OT
E
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 11
2" POLYISOCYANURATE INSULATION
· 1
2" WOOD FIBER INSULATION
· 1
2" WOOD FIBER INSULATION
· EXISTING GYPSUM ROOF DECK
OPEN TO
COURTYARD
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 2" POLYISOCYANURATE INSULATION
· 1
2" WOOD FIBER INSULATION
· 1
2" WOOD FIBER INSULATION
· EXISTING ACOUSTICAL METAL ROOF DECK
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 11
2" POLYISOCYANURATE INSULATION
· 1
2" WOOD FIBER INSULATION
· 1
2" WOOD FIBER INSULATION
· EXISTING METAL ROOF DECK
ROOFTOP
HVAC
ROOF AREA "E"
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 1" PERLITE INSULATION
· 2" POLYISOCYANURATE INSULATION
· EXISTING GYPSUM ROOF DECK
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
HIGH POINTHIGH POINT HIGH POINT H.P.
1 8" P
ER
FO
OT
TA
PE
R
IN
SU
LA
TI
ON
1 8" P
ER
FO
OT
TA
PE
R
IN
SU
LA
TI
ON
8" PER
FOOT
TAPER
INSULATION
HIGH POIN
T
GASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGASGAS
GAS
GAS
GAS
GAS
GAS
WORK NOTES:
1.
GENERAL NOTES:
DO NOT SCALE DRAWING. DRAWING SCALE IS SHOWN FOR GENERAL REFERENCE ONLY.G1.
G2. FIELD VERIFY ALL DIMENSIONS, ROOF SUMP LOCATIONS, EQUIPMENT CURBS, ETC. PRIOR TO
COMMENCING WITH CONSTRUCTION OPERATIONS.
THE ROOFING SHALL BE A TWENTY-FIVE (25) YEAR MANUF. ROOFING SYSTEM WARRANTY
ALONG WITH A FIVE (5) YEAR LABOR WARRANTY. EDGE METAL TO BE INCLUDED IN FULL
SYSTEM WARRANTY.
G3.
G4. REFER TO ROOF DETAILS AND MANUFACTURER'S STANDARD DETAILS FOR ADDITIONAL
INFORMATION.
G5. EXISTING ROOF DECK THICKNESS AND SLOPE IS UNKNOWN. CONTRACTOR TO VERIFY AFTER
THE ROOFING HAS BEEN REMOVED AND REPORT ANY DISCREPANCIES THAT MAY BE
DISCOVERED TO THE ARCHITECT / ROOFING SYSTEM REPRESENTATIVE FOR FURTHER
DIRECTION.
G6. ALL MECHANICAL EQUIPMENT CURBS SHALL HAVE NEW BASE FLASHING A MINIMUM OF 8"
ABOVE THE ROOFING MEMBRANE, UNLESS MORE STRINGENT REQUIREMENTS ARE NEEDED
TO MEET THE ROOFING MANUFACTURER SPECIFICATIONS. CONTRACTOR TO FIELD VERIFY
HEIGHT -- ASSUME THE EXISTING HVAC CURBS WILL NEED TO BE RAISED.
G7. INSTALL CRICKETS AT ALL EQUIPMENT CURBS HIGH SIDE, WHETHER SHOWN OR NOT.
G8. EXISTING EQUIPMENT, PENETRATIONS, ROOF DRAINS, CURBS, ETC. IDENTIFIED SHALL BE
FIELD VERIFIED BY THE CONTRACTOR WHOM WILL BE RESPONSIBLE FOR THE QUANTITIES,
CONDITIONS, HEIGHTS, ETC.
G9.
ANY EXISTING WOOD BLOCKING FOR ELECTRICAL CONDUIT AND/OR GAS PIPING SHALL BE
REPLACED WITH PROPER PREFABRICATED SUPPORT WHETHER PARTICULARLY INDICATED OR
NOT (NO WOOD BLOCKING IS PERMITTED).
G10.
CONTRACTOR TO VISIT THE SITE AND VERIFY ALL MEASUREMENTS, CONDITIONS, ETC. THAT
MAY AFFECT THE SPECIFIED WARRANTY.
G11.
AN ON-SITE PRE-CONSTRUCTION MEETING WITH THE ARCHITECT, ROOFING SYSTEM
REPRESENTATIVE, OWNER, AND CONTRACTOR SHALL BE CONDUCTED PRIOR TO THE START
OF CONSTRUCTION AND PRIOR TO ORDERING OF MATERIAL. REFER TO SPECIFICATIONS FOR
FURTHER INFORMATION.
G12.
CRICKET SLOPE TO BE 14" PER FOOT UNLESS NOTED OTHERWISE.
G13.
DRAINAGE SADDLES TO SLOPE 14" PER FOOT UNLESS NOTED OTHERWISE. CONTRACTOR TO
ASSURE POSITIVE DRAINAGE TO ROOF DRAINS / GUTTER EDGE.
RAISED MECHANICAL EXHAUST FAN UNIT / RELIEF HOOD AS REQUIRED TO MEET SYSTEM
WARRANTY REQUIREMENTS.
2.
PREFINISHED METAL CAP FLASHING (PRE-SLOPED)--REFER TO GENERAL NOTE G12.
3.
CRICKET AS REQUIRED TO PROVIDE DRAINAGE AT MECHANICAL ITEM, ETC. REFER TO
GENERAL NOTES G7 AND G19 FOR FURTHER INFORMATION.
4.
5.
6.
7.
PLUMBING VENT BOOT FLASHING (AND EXTENSION WHERE REQUIRED-C.F.V.).
8.
9.
HVAC STACK FLASHING TO SUIT CONDITIONS (C.F.V.).
10.
11.
12.
13.
14.
REMOVE EXISTING ROOFING SYSTEMS COMPETE DOWN TO EXISTING ROOF DECK.
INFORMATION ABOUT EXISTING ROOFING COMPOSITION IS FOR REFERENCE ONLY AND
SHOULD BE FIELD VERIFIED BY THE CONTRACTOR.
ROOFTOP DUCTWORK, GAS LINES, ELECTRICAL CONDUITS, ETC. MAY NOT BE INDICATED FOR
DRAWING CLARITY, BUT WILL REQUIRE RE-WORK AND MODIFICATIONS DUE TO THE WORK.
CONTRACTOR TO FIELD VERIFY ALL EXISTING CONDITIONS AND COORDINATE WITH OWNER.
PROVIDE PROPER SUPPORTS (ROLLER SUPPORTS, UNISTRUT PADS, ETC.).
CONTRACTOR WILL BE REQUIRED TO BUILD UP THE ROOF EDGE (PARAPET) AT MOST
LOCATIONS DUE TO INCREASED INSULATION HEIGHT. CONTRACTOR TO FIELD VERIFY AND
PROVIDE THE NECESSARY BLOCKING.
NEW EDGE FLASHING (PARAPET) MATERIAL IS TO BE FIELD VERIFIED WITH EXISTING WALL
CONDITIONS. WHERE ALUMINUM WALL PANELS EXIST, CONTRACTOR TO INSTALL ALUMINUM
CAP / FLASHINGS TO BE COMPATIBLE WITH WALL MATERIALS.
G14.
G15.
G16.
G17.
POLYISOCYANURATE HINGED TARGET SUMP AT EXISTING ROOF DRAIN LOCATION.
ROOF TO ROOF EXPANSION JOINT / AREA DIVIDER.
PATE EQUIPMENT SUPPORT RAILS FOR ROOFTOP HVAC ITEM (ROOFTOP CONDENSER).
PATE PIPE CURB ASSEMBLY FOR ROOFTOP HVAC ITEM (ROOFTOP CONDENSER LINESETS).
REMOVE EXISTING CURB AND COVER (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING
SYSTEM). CONTRACTOR TO CONFIRM WITH OWNER THAT ITEM IS ABANDONED PRIOR TO
REMOVAL.
ROOF EXPANSION JOINT / AREA DIVIDER.
REPLACE EXISTING ROOF HATCH WITH GALVANIZED ROOF HATCH WITH SAFETY RAILS AND
EASY-UP LADDER (IN EXISTING LOCATION). CONTRACTOR TO FIELD VERIFY EXISTING HATCH
SIZE AND REPLACE WITH SAME SIZE.
REPLACEMENT OF THE ROOF SHALL BE DONE SO-AS TO NOT REMOVE ANY MORE OF THE
ROOFING THAN CAN BE REPLACED IN A GIVEN DAY. AT NO TIME SHALL THE ROOF BE LEFT
OPEN AND SUBJECT TO WEATHER CONDITIONS. CONTRACTOR SHALL BE RESPONSIBLE FOR
ANY DAMAGE THAT OCCURS.
ANY UTILITY SHUT-DOWNS THAT ARE REQUIRED IN ORDER TO PERFORM THE RE-ROOFING
OPERATIONS SHALL BE SCHEDULED IN ADVANCE WITH THE OWNER.
CONTRACTOR TO ASSURE THAT ALL ROOF DRAINS ARE IN PROPER WORKING CONDITION
PRIOR TO COMPLETING THE RE-ROOFING OPERATIONS. REPORT ANY DISCREPANCIES TO THE
OWNER / ARCHITECT FOR FURTHER DIRECTION.
PROVIDE WALKWAY PADS / SLIP SHEETS UNDER ALL PIPE SUPPORTS.
G18.
G19.
G20.
G21.
REMOVE EXISTING PLUMBING VENT AND CAP BELOW ROOF PER CODE REQUIREMENTS
(ASSUMED ABANDONED). CONTRACTOR TO CONFIRM WITH OWNER THAT ITEM IS ABANDONED
PRIOR TO REMOVAL.
PITCH POCKET FOR EXISTING PENETRATION.
EXISTING PATE PIPE CURB TO REMAIN.
COUNTERFLASHING (MINIMUM 12" ABOVE MEMBRANE SURFACE).17.
CONTRACTOR TO PROVIDE SLIP FLASHING AT ALL UNITS AND AS REQUIRED.G22.
NOT ALL NOTES MAY APPLY TO THIS SHEET.G23.
15.
16.
WRAP ROOFING MEMBRANE UP FACE OF WALL AND UNDER EXISTING CAP FLASHING.
REMOVE AND REINSTALL FLASHING AS REQUIRED.
REMOVE EXISTING WOOD GUARDRAIL AROUND EXISTING SKYLIGHT.18.
CONTRACTOR TO PROTECT OWNER'S EXISTING ASPHALT / CONCRETE PAVING AND/OR LAWN
AREAS FROM CONSTRUCTION TRAFFIC. IF DAMAGE SHOULD OCCUR, CONTRACTOR IS
RESPONSIBLE TO COORDINATE AND PAY FOR ALL REPAIRS TO BRING THE ITEM BACK TO THE
CONDITION BEFORE CONSTRUCTION COMMENCED. IT SHALL BE THE OWNER'S OPTION TO
HAVE THEIR VENDOR MAKE ANY REPAIRS, AND THE CONTRACTOR'S CONTRACT WILL BE
REDUCED VIA CHANGE ORDER TO COVER SUCH REPAIRS.
G24.
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· ADHESIVE APPLIED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER START)
· MECHANICALLY FASTENED ASPHALT BASE SHEET WITH IMPACT BASE SHEET FASTENERS
· EXISTING TECTUM ROOF DECK (ASSUMED FLAT)
30" x 30" WALKWAY PAD INSTALLED PER MANUFACTURER'S REQUIREMENTS. INTENT IS
FOR WALKWAY PADS TO BE INSTALLED AT ROOF HATCHES AND AROUND ALL HVAC
ROOFTOP UNITS.
COUNTERFLASHING (MINIMUM 12" ABOVE MEMBRANE SURFACE).
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· MECHANICALLY FASTENED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER
START)
· SELF-ADHERING VAPOR BARRIER (AT ACOUSTICAL METAL DECK ONLY)
· EXISTING METAL / ACOUSTICAL METAL ROOF DECK (ASSUMED FLAT)
29.
LEGEND:
REMOVE EXISTING WOOD GUARDRAIL AROUND EXISTING SKYLIGHT.18.
REMOVE EXISTING SKYLIGHT (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING SYSTEM).
DRAINAGE SCUPPER THROUGH WALL.20.
19.
PREFINISHED METAL EDGE FLASHING--REFER TO GENERAL NOTE G12.21.
REMOVE AND REINSTALL EXISTING GUTTER SYSTEM AS NEEDED FOR ROOFING OPERATIONS.22.
EXISTING COPPER / METAL CAP AND RIDGE CAP TO REMAIN.23.
CONTRACTOR TO PROVIDE PRESERVATIVE TREATED WOOD BLOCKING AT LOCATION OF
ALUMINUM WALL PANELS DUE TO RAISED PARAPET HEIGHT (BASED ON PREVIOUS ROOF
REPLACEMENT, ALUMINUM WALL PANELS STOP SHORT AND REQUIRES ADDITIONAL
BLOCKING).
EXISTING ROOF EXPANSION JOINT METAL TO BE REMOVED AND REINSTALLED TO COMPLETE
ROOFING OPERATIONS.
25.
24.
26.
ROOFING SYSTEM COMPOSITION:
· ASPHALT SHINGLES
· ROOF DECK PROTECTION OVER ENTIRE ROOF AREA (ICE & WATER SHIELD)
· EXISTING ROOF DECK (UNKNOWN)
27.
PREFINISHED RIDGE / CAP FLASHING OVER EXISTING SLOPED METAL ROOF / WALL PANELS.28.
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· ADHESIVE APPLIED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER START)
· MECHANICALLY FASTENED ASPHALT BASE SHEET WITH IMPACT BASE SHEET FASTENERS
· EXISTING GYPSUM ROOF DECK (ASSUMED FLAT)
30.
EXISTING ELECTRICAL JUNCTION BOX TO REMAIN--INSTALL ROOF WALKWAY PAD / SLIP
SHEET UNDER JUNCTION BOX.
EXISTING WALL-MOUNTED LADDER TO BE REMOVED AND RELOCATED PER OWNER DIRECTED
LOCATION. CONTRACTOR TO MODIFY BRACKET(S) AS REQUIRED TO SUIT BUILDING
CONDITIONS. PATCH / REPAIR FASTENER HOLES IN EXISTING WALL PANELS / FLASHINGS,
ETC.
32.
31.
EXISTING STRUCTURAL COLUMN PENETRATION--PROVIDE MANUFACTURER'S TYPICAL I-BEAM
PENETRATION DETAIL.
33.
REMOVE AND REPLACE EXISTING ROOFING, BASE FLASHING, INSULATION, ETC. IN AREA
BETWEEN ROOF EDGE AND PARAPET.
34.
PREFINISHED METAL GUTTER AND DOWNSPOUT TO GRADE. SLOPE GUTTER TO DOWNSPOUT
LOCATION AND PROVIDE CONCRETE SPLASH BLOCK ON GRADE.
35.
AT ACOUSTICAL METAL DECK LOCATIONS, CONTRACTOR TO PROVIDE PLASTIC SHEETING
(VISQUEEN) TO PROTECT FLOOR BELOW FROM DUST AND DEBRIS. CONTRACTOR TO PLACE
SHEETING AND REMOVE AFTER ROOFING OPERATIONS. OWNER WILL PROVIDE THE FINAL
CONSTRUCTION CLEANING. REFER TO ALTERNATE #1 FOR FURTHER INFORMATION.
36.
© Ehresman Architects
C2.52Project No. 6524
Bloomfield Hills Schools District-Wide Roofing Replacement
Enlarged Roof Plan
Addendum #1: 24 January 2025
Permits & Bidding: 21 January 2025
Conant Elementary School
Scale: 1/8"=1'-0" Enlarged Roof Plan (Conant Elementary)
C2.52
ROOF AREA "I"
ROOF AREA "J"
Scale: 1/8"=1'-0" Enlarged Roof Plan (Conant Elementary)
C2.52
EXISTING ROOFING COMPOSITION
· GRAVELED BUILT-UP ROOF SYSTEM
· 1
2" FIBERGLASS INSULATION
· 21
2" FOAM INSULATION
· EXISTING ACOUSTICAL METAL ROOF
DECK
OPEN TO
COURTYARD
EXISTING ROOFING COMPOSITION
· SHINGLES
· EXISTING ROOF DECK (UNKNOWN)
EX
IS
TI
N
G
SL
OP
E
DN
EXISTING
SLOPE DN.
EX
IS
TI
N
G
SL
OP
E
DN
EXISTING
SLOPE DN.
EXISTIN
G
SLOPE DN.
EXISTING
SLOPE DN.
EX
IS
TI
NG
SL
OP
E
DN
EX
IS
TI
N
G
SL
OP
E
DN
EX
IS
TI
N
G
SL
OP
E
DN
EXISTING
SLOPE DN.
EXISTING
SLOPE DN.
ROOF AREA "D.1"
EXISTING ROOFING COMPOSITION
· FULLY-ADHERED ROOFING MEMBRANE
· 2" POLYISOCYANURATE INSULATION
· EXISTING WOOD ROOF DECK
H
IG
H P
OI
N
T
HIGH POINT
H
IG
H P
OI
N
T
H
IG
H P
OI
N
T
8" PER FOOT
TAPER INSULATION
8" PER FOOT
TAPER INSULATION
8" PER FOOT
TAPER INSULATION
8" PER FOOT
TAPER INSULATION
8" PER FOOT
TAPER INSULATION
8" PER
FOOT
TAPER
INSULATION
8" PER
FOOT
TAPER
INSULATION
8" PER
FOOT
TAPER
INSULATION
8" PER
FOOT
TAPER
INSULATION
H
IG
H P
OI
N
T
8" PER
FOOT
TAPER
INSULATION
1 8" P
ER
F
OO
T
TA
PE
R
IN
SU
LA
TI
ON
8" PER FOOT
TAPER INSULATION
WORK NOTES:
1.
GENERAL NOTES:
DO NOT SCALE DRAWING. DRAWING SCALE IS SHOWN FOR GENERAL REFERENCE ONLY.G1.
G2. FIELD VERIFY ALL DIMENSIONS, ROOF SUMP LOCATIONS, EQUIPMENT CURBS, ETC. PRIOR TO
COMMENCING WITH CONSTRUCTION OPERATIONS.
THE ROOFING SHALL BE A TWENTY-FIVE (25) YEAR MANUF. ROOFING SYSTEM WARRANTY
ALONG WITH A FIVE (5) YEAR LABOR WARRANTY. EDGE METAL TO BE INCLUDED IN FULL
SYSTEM WARRANTY.
G3.
G4. REFER TO ROOF DETAILS AND MANUFACTURER'S STANDARD DETAILS FOR ADDITIONAL
INFORMATION.
G5. EXISTING ROOF DECK THICKNESS AND SLOPE IS UNKNOWN. CONTRACTOR TO VERIFY AFTER
THE ROOFING HAS BEEN REMOVED AND REPORT ANY DISCREPANCIES THAT MAY BE
DISCOVERED TO THE ARCHITECT / ROOFING SYSTEM REPRESENTATIVE FOR FURTHER
DIRECTION.
G6. ALL MECHANICAL EQUIPMENT CURBS SHALL HAVE NEW BASE FLASHING A MINIMUM OF 8"
ABOVE THE ROOFING MEMBRANE, UNLESS MORE STRINGENT REQUIREMENTS ARE NEEDED
TO MEET THE ROOFING MANUFACTURER SPECIFICATIONS. CONTRACTOR TO FIELD VERIFY
HEIGHT -- ASSUME THE EXISTING HVAC CURBS WILL NEED TO BE RAISED.
G7. INSTALL CRICKETS AT ALL EQUIPMENT CURBS HIGH SIDE, WHETHER SHOWN OR NOT.
G8. EXISTING EQUIPMENT, PENETRATIONS, ROOF DRAINS, CURBS, ETC. IDENTIFIED SHALL BE
FIELD VERIFIED BY THE CONTRACTOR WHOM WILL BE RESPONSIBLE FOR THE QUANTITIES,
CONDITIONS, HEIGHTS, ETC.
G9.
ANY EXISTING WOOD BLOCKING FOR ELECTRICAL CONDUIT AND/OR GAS PIPING SHALL BE
REPLACED WITH PROPER PREFABRICATED SUPPORT WHETHER PARTICULARLY INDICATED OR
NOT (NO WOOD BLOCKING IS PERMITTED).
G10.
CONTRACTOR TO VISIT THE SITE AND VERIFY ALL MEASUREMENTS, CONDITIONS, ETC. THAT
MAY AFFECT THE SPECIFIED WARRANTY.
G11.
AN ON-SITE PRE-CONSTRUCTION MEETING WITH THE ARCHITECT, ROOFING SYSTEM
REPRESENTATIVE, OWNER, AND CONTRACTOR SHALL BE CONDUCTED PRIOR TO THE START
OF CONSTRUCTION AND PRIOR TO ORDERING OF MATERIAL. REFER TO SPECIFICATIONS FOR
FURTHER INFORMATION.
G12.
CRICKET SLOPE TO BE 14" PER FOOT UNLESS NOTED OTHERWISE.
G13.
DRAINAGE SADDLES TO SLOPE 14" PER FOOT UNLESS NOTED OTHERWISE. CONTRACTOR TO
ASSURE POSITIVE DRAINAGE TO ROOF DRAINS / GUTTER EDGE.
RAISED MECHANICAL EXHAUST FAN UNIT / RELIEF HOOD AS REQUIRED TO MEET SYSTEM
WARRANTY REQUIREMENTS.
2.
PREFINISHED METAL CAP FLASHING (PRE-SLOPED)--REFER TO GENERAL NOTE G12.
3.
CRICKET AS REQUIRED TO PROVIDE DRAINAGE AT MECHANICAL ITEM, ETC. REFER TO
GENERAL NOTES G7 AND G19 FOR FURTHER INFORMATION.
4.
5.
6.
7.
PLUMBING VENT BOOT FLASHING (AND EXTENSION WHERE REQUIRED-C.F.V.).
8.
9.
HVAC STACK FLASHING TO SUIT CONDITIONS (C.F.V.).
10.
11.
12.
13.
14.
REMOVE EXISTING ROOFING SYSTEMS COMPETE DOWN TO EXISTING ROOF DECK.
INFORMATION ABOUT EXISTING ROOFING COMPOSITION IS FOR REFERENCE ONLY AND
SHOULD BE FIELD VERIFIED BY THE CONTRACTOR.
ROOFTOP DUCTWORK, GAS LINES, ELECTRICAL CONDUITS, ETC. MAY NOT BE INDICATED FOR
DRAWING CLARITY, BUT WILL REQUIRE RE-WORK AND MODIFICATIONS DUE TO THE WORK.
CONTRACTOR TO FIELD VERIFY ALL EXISTING CONDITIONS AND COORDINATE WITH OWNER.
PROVIDE PROPER SUPPORTS (ROLLER SUPPORTS, UNISTRUT PADS, ETC.).
CONTRACTOR WILL BE REQUIRED TO BUILD UP THE ROOF EDGE (PARAPET) AT MOST
LOCATIONS DUE TO INCREASED INSULATION HEIGHT. CONTRACTOR TO FIELD VERIFY AND
PROVIDE THE NECESSARY BLOCKING.
NEW EDGE FLASHING (PARAPET) MATERIAL IS TO BE FIELD VERIFIED WITH EXISTING WALL
CONDITIONS. WHERE ALUMINUM WALL PANELS EXIST, CONTRACTOR TO INSTALL ALUMINUM
CAP / FLASHINGS TO BE COMPATIBLE WITH WALL MATERIALS.
G14.
G15.
G16.
G17.
POLYISOCYANURATE HINGED TARGET SUMP AT EXISTING ROOF DRAIN LOCATION.
ROOF TO ROOF EXPANSION JOINT / AREA DIVIDER.
PATE EQUIPMENT SUPPORT RAILS FOR ROOFTOP HVAC ITEM (ROOFTOP CONDENSER).
PATE PIPE CURB ASSEMBLY FOR ROOFTOP HVAC ITEM (ROOFTOP CONDENSER LINESETS).
REMOVE EXISTING CURB AND COVER (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING
SYSTEM). CONTRACTOR TO CONFIRM WITH OWNER THAT ITEM IS ABANDONED PRIOR TO
REMOVAL.
ROOF EXPANSION JOINT / AREA DIVIDER.
REPLACE EXISTING ROOF HATCH WITH GALVANIZED ROOF HATCH WITH SAFETY RAILS AND
EASY-UP LADDER (IN EXISTING LOCATION). CONTRACTOR TO FIELD VERIFY EXISTING HATCH
SIZE AND REPLACE WITH SAME SIZE.
REPLACEMENT OF THE ROOF SHALL BE DONE SO-AS TO NOT REMOVE ANY MORE OF THE
ROOFING THAN CAN BE REPLACED IN A GIVEN DAY. AT NO TIME SHALL THE ROOF BE LEFT
OPEN AND SUBJECT TO WEATHER CONDITIONS. CONTRACTOR SHALL BE RESPONSIBLE FOR
ANY DAMAGE THAT OCCURS.
ANY UTILITY SHUT-DOWNS THAT ARE REQUIRED IN ORDER TO PERFORM THE RE-ROOFING
OPERATIONS SHALL BE SCHEDULED IN ADVANCE WITH THE OWNER.
CONTRACTOR TO ASSURE THAT ALL ROOF DRAINS ARE IN PROPER WORKING CONDITION
PRIOR TO COMPLETING THE RE-ROOFING OPERATIONS. REPORT ANY DISCREPANCIES TO THE
OWNER / ARCHITECT FOR FURTHER DIRECTION.
PROVIDE WALKWAY PADS / SLIP SHEETS UNDER ALL PIPE SUPPORTS.
G18.
G19.
G20.
G21.
REMOVE EXISTING PLUMBING VENT AND CAP BELOW ROOF PER CODE REQUIREMENTS
(ASSUMED ABANDONED). CONTRACTOR TO CONFIRM WITH OWNER THAT ITEM IS ABANDONED
PRIOR TO REMOVAL.
PITCH POCKET FOR EXISTING PENETRATION.
EXISTING PATE PIPE CURB TO REMAIN.
COUNTERFLASHING (MINIMUM 12" ABOVE MEMBRANE SURFACE).17.
CONTRACTOR TO PROVIDE SLIP FLASHING AT ALL UNITS AND AS REQUIRED.G22.
NOT ALL NOTES MAY APPLY TO THIS SHEET.G23.
15.
16.
WRAP ROOFING MEMBRANE UP FACE OF WALL AND UNDER EXISTING CAP FLASHING.
REMOVE AND REINSTALL FLASHING AS REQUIRED.
REMOVE EXISTING WOOD GUARDRAIL AROUND EXISTING SKYLIGHT.
CONTRACTOR TO PROTECT OWNER'S EXISTING ASPHALT / CONCRETE PAVING AND/OR LAWN
AREAS FROM CONSTRUCTION TRAFFIC. IF DAMAGE SHOULD OCCUR, CONTRACTOR IS
RESPONSIBLE TO COORDINATE AND PAY FOR ALL REPAIRS TO BRING THE ITEM BACK TO THE
CONDITION BEFORE CONSTRUCTION COMMENCED. IT SHALL BE THE OWNER'S OPTION TO
HAVE THEIR VENDOR MAKE ANY REPAIRS, AND THE CONTRACTOR'S CONTRACT WILL BE
REDUCED VIA CHANGE ORDER TO COVER SUCH REPAIRS.
G24.
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· ADHESIVE APPLIED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER START)
· MECHANICALLY FASTENED ASPHALT BASE SHEET WITH IMPACT BASE SHEET FASTENERS
EXISTING TECTUM ROOF DECK (ASSUMED FLAT)
COUNTERFLASHING (MINIMUM 12" ABOVE MEMBRANE SURFACE).
REMOVE EXISTING WOOD GUARDRAIL AROUND EXISTING SKYLIGHT.18.
REMOVE EXISTING SKYLIGHT (INFILL DECK AS REQUIRED PRIOR TO NEW ROOFING SYSTEM).
DRAINAGE SCUPPER THROUGH WALL.20.
19.
PREFINISHED METAL EDGE FLASHING--REFER TO GENERAL NOTE G12.21.
REMOVE AND REINSTALL EXISTING GUTTER SYSTEM AS NEEDED FOR ROOFING OPERATIONS.22.
EXISTING COPPER / METAL CAP AND RIDGE CAP TO REMAIN.23.
CONTRACTOR TO PROVIDE PRESERVATIVE TREATED WOOD BLOCKING AT LOCATION OF
ALUMINUM WALL PANELS DUE TO RAISED PARAPET HEIGHT (BASED ON PREVIOUS ROOF
REPLACEMENT, ALUMINUM WALL PANELS STOP SHORT AND REQUIRES ADDITIONAL
BLOCKING).
EXISTING ROOF EXPANSION JOINT METAL TO BE REMOVED AND REINSTALLED TO COMPLETE
ROOFING OPERATIONS.
25.
24.
26.
ROOFING SYSTEM COMPOSITION:
· 60-MIL FULLY ADHERED EPDM ROOFING MEMBRANE (WITH 25-YEAR DETAILS) CARRIED
UP AND OVER PARAPET WALL
· ADHESIVE APPLIED TAPER INSULATION
· MECHANICALLY FASTENED POLYISOCYANURATE INSULATION (1.5 INCHES PLUS 12" TAPER
START)
· SELF-ADHERING VAPOR BARRIER (AT ACOUSTICAL METAL DECK ONLY)
· EXISTING METAL / ACOUSTICAL METAL ROOF DECK (ASSUMED FLAT)
29.
ROOFING SYSTEM COMPOSITION:
· ASPHALT SHINGLES
·…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .