2025-009 - Addendum 2 - Vendor Questions.pdf
PDF 192 KB Posted
- Attached to
- 2025-009 - Ridgeview Loop Overlay State and local contract opportunity
- Solicitation number
- 2025-009
- Issued by
- El Paso County, Colorado
About this file
This document is Addendum 2 for Invitation for Bid (IFB) No. 2025-009 issued by the Elbert County Government Public Works Department in Kiowa, Colorado, addressing the Ridgeview Loop Overlay project. The addendum responds to three vendor questions regarding the road overlay project, clarifying key project details. Specifically, the document confirms a 1-year warranty period for the Performance and Payment (P&P) Bond, indicates that traffic control should be added as a separate bid item, and acknowledges that the square yardage estimate for the 2-inch overlay is approximately 20% less than the original scope of work, which aligns with the county's own estimate.
The addendum does not provide specific pricing terms, funding sources, or detailed project costs. It serves primarily as a clarification document to help potential bidders understand specific aspects of the project requirements and to ensure consistent interpretation of the project specifications. The document suggests the county is seeking a road overlay contractor who can complete the Ridgeview Loop project with clear understanding of the warranty expectations, traffic control needs, and precise measurement considerations.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 2025-009 - Addendum 1 - Vendor Questions.pdf | ||
| Ridgeview Loop in Wild Pointe.png | PNG image | |
| 2025-009 Ridgeview Loop Overlay - IFB.pdf | ||
| 2025-009 Ridgeview Loop Overlay - Scope of Work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Elbert County Government
Public Works Department
11330 CO-86
Kiowa, CO 80117
303-621-3157
Addendum: 2 IFB No. 2025-009 - Ridgeview Loop Overlay
1. For a P & P Bond what is the warranty period?
➢ 1 Year Warranty.
2. Is traffic control incidental to the work, or can a bid item be added for traffic control?
➢ Yes, please add traffic control.
3. From a rough take off on Google Earth, I’m coming up with approximately 20% less S.Y. than the scope of work calls out for on the 2” overlay. Is that intentional for overrun purposes?
➢ That is what our estimate came up with.