2-Norma Street Sewer Main Extension Project Drawings 4660.002.pdf
PDF 9 MB Posted
- Solicitation number
- Not on record
- Issued by
- Northampton County, Pennsylvania
About this file
This file contains construction drawing documents for the Norma Street Sewer Main Extension Project being conducted by Palmer Township, Northampton County, Pennsylvania. The project involves the extension of the existing sanitary sewer system with approximately 1,350 linear feet of 8-inch sanitary sewer pipe and installation of six sanitary sewer manholes, along with associated trenching, backfilling, testing, bypass pumping, and restoration work. The project is located along Norma Street, South Nulton Avenue, and Dalton Street in Palmer Township, Easton, Pennsylvania. Bids for construction will be received electronically via the PennBid Program until Monday, February 9th at 3:00 P.M. local time. A pre-bid conference is scheduled for Wednesday, January 28th at 1:00 P.M. at the Township's Public Works/Public Utilities Office located at 3500 Hartley Avenue, Easton, PA 18045, though attendance is not required. The project drawings indicate a limit of disturbance of 0.87 acres and include plan and profile views for multiple street segments, construction details for sanitary sewer installations, and erosion and sedimentation control measures. All surplus soils excavated within Palmer Township property must remain on-site with disposal location coordinated with the township.
The project is subject to American Iron and Steel (AIS) requirements under P.L. 113-76, the Consolidated Appropriations Act of 2014, and Davis Bacon Act Federal Wage Rates apply to this federally funded project. Contractors must comply with Pennsylvania Department of Environmental Protection (PADEP) minimum separation distances, including a minimum of ten feet horizontal separation between water and sanitary sewer lines and 36 inches vertical clearance below petroleum pipelines. The contractor is required to verify all existing facility locations and elevations through field investigation prior to construction, utilize rubber-tracked equipment or protective matting on paved surfaces, and maintain dust control measures throughout construction operations. Night work and weekend work may be required at the owner's discretion with no additional compensation to the contractor. All bidding documents are available at no cost through the PennBid Program, and further requirements regarding bid submittal, bid security, qualifications, and contract award procedures are specified in the Instructions to Bidders included in the complete bidding documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CIVIL LEGEND
LIMIT OF DISTURBANCE
Bh SwD
PROPOSED SANITARY SEWERSAN
PROPOSED SANITARY MANHOLE
NPDES PERMIT BOUNDARY
TEXT PROPOSED TEXT
MATCHLINE
MATCH LINE REFER TO DWG C-101
CS-12 CS-12 CS-12 COMPOST SILT SOCK
S
PROPOSED SANITARY LATERALSL
INLET FILTER PROTECTION
PROPOSED SANITARY CLEANOUTCO
ROCK CONSTRUCTION ENTRANCE
PROPOSED TREELINE
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\G-001.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
G-001
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
C O
VE
R
S H
EE
T
G
EN
ER
AL
JANUARY 21, 2026
BIDDING
PALMER TOWNSHIP, PENNSYLVANIA 18045
3 WELLER PL
PALMER TOWNSHIP
PALMER TOWNSHIP, NORTHAMPTON COUNTY, PA
NORMA STREET SEWER MAIN EXTENSION PROJECT
LOCATION / TOPOGRAPHICAL MAP
SCALE: 1"=2000'
REFERENCE: USGS 7.5 MINUTE SERIES (TOPOGRAPHIC MAP) - NAZARETH, PA
00 2000' 4000'
GENERAL PROJECT NOTES
SECTION INDICATOR
DETAIL INDICATOR
ELEVATION INDICATOR
DRAWING CONVENTIONS
?-201
A ?-301
A ?-301
?-501
SCALE:1 1" = 1'-0"
DRAWING TITLE
DRAWING NUMBER
SECTION LETTER
DRAWING NUMBER
ELEVATION LETTER
IDENTIFICATION NUMBER/LETTER
DRAWING TITLE
A
SHEET KEYNOTE SYMBOL
DEMOLITION KEYNOTE
SYMBOL
PHOTOGRAPH INDICATOR
PHOTOGRAPH
IDENTIFICATION
DRAWING NUMBER
DETAIL NUMBER
A
TEXT
INDICATES EXIST
CONDITIONS/FEATURES
INDICATES NEW
WORK/FEATURES
DRAWING INDEX
DWG. NO. DRAWING DESCRIPTION/TITLE
GENERAL
G-001 COVER SHEET
G-101 INDEX PLAN
CIVIL
C-101 NORMA STREET PLAN AND PROFILES (STA 0+00 TO STA 6+40)
C-102 NORMA STREET PLAN AND PROFILES (STA 6+40 TO STA 13+50)
C-103 DALTON STREET PLAN AND PROFILE (STA 0+00 TO STA 1+59)
C-104 SOUTH NULTON AVENUE PLAN AND PROFILES (STA -3+43 TO STA 0+16)
C-501 CONSTRUCTION DETAILS
C-701 RESTORATION DETAILS
EROSION AND SEDIMENTATION
ES-501 EROSION AND SEDIMENTATION CONTROL NOTES
ES-502 EROSION AND SEDIMENTATION CONTROL DETAILS
DENOTES REFERENCE TO ENLARGED PLAN
WITH DRAWING NUMBER INDICATED
X
?-XXX
DESIGN PA ONE CALL
UTILITY RESPONSE ADDRESS CONTACT INFORMATION CONTACT PERSON
ASTOUND BROADBAND POWERED BY RCN 5508 NORBATH BLVD,
NORTHAMPTON, PA 18067
EMAIL: eric.beers@astound.com
PHONE: 610-972-0597 ERIC BEERS
EASTON SUBURBAN WATER AUTHORITY
3700 HARTLEY AVE,
PO BOX 3819
EASTON , PA 180433819
PHONE: 610-258-7181 OFFICE PERSONNEL
COMCAST 1004 CORNERSTONE BLVD,
DOWNINGTOWN, PA 19335
EMAIL: johncedrick_salvatierra@comcast.com
PHONE: 267-271-9781 JOHN CEDRICK SALVATIERRA
PALMER TOWNSHIP 3500 HARTLEY AVE,
EASTON, PA 18045
EMAIL: skistler@palmertwp.com PHONE: 610-253-2995 ext. 1407 SCOTT KISTLER
PENNSYLVANIA ELECTRIC CO 341 WHITE POND DRIVE,
AKRON, OH 44320
EMAIL: madams@firstenergycorp.com
PHONE: 330-252-4013 MELLYSSA ADAMS
PPL ELECTRIC UTILITIES CORPORATION 437 BLUE CHURCH RD,
PAXINOS, PA 17860
EMAIL: dlhaupt@pplweb.com
PHONE: 570-490-5684 DOUG HAUPT
SERVICE ELECTRIC CABLE TV INC
2260 AVENUE A,
LVIP 1,
BETHLEHEM, PA 18017
EMAIL: rperich@sectv.com
PHONE: 610-625-8502 RICH PERICH
UGI 2121 CITY LINE ROAD,
BETHLEHEM, PA 18017
EMAIL: tsteward@ugi.com
PHONE: 484-226-8132 TIMOTHY STEWARD
VERIZON PENNSYLVANIA LLC EMAIL: 1call-verizon-pade@verizon.com OFFICE PERSONNEL
1-800-242-1776
(TOLL FREE)
"Pa. Law requires advance notification"
PA ONE CALL SERIAL NUMBER
COORDINATE PA PROJECT #: 8866034
SERIAL NUMBERS ISSUED:
20243461989 - PRELIMINARY
20260052607 - FINAL
1-800-242-1776
PE
NN
SY
LV
AN
IA ONE CALL SYSTEM
, INC
STOP-CALL BEFORE YOU D
IG
1. FIELD SURVEY BY OTT CONSULTING, INC.; DATED APRIL, 2024.
2. PROPERTY LINES SHOWN ARE APPROXIMATE AND HAVE NOT BEEN
SURVEYED OR FIELD VERIFIED.
3. THE LOCATION AND DIMENSIONS OF ALL SITE FEATURES SHOWN ARE
APPROXIMATE AND MUST BE VERIFIED IN THE FIELD BY THE
CONTRACTOR PRIOR TO BIDDING.
4. ALL UNDERGROUND UTILITIES SHALL BE LOCATED BY THE CONTRACTOR
PRIOR TO ANY EARTH MOVING ACTIVITIES, PURSUANT TO ACT 287.
UNDERGROUND UTILITY LOCATIONS MUST BE VERIFIED BY CALLING
1-800-242-1776.
5. ALL UNDERGROUND UTILITY LOCATIONS AND ELEVATIONS ON THE
CONSTRUCTION PLANS ARE APPROXIMATE LOCATIONS DELINEATED FROM
LIMITED FIELD MARKINGS AND AVAILABLE RECORDS. THEREFORE, ANY
UTILITIES NOT SHOWN OR NOT LOCATED AS SHOWN, SHALL NOT BE THE
CAUSE OF THE CONTRACTOR TO DENY RESPONSIBILITY FOR PROTECTION
AND/OR REPAIR DURING CONSTRUCTION. CONTRACTOR SHALL FIELD
VERIFY ALL EXISTING FACILITIES AND PROVIDE ALL PROTECTIVE
MEASUREMENTS, RESTRAINTS AND APPURTENANCES AS NECESSARY.
6. THESE DESIGN DRAWINGS MUST BE WORKED IN CONJUNCTION WITH THE
PROJECT MANUAL/SPECIFICATIONS.
7. CONTRACTOR SHALL PROVIDE ALL FITTINGS NECESSARY TO MAINTAIN
HORIZONTAL AND VERTICAL ALIGNMENT OF PIPELINES.
8. CONTRACTOR SHALL USE, MAINTAIN AND PROVIDE ADEQUATE, PROPER
SHORING DEVICES ON SITE AT ALL TIMES. CONTRACTOR SHALL CONFORM
TO ALL LOCAL, STATE AND FEDERAL REGULATIONS.
9. CONTRACTOR SHALL USE RUBBER - TRACKED EXCAVATOR OR PROVIDE 1"
THICK (MINIMUM) MATTING TO PROTECT PAVED LOCAL MUNICIPAL, STATE
AND PRIVATE ROAD SURFACES, DURING TRENCHING, EXCAVATION AND
GENERAL CONSTRUCTION OPERATIONS.
10. CONTRACTORS SHALL BE REQUIRED TO HAVE A POWER BROOM WITH
WATER SUPPLY AT ALL TIMES. CONTRACTOR SHALL USE WATER OR
OTHER MEANS NECESSARY FOR DUST CONTROL.
11. CONTRACTOR SHALL ABIDE BY ALL ISSUED PERMIT CONDITIONS
INCLUDING TRAFFIC CONTROL AND EROSION AND SEDIMENTATION
CONTROL.
12. CONTRACTOR SHALL PROVIDE ALL PIPE, MANHOLES, CLEANOUTS,
FITTINGS, TRACER WIRE AND OTHER COMPONENTS AS DESCRIBED IN THE
PROJECT MANUAL AND DRAWINGS.
13. THE CONTRACTOR IS ADVISED THAT NIGHT WORK AND/OR WORK ON
SATURDAY AND SUNDAY MAY BE REQUIRED. IT WILL BE THE DECISION OF
THE OWNER IF CONNECTIONS MUST BE MADE OTHER THAN NORMAL
WORKING HOURS. THE WORK WILL BE ACCOMPLISHED AT NO ADDITIONAL
COST TO THE OWNER.
14. CONTRACTOR SHALL ABIDE BY ALL PADEP MINIMUM SEPARATION
DISTANCES, INCLUDING BUT NOT LIMITED TO A MINIMUM OF TEN (10) FEET
HORIZONTAL SEPARATION BETWEEN ALL WATER AND SANITARY SEWER
LINES. SEWER MAINS MUST BE INSTALLED A MINIMUM OF 36" VERTICALLY
BELOW THE BOTTOM OF PETROLEUM PIPELINES. A MINIMUM OF 18"
VERTICAL AND 18" HORIZONTAL CLEARANCE IS REQUIRED BETWEEN
SEWER MAINS AND ALL OTHER UTILITIES.
15. LOCATIONS OF LATERALS AND CURB STOPS ARE SUBJECT TO CHANGE
UPON VERIFICATION WITH THE OWNER.
16. CONTRACTOR SHALL VERIFY WITH THE PROPERTY OWNER ALL LATERAL
LOCATIONS AND RECEIVE APPROVAL WITH OWNER FOR ALL WORK
LOCATED ON PROPERTY.
PROJECT AREAS
ISSUED FOR
S
S
SA
N
SA
N
SA
N
SSAN SAN
SSAN SAN
SSAN SAN
SSAN SAN SAN
SSAN SAN
S
SAN
C O
C O
CO
C O
CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12
CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\G-101.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
G-101
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
IN
D
EX
P
LA
N
G
EN
ER
AL
GENERAL PROJECT NOTES
1. REFER TO DRAWING G-001 FOR DRAWING INDEX, GENERAL PROJECT
NOTES AND LEGENDS.
SCALE:1 1" = 80'
INDEX PLAN
00 80' 160'
DWG C-101
DWG C-101
DWG C-102
DWG C-102
DWG C-103
DWG C-103
DWG C-104
DWG C-104
C S-12
-1 +2
-0
+6
0+
0+60 1+20 1+80 2+40 3+00 3+60 4+20 4+80 5+40 6+00
S
S
MH-7
STA 2+52
SAN SAN SAN SAN SAN SAN
S
MH-8
STA 4+73
SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN
MH-6
STA 0+16
CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12
C S-12 0+00
0+16
UoB UudB
UbB
UbB UbB UbB
UbB
UoB
UbB
UoB
UudB
0+00 0+30 0+60 0+90 1+20 1+50 1+80 2+10 2+40 2+70 3+00 3+30 3+60 3+90 4+20 4+50 4+80 5+10 5+40 5+70 6+00 6+30 6+40
MH-6
STA 0+16
TOP 410.24
INV IN 404.56 (8" S)
INV OUT 404.46 (8" E)
MH-7
STA 2+52
TOP 416.00
INV IN 403.53 (8" W)
INV OUT 403.43 (8" E)
MH-8
STA 4+73
TOP 417.22
INV IN 402.56 (8" W)
INV IN 402.56 (8" S)
INV OUT 402.46 (8" E)
232' of 8" PVC @ 0.40%
217' of 8" PVC @ 0.40%
255' of 8" PVC @ 1.82%
1' -6
M
IN
TY
P.
14' of 8" PVC @ 0.40%
Bh SwD
12" COMPOST FILTER SOCK
ROCK CONSTRUCTION ENTRANCE
LIMIT OF DISTURBANCE
CS-12 CS-12
INLET FILTER PROTECTION
PROPOSED TREELINE
0+00 0+16
14' of 8" PVC @ 2.17%
MH-8
STA 0+00
TOP 417.22
INV IN 402.56 (8" W)
INV IN 402.56 (8" S)
INV OUT 402.46 (8" E)
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\C-101.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
C-101
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
N O
R M
A
ST
R
EE
T
PL
AN
A
N D
P R
O
FI
LE
S
(S
TA
+0
TO
S
TA
+4
0) C
IV
IL
SCALE:1 1" = 30'
NORMA STREET PLAN (STA 0+00 TO STA 6+40)
00 30' 60'
SCALE:2 1" = 30'
NORMA STREET PROFILE (STA 0+00 TO STA 6+40)
1" = 3'
00 30' 60'
M A
TC
H
L
IN
E R
EF
ER
T O
D W
G C
-1
GENERAL PROJECT NOTES
1. REFER TO DRAWING G-001 FOR DRAWING INDEX, GENERAL PROJECT
NOTES AND LEGENDS.
2. WATERSHED INFO: SITE DRAINS TO LEHIGH RIVER (WWF-MF).
3. CONTRACTOR SHALL TEST PIT EXISTING UTILITIES AS NECESSARY TO
FACILITATE PROPOSED SANITARY SEWER MAIN AND LATERAL
INSTALLATION.
4. ALL SURPLUS SOILS EXCAVATED WITHIN PALMER TOWNSHIP PROPERTY
MUST REMAIN ON-SITE. ON-SITE DISPOSAL LOCATION TO BE
COORDINATED WITH THE TOWNSHIP. UNLESS SPECIFICALLY CALLED OUT,
THERE IS TO BE NO CUTTING, CLEARING OR GRUBBING OF TREES.
E&S LEGEND
SOIL TYPES
SHEET KEYNOTES
UbB UDORTHENTS, LIMESTONE, 0 TO 8 PERCENT SLOPES UoB URBAN LAND - DUFFIELD COMPLEX, 0 TO 8 PERCENT SLOPES UudB URBAN LAND - UDORTHENTS, LIMESTONE COMPLEX, 0 TO 8 PERCENT
SLOPES
1. CONTRACTOR TO PROVIDE TEST PIT TO VERIFY EXISTING PIPE
LOCATION, SIZE, MATERIAL, AND DEPTH.
2. CONTRACTOR, IN CONJUNCTION WITH PALMER TOWNSHIP, SHALL
COORDINATE FINAL LOCATION OF LATERAL WITH HOMEOWNER.
3. MINOR TREE REMOVAL ANTICIPATED. CONTRACTOR SHALL
COORDINATE WITH PALMER TOWNSHIP TO DETERMINE THE EXTENT OF
TREE REMOVAL BEFORE CONSTRUCTION BEGINS.
SANITARY SEWER
MANHOLE (TYP. 3 PLCS.)
C-501
LIMIT OF DISTURBANCE:
0.87 ACRES
12" COMPOST
FILTER SOCK (TYP.)
ES-502ROCK CONSTRUCTION
ENTRANCE
ES-502
14'-0" PLUGGED STUB
FOR FUTURE
8" PLUG
INV APPROX. 404.62
SCALE:3 1" = 30'
(STA 0+00 TO STA 0+16)
STONES CROSSING ROAD PROFILE
1" = 3' 00 30' 60'
8" PLUG
INV APPROX. 402.86
14'-0" PLUGGED STUB
FOR FUTURE
INLET FILTER
PROTECTION
ES-502
C-501
13+50
6+60 7+20 7+80 8+40 9+00 9+60 10+20 10+80 11+40 12+00 12+60
+2
S
MH-10
STA 7+33
SAN SAN SAN
S
MH-13
STA 10+33
SAN SAN SAN SAN SAN SAN SAN SAN
S
MH-14
STA 12+93
SAN SAN SAN SAN SAN SAN SAN
SAN
SL
CO
CS-12 CS-12 CS-12 CS-12 CS-12
CS-12 CS-12 CS-12 CS-12
CS-12
CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12 CS-12
CS-12 CS-12 CS-12 CS-12
0+00
0+16
UbB UbB UbB
UbB UoB
UbB UoB
UbB UoB
UoBUoB
UoB
6+40 6+60 6+90 7+20 7+50 7+80 8+10 8+40 8+70 9+00
9+00 9+30 9+60 9+90 10+20 10+50 10+80 11+10 11+40 11+70 12+00 12+30 12+60 12+90 13+20 13+5013+50
MH-10
STA 7+33
TOP 410.03
INV IN 397.80 (8" W)
INV IN 397.80 (8" S)
INV OUT 397.70 (8" E)
255' of 8" PVC @ 1.82%
296' of 8" PVC @ 3.53%
MH-13
STA 10+33
TOP 394.27
INV IN 387.24 (8" W)
INV OUT 387.14 (8" E)
MH-14
STA 12+93
TOP 391.06
INV IN 386.12 (8" W)
INV OUT 386.02 (8" S)
256' of 8" PVC @ 0.40% 54' of 8" PVC @ 0.40%
INV IN 385.81 (8" N)
296' of 8" PVC @ 3.53%
0+00 0+16
14' of 8" PVC @ 0.40%
MH-10
STA 0+00
TOP 410.03
INV IN 397.80 (8" W)
INV IN 397.80 (8" S)
INV OUT 397.70 (8" E)
Bh SwD
12" COMPOST FILTER SOCK
ROCK CONSTRUCTION ENTRANCE
LIMIT OF DISTURBANCE
CS-12 CS-12
INLET FILTER PROTECTION
PROPOSED TREELINE
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\C-102.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
C-102
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
N O
R M
A
ST
R
EE
T
PL
AN
A
N D
P R
O
FI
LE
S
(S
TA
+4
TO
S
TA
3+
C
IV
IL
SCALE:1 1" = 30'
NORMA STREET PLAN (STA 6+40 TO STA 13+50)
00 30' 60'
SCALE:2 1" = 30'
NORMA STREET PROFILE (STA 6+40 TO STA 9+00)
1" = 3'
00 30' 60'
M A
TC
H
L
IN
E R
EF
ER
T O
D W
G C
-1
SCALE:3 1" = 30'
NORMA STREET PROFILE (STA 9+00 TO STA 13+50)
1" = 3'
00 30' 60'
8"x6" WYE
SANITARY SEWER
MANHOLE
(TYP. 3 PLCS.)
C-501
SEWER
LATERAL
C-501
LIMIT OF DISTURBANCE:
0.87 ACRES
12" COMPOST
FILTER SOCK (TYP.)
ES-502
TIE-IN TO
EXISTING MANHOLE
C-501
SCALE:4 1" = 30'
(STA 0+00 TO STA 0+16)
ARLINGTON STREET PROFILE
1" = 3' 00 30' 60'
8" PLUG
INV APPROX. 397.86
14'-0" PLUGGED STUB
FOR FUTURE
GENERAL PROJECT NOTES
1. REFER TO DRAWING G-001 FOR DRAWING INDEX, GENERAL PROJECT
NOTES AND LEGENDS.
2. WATERSHED INFO: SITE DRAINS TO LEHIGH RIVER (WWF-MF).
3. CONTRACTOR SHALL TEST PIT EXISTING UTILITIES AS NECESSARY TO
FACILITATE PROPOSED SANITARY SEWER MAIN AND LATERAL
INSTALLATION.
4. ALL SURPLUS SOILS EXCAVATED WITHIN PALMER TOWNSHIP PROPERTY
MUST REMAIN ON-SITE. ON-SITE DISPOSAL LOCATION TO BE
COORDINATED WITH THE TOWNSHIP. UNLESS SPECIFICALLY CALLED OUT,
THERE IS TO BE NO CUTTING, CLEARING OR GRUBBING OF TREES.
E&S LEGEND
SOIL TYPES
SHEET KEYNOTES
UbB UDORTHENTS, LIMESTONE, 0 TO 8 PERCENT SLOPES UoB URBAN LAND - DUFFIELD COMPLEX, 0 TO 8 PERCENT SLOPES UudB URBAN LAND - UDORTHENTS, LIMESTONE COMPLEX, 0 TO 8 PERCENT
SLOPES
1. CONTRACTOR TO PROVIDE TEST PIT TO VERIFY EXISTING PIPE
LOCATION, SIZE, MATERIAL, AND DEPTH.
2. CONTRACTOR, IN CONJUNCTION WITH PALMER TOWNSHIP, SHALL
COORDINATE FINAL LOCATION OF LATERAL WITH HOMEOWNER.
3. MINOR TREE REMOVAL ANTICIPATED. CONTRACTOR SHALL
COORDINATE WITH PALMER TOWNSHIP TO DETERMINE THE EXTENT OF
TREE REMOVAL BEFORE CONSTRUCTION BEGINS.
0+00
0+60 1+20 1+59
S
MH-15
STA 0+00
SAN SAN SAN SAN
CO
UbB UoB
UbB UoB
UbB UoB UoB UoB
UoBUoB
0+00 0+30 0+60 0+90 1+20 1+501+59
MH-15
STA 0+00
TOP 383.84
INV OUT 379.53 (8" S)
155' of 8" PVC @ 0.40%
1+591+50
INV IN 378.91 (8" N)
1' -6
M
IN
TY
P.
Bh SwD
12" COMPOST FILTER SOCK
ROCK CONSTRUCTION ENTRANCE
LIMIT OF DISTURBANCE
CS-12 CS-12
INLET FILTER PROTECTION
PROPOSED TREELINE
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\C-103.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
C-103
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
D
AL
TO
N
S
TR
EE
T
PL
AN
A N
D P
R O
FI
LE
(S
TA
+0
TO
S
TA
+5
9) C
IV
IL
SCALE:1 1" = 30'
DALTON STREET PLAN (STA 0+00 TO STA 1+59)
00 30' 60'
00 30' 60'
SCALE:2 1" = 30'
DALTON STREET PROFILE (STA 0+00 TO STA 1+59)
1" = 3'
TIE-IN TO
EXISTING MANHOLE
C-501
SANITARY SEWER
MANHOLE
C-501
LIMIT OF DISTURBANCE:
0.87 ACRES
8"x6" WYE
ADD ALTERNATE NO. 1.1
INSTALL SANITARY SEWER MAIN
GENERAL PROJECT NOTES
1. REFER TO DRAWING G-001 FOR DRAWING INDEX, GENERAL PROJECT
NOTES AND LEGENDS.
2. WATERSHED INFO: SITE DRAINS TO LEHIGH RIVER (WWF-MF).
3. CONTRACTOR SHALL TEST PIT EXISTING UTILITIES AS NECESSARY TO
FACILITATE PROPOSED SANITARY SEWER MAIN AND LATERAL
INSTALLATION.
4. ALL SURPLUS SOILS EXCAVATED WITHIN PALMER TOWNSHIP PROPERTY
MUST REMAIN ON-SITE. ON-SITE DISPOSAL LOCATION TO BE
COORDINATED WITH THE TOWNSHIP. UNLESS SPECIFICALLY CALLED OUT,
THERE IS TO BE NO CUTTING, CLEARING OR GRUBBING OF TREES.
E&S LEGEND
SOIL TYPES
SHEET KEYNOTES
UbB UDORTHENTS, LIMESTONE, 0 TO 8 PERCENT SLOPES UoB URBAN LAND - DUFFIELD COMPLEX, 0 TO 8 PERCENT SLOPES UudB URBAN LAND - UDORTHENTS, LIMESTONE COMPLEX, 0 TO 8 PERCENT
SLOPES
1. CONTRACTOR TO PROVIDE TEST PIT TO VERIFY EXISTING PIPE
LOCATION, SIZE, MATERIAL, AND DEPTH.
2. CONTRACTOR, IN CONJUNCTION WITH PALMER TOWNSHIP, SHALL
COORDINATE FINAL LOCATION OF LATERAL WITH HOMEOWNER.
3. MINOR TREE REMOVAL ANTICIPATED. CONTRACTOR SHALL
COORDINATE WITH PALMER TOWNSHIP TO DETERMINE THE EXTENT OF
TREE REMOVAL BEFORE CONSTRUCTION BEGINS.
SEWER LATERAL
PLUGGED FOR FUTURE
C-501
CS-12
-3+43
-3+00 -2+40 -1+80 -1+20 -0+60 0+00
0+
1+
S
MH-4
STA -3+27
SSAN SAN SAN SAN SAN SAN SAN SAN SAN
SAN
SAN
SAN
SL
CO
CO
C S-12
CS-12
MH-6
STA 0+16
0+
0+00
UudBUudB
UoB
UoB UoB
UudB
UbB UudBUudB
UbB
-3+43 -3+30 -3+00 -2+70 -2+40 -2+10 -1+80 -1+50 -1+20 -0+90 -0+60 -0+30 0+00 0+16
14' of 8" PVC @ 0.40%
MH-4
STA -3+27
TOP 413.62
INV IN 406.02 (8" S)
INV IN 406.02 (8" E)
INV OUT 405.92 (8" N)
339' of 8" PVC @ 0.40%
MH-6
STA 0+16
TOP 410.24
INV IN 404.56 (8" S)
INV OUT 404.46 (8" E)
Bh SwD
12" COMPOST FILTER SOCK
ROCK CONSTRUCTION ENTRANCE
LIMIT OF DISTURBANCE
CS-12 CS-12
INLET FILTER PROTECTION
PROPOSED TREELINE
0+00 0+30
28' of 8" PVC @ 1.16%
MH-4
STA 0+00
TOP 413.62
INV IN 406.02 (8" S)
INV IN 406.02 (8" E)
INV OUT 405.92 (8" N)
1' -6
M
IN
TY
P.
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\C-104.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
C-104
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
SO
U
TH
N
U
LT
O N
A
VE
N U
E
PL
AN
A
N D
P R
O
FI
LE
S
(S
TA
-3 +4
TO
S
TA
+1
6) C
IV
IL
SCALE:1 1" = 30'
PLAN (STA -3+43 TO STA 0+16)
SOUTH NULTON AVENUE
00 30' 60'
00 30' 60'
SCALE:2 1" = 30'
PROFILE (STA -3+43 TO STA 0+16)
SOUTH NULTON AVENUE
1" = 3'
SANITARY SEWER
MANHOLE
SEWER LATERAL
(TYP. 2 PLCS.)
C-501
C-501
8"x6" WYE
INLET FILTER
PROTECTION
(TYP. 2 PLCS.)
ES-502
LIMIT OF DISTURBANCE:
0.87 ACRES
ADD ALTERNATE NO. 2.1
INSTALL SANITARY SEWER MAIN
8"x6" WYE
14'-0" PLUGGED STUB
FOR FUTURE
28'-0" PLUGGED STUB
FOR FUTURE
GENERAL PROJECT NOTES
1. REFER TO DRAWING G-001 FOR DRAWING INDEX, GENERAL PROJECT
NOTES AND LEGENDS.
2. WATERSHED INFO: SITE DRAINS TO LEHIGH RIVER (WWF-MF).
3. CONTRACTOR SHALL TEST PIT EXISTING UTILITIES AS NECESSARY TO
FACILITATE PROPOSED SANITARY SEWER MAIN AND LATERAL
INSTALLATION.
4. ALL SURPLUS SOILS EXCAVATED WITHIN PALMER TOWNSHIP PROPERTY
MUST REMAIN ON-SITE. ON-SITE DISPOSAL LOCATION TO BE
COORDINATED WITH THE TOWNSHIP. UNLESS SPECIFICALLY CALLED OUT,
THERE IS TO BE NO CUTTING, CLEARING OR GRUBBING OF TREES.
E&S LEGEND
SOIL TYPES
SHEET KEYNOTES
UbB UDORTHENTS, LIMESTONE, 0 TO 8 PERCENT SLOPES UoB URBAN LAND - DUFFIELD COMPLEX, 0 TO 8 PERCENT SLOPES UudB URBAN LAND - UDORTHENTS, LIMESTONE COMPLEX, 0 TO 8 PERCENT
SLOPES
1. CONTRACTOR TO PROVIDE TEST PIT TO VERIFY EXISTING PIPE
LOCATION, SIZE, MATERIAL, AND DEPTH.
2. CONTRACTOR, IN CONJUNCTION WITH PALMER TOWNSHIP, SHALL
COORDINATE FINAL LOCATION OF LATERAL WITH HOMEOWNER.
3. MINOR TREE REMOVAL ANTICIPATED. CONTRACTOR SHALL
COORDINATE WITH PALMER TOWNSHIP TO DETERMINE THE EXTENT OF
TREE REMOVAL BEFORE CONSTRUCTION BEGINS.
8" PLUG
INV APPROX. 406.08
00 30' 60'
SCALE:3 1" = 30'
(STA 0+00 TO STA 0+30)
ARCH STREET PROFILE
1" = 3'
8" PLUG
INV APPROX. 406.35
PLAN
WYE
SEWER MAIN
FL
O
W
6" P.V.C. SEWER
LATERAL
6" P.V.C. BEND(S)
AS REQUIRED
SCALE:4 NONE
SEWER LATERAL DETAIL
WYE
SECTION
6" P.V.C. SDR 26 LATERAL
SLOPE 1/4" PER FT. MIN.
6" BEND(S)
AS REQUIRED
NOTES:
1. LATERAL MUST BE STRAIGHT ALIGNMENT FROM HOUSE LATERAL TO SEWER MAIN WYE.
2. C.I. BOX SHALL BE TYLER 10" C.I. VALVE BOX TOP SECTION SLIP MODEL 10T-A WITH 5 1/4"
DROP LID MODEL 145349 MARKED "SEWER".
3. FLEXIBLE PIPE COUPLING TO BE FERNCO STRONG BACK RC 5000 SERIES.
4. HOME OWNER IS RESPONSIBLE FOR CONNECTION TO 4'-0" STUB.
5. WARNING TAPE SHALL BE PLACED AT A MINIMUM OF 2'-0" ABOVE ANY MAINLINE OR LATERAL.
6" PVC TEE
TO CURB OR EDGE
OF PAVING / ROW
TO CURB OR EDGE
OF PAVING / ROW
COVER MARKED - "SEWER"
MATCH EXISTING SURFACE
CAST IRON BOX
6" PVC CLEANOUT
END CAP
C O
N
ST
R U
C
TI
O N
D
ET
AI
LS
C
IV
IL
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\C-501.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
C-501
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
GENERAL PROJECT NOTES
1. REFER TO DRAWING G-001 FOR DRAWING INDEX, GENERAL PROJECT
NOTES AND LEGENDS.
4'-0" PIPE STUB
SCALE:8 NONE
CONCRETE ENCASEMENT DETAIL
PIPE SIZE "A"
4" - 16" 6"
18" - 48" 6"
54" - 84" 10"
UNDISTURBED EARTH
SEWER LINE
BARREL OF PIPE
BELL OF PIPE
NOTE:
1. ALL CONCRETE SHALL HAVE MINIMUM COMPRESSIVE
STRENGTH OF 3,000 PSI AT THE END OF 28 DAYS.
M
IN
"A
8" OD 8"
TRENCH WIDTH
SCALE:7 NONE
UNDER EXISTING WATER MAIN DETAIL
NEW SEWER LINE CROSSING
MECHANICAL JOINTS REQUIRED (TYP.)
<18"
NEW SEWER LINE
REFER TO CONCRETE
ENCASEMENT DETAIL
GRADE
4' -0
M
IN
NOTES :
1. WHEN VERTICAL SEPARATION IS LESS THAN 18" PROVIDE CONCRETE ENCASEMENT
ON UNDISTURBED GROUND. THE LENGTH OF THE ENCASEMENT SHALL BE EXTENDED
A MINIMUM OF 10 FEET BEYOND THE CENTERLINE OF THE WATER MAIN IN BOTH
DIRECTIONS.
2. ALL CONCRETE SHALL HAVE MINIMUM COMPRESSIVE STRENGTH OF 3,000 PSI AT THE
END OF 28 DAYS.
EQUAL
DISTANCE
EQUAL
DISTANCE
10'-0"
SCALE:6 NONE
OVER EXISTING WATER MAIN DETAIL
NEW SEWER LINE CROSSING
GRADE
4' -0
M
IN
NOTES :
1. WHEN VERTICAL SEPARATION IS LESS THAN 18" PROVIDE CONCRETE ENCASEMENT
ON UNDISTURBED GROUND. THE LENGTH OF THE ENCASEMENT SHALL BE EXTENDED
A MINIMUM OF 10 FEET BEYOND THE CENTERLINE OF THE WATER MAIN IN BOTH
DIRECTIONS.
2. ALL CONCRETE SHALL HAVE MINIMUM COMPRESSIVE STRENGTH OF 3000 PSI AT THE
END OF 28 DAYS.
NEW SEWER LINE
MECHANICAL JOINTS REQUIRED (TYP.)
<18"
REFER TO CONCRETE
ENCASEMENT DETAIL
EQUAL
DISTANCE
EQUAL
DISTANCE
10'-0"
POLYETHYLENE ENCASEMENT
SCALE:2 NONE
MANHOLE FRAME & COVER
CAST IRON STANDARD
EA
ST
J O
RD
AN
IR
O
N W
O
RK
S
1120141120 Z1
M
ADE IN USA
M O
/DAY/YR
(4) 7/8" DIA. HOLES
ON 33 3/4" DIA B.C.
25 1/2"
24 1/4"
7"5/ 8"
1/
2"
22"
26 3/16"
36"
FRAME PLAN
FRAME SECTION
EAST JORDAN I RON WORKS
SAN I TARY
S EWE R
MA DE I N USA
MO/DAY/YR X
PROD NO.
1120 A
GS
1 1/2" LETTER
(RECESSED FLUSH)
(2) CLOSED
PICKHOLES
24" DIA.
23 1/4" DIA.
GROOVE O.D.
1/
2"
/1 6"
COVER TOP PLAN
COVER BOTTOM PLAN
COVER SECTION
.1
-.0
.240" +.000 -.005
GROOVE DETAIL
7/
1" 1 3/8"
2 1/4"
PICKHOLE DETAIL
1/4" DIA.
NEOPRENE GASKET
1/
2"
NOTE: FOUR (4) BOLTS REQUIRED PER MANHOLE.
SCALE:3 NONE
MANHOLE FRAME - ANCHOR BOLT DETAIL
3/4" GALV. NUT
3/4"x 1 1/2" GALV. WASHER
3/4" GALV. ALL THREADED ROD
PRECAST CONCRETE TOP SECTION
3"
MIN.
2 1/2" MIN. PROJECTION
ABOVE FINAL COURSE OF
CONCRETE RISER GRADE RINGS
NOTES:
1. ALL PIPE TO MANHOLE CONNECTIONS SHALL BE MADE WITH A CAST-IN-PLACE
GASKET. (TYP) (A-LOK OR APPROVED EQUAL)
2. MANHOLES EXCEEDING A DEPTH OF 16 FEET SHALL PROVIDE PRE-CAST LANDING
PLATFORM.
SCALE:1 NONE
TYPICAL SANITARY SEWER MANHOLE DETAIL
REFER TO FRAME AND COVER DETAIL
24" MIN.
PRECAST CONCRETE GRADE
RINGS (VARIES, MIN. 6", MAX. 12")
HEAT SHRINKABLE
SHEET (TYP.)
VA
R
IE
S
9"
M
AX
CHANNEL6"
MAX.
5" 48" INSIDE
8"
24"x48" ADAPTOR
O-RING JOINT (TYP.)
PREFORMED PLASTIC
SEALING COMPOUND:
FS SS-S-210A, TYPE 1,
ROPE FORM (TYP.)
MANHOLE EXTERIOR TO
BE COATED WITH
BITUMASTIC SEALANT (TYP.)
48" RISERS
COATED ALUMINUM ALLOY MANHOLE
STEPS @ 12" OC WITH CAST IN
PRECAST BASE
6" MIN. COMPACTED
PennDOT 2A MODIFIED ON
UNDISTURBED SUBGRADE
<1 8"
WHEN VERTICAL SEPARATION IS
LESS THAN 18"; PROVIDE CONCRETE
ENCASEMENT ON UNDISTURBED
GROUND. THE LENGTH OF THE
ENCASEMENT SHALL BE EXTENDED
A MINIMUM OF 3 FEET BEYOND THE
CENTERLINE OF THE EXISTING UTILITY IN BOTH
DIRECTIONS
NEW SEWER LINE
REFER TO CONCRETE
ENCASEMENT DETAIL
NOTES :
1. ALL CONCRETE SHALL HAVE MINIMUM COMPRESSIVE STRENGTH OF
3000 PSI AT THE END OF 28 DAYS.
SCALE:5 NONE
UNDER EXIST UTILITY DETAIL
NEW SEWER LINE CROSSING
HPDE MANHOLE INSERT
LATERAL NOTES:
MATERIAL ALLOWED BY TOWNSHIP FOR
BUILDING GRAVITY AND LOW PRESSURE SEWERS
1. ALL MATERIAL USED FOR LATERAL INSTALLATIONS SHALL BE NEW,
FREE FROM DEFECTS AND CONFORM TO ALL STANDARDS SET FORTH
BY THE TOWNSHIP.
2. ALL LATERALS MUST BE INSPECTED BEFORE BACKFILLING. COMPLETED
DRAWINGS SHOWING THE EXACT LOCATION AND DEPTH OF LINE SHALL
BE SUBMITTED TO THE TOWNSHIP DURING FINAL INSPECTION OR THE
LATERAL WILL NOT BE AUTHORIZED TO USE.
3. ALL FEES MUST BE PAID IN PROPER AMOUNT BEFORE A CONNECTION
PERMIT WILL BE ISSUED.
1. GRAVITY BUILDING SEWER: SCH 80 PVC, MINIMUM DIAMETER 4 INCH.
2. GRAVITY SEWER LATERAL: SDR 26 PVC, MINIMUM DIAMETER 6 INCH.
3. GRAVITY SEWER MAIN: SDR 26 PVC, MINIMUM DIAMETER 8 INCH.
4. MINIMUM SLOPE FOR GRAVITY SEWERS AND LATERALS:
a. 4 INCH BUILDING SEWER: 2% (1/4 INCH PER FOOT).
b. 6 INCH LATERAL: 1.0% (1/8 INCH PER FOOT).
c. 8 INCH MAIN: 0.4%.
EXISTING
CONCRETE
MANHOLE
PROPOSED
SEWER PIPE
LINKSEAL OR
APPROVED EQUIVALANT
CORE DRILL PIPE OPENING;
PREVENT CRACKING AND
SPALLING. SIZE TO
ACCOMMODATE PIPE AND
EXPANDABLE SLEEVE
SCALE:9 NONE
TYPICAL TIE-IN TO EXISTING MANHOLE DETAIL
NOTES:
1. PROPOSED SEWER PIPE INVERT ELEVATION SHALL NOT BE BELOW
EXISTING SEWER INVERT ELEVATION.
2. PROPOSED SEWER PIPE SHALL BE LOCATED A MINIMUM OF 8" ABOVE OR
BELOW EXISTING MANHOLE JOINT.
3. AFTER CONNECTION OF PIPE TO MANHOLE, REMOVE CONCRETE CHANNEL
AS REQUIRED AND RECONSTRUCT CHANNEL.
4. KEEP GROUNDWATER, SURFACE WATER AND DEBRIS FROM ENTERING
EXISTING FACILITIES.
5. MAINTAIN EXISTING FLOW DURING CONSTRUCTION.
6. DROPS OVER 2 FT WILL REQUIRE AN INSIDE DROP CONNECTION.
NOTES;
1. PAVEMENT IS SAW CUT FULL DEPTH, WITH A BIT RANGE FROM 10" TO 18" IN DIAMETER;
RESULTING IN A "CORE".
2. THE CORE IS REMOVED AND SAVED FOR REUSE (IF STRUCTURALLY SOUND).
3. A PROTECTIVE STEEL RING IS PLACED TO PROTECT THE EDGE OF OPENING FROM
DAMAGE.
4. VACUUM EQUIPMENT IS USED TO EXCAVATE COMPACTED MATERIAL FROM BOTTOM OF
BASE COURSE TO UTILITY FACILITY.
5. UTILITY WORK IS PERFORMED (E.G., LEAK REPAIR, SERVICE CONNECTION OR DEPTH
OF UTILITY IS VERIFIED.)
6. UTILITY FACILITY IS PROTECTED WITH FINE MATERIAL.
7. SELF-MIXING FLOWABLE FILL MATERIAL IS PLACED FROM TOP OF FINE MATERIAL TO
BOTTOM OF BASE COURSE (FILL IS DESIGNED TO BE TRAFFIC-BERING IN 90 MINUTES).
8. NON-SHRINK GROUT IN PLACED (GROUT IS DESIGNED TO BE TRAFFIC BEARING IN
ABOUT 90 MINUTES).
9. THE REMOVED CORE (OR GENERIC EQUIVALENT REPLACEMENT CORE) IS PLACED IN
THE REMAINING OPENING (ORIGINAL ALIGNMENT AND ORIENTATION IS MAINTAINED IF
REMOVED CORE IS USED) FOR THE GROUT TO THE SURFACE TO FILL THE ANNULAR
SPACE AND CORE EXTRACTION HOLE.
10. THE RESTORED OPENING IS SEALED.
HOT SEAL ALL VERTICAL EDGES WITH
12" WIDE APPLICATION OF CRAFCO
ASPHALT RUBBER TYPE 2, CRAFCO
SUPERFLEX OR EQUIVALENT (TYPICAL)
'CORE' RESULTING FROM SAW-CUT
REMOVE AND REUSE IF POSSIBLE SAW-CUT
10" TO 18"
STEEL RING PLACED
AFTER SAW CUT IS MADE
PLACE NON-SHRINK GROUT
BEFORE PLACING 'CORE' SELF MIXING FLOWABLE FILL
TEST CORE
PROTECT UTILITY WITH
FINE BACKFILL MATERIAL
SCALE:4 TYPICAL TEST CORE FOR ASPHALT DETAIL
NONE
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\C-701.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
C-701
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
R
ES
TO
R
AT
IO
N D
ET
AI
LS
C
IV
IL
GENERAL PROJECT NOTES
1. REFER TO DRAWING G-001 FOR DRAWING INDEX, GENERAL PROJECT
NOTES AND LEGENDS.
SCALE:6 NONE
TYPICAL CONCRETE CURB DETAIL
NOTES:
1. EXISTING CURB REMOVAL SHALL BE IN COMPLETE SECTIONS (JOINT TO JOINT),
NOT PARTIAL SECTIONS.
2. PROVIDE MATERIALS AND CONSTRUCTION MEETING THE REQUIREMENTS OF
PENNDOT SPECIFICATIONS, PUBLICATION 408, CURRENT EDITION, SECTION 630.
3. SPACE CONTRACTION JOINTS IN UNIFORM LENGTHS OR SECTIONS, 10'-0" MAX. TO
4'-0" MIN.
4. PLACE 1/2" BITUMINOUS PREMOLDED EXPANSION JOINT FILLER MATERIAL AT
STRUCTURES AND AT THE END OF THE WORK DAY. CUT MATERIAL TO CONFORM
TO AREA ADJACENT TO CURB OR TO CONFORM TO CROSS SECTIONAL AREA OF
CURB.
5. EXPANSION JOINTS SHALL BE SPACED AS REQUIRED BY THE TOWNSHIP -
TYPICALLY 30' OC.
6. EXISTING FULL HEIGHT CURB CANNOT BE MODIFIED INTO DEPRESSED CURB.
CONCRETE CURB
6"2"
SUBGRADE
PAVEMENT STRUCTURE
7"
8"
SEAL CURB IN A NEAT AND
UNIFORM MANNER WITH KOCH 9005
RUBBERIZED BITUMINOUS SEALER
12"
MIN.
12"
MIN.
NOTES:
1. PIPE TO BE ENVELOPED IN, AND INITIAL 12" BACKFILL ON TOP TO BE 1B STONE.
2. BEDDING AND HAUNCHING TO BE 1B STONE (#8 AGGREGATE).
3. FINAL BACKFILL WITHIN PAVED AREAS TO BE 2A LIMESTONE, COMPACTED IN MAXIMUM LAYERS OF 8".
4. SELECT BACKFILL MAY BE UTILIZED WITHIN NON-PAVED AREAS.
5. TRENCH WIDTH SHOWN IS A MINIMUM REQUIREMENT. THE TRENCH WIDTH REQUIRED TO COMPLETE THE
UTILITY INSTALLATION IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR.
6. WARNING TAPE SHALL BE PLACED AT A MINIMUM OF 2'-0" ABOVE ANY MAINLINE OR LATERAL.
7. AN 8" CLAY CAP/PLUG MAY BE REQUIRED AS DIRECTED BY THE OWNER/ENGINEER. LOCATION TO BE
DETERMINED IN THE FIELD BASED ON SITE CONDITIONS.
SCALE:1 NONE
BACKFILL & PIPE EMBEDMENT DETAIL
TYPICAL EXCAVATION,
FINAL BACKFILL
12" INITIAL
BACKFILL
6" BEDDING
PROPOSED PIPE HAUNCHING
REFER TO SURFACE
RESTORATION DETAILS
NOTES:
1. TEMPORARY PAVING SHALL BE PLACED ON ALL BACK FILLED TRENCHES DAILY.
2. TEMPORARY PAVING SHALL BE MAINTAINED (FLUSH WITH ADJOINING PAVED SURFACES)
FOR A MINIMUM OF THIRTY DAYS PRIOR TO FINAL TRENCH RESTORATION.
REFER TO TRENCH
RESTORATION DETAILS
SCALE:2 RESTORATION DETAIL FOR PAVED ROADWAYS
TYPICAL TEMPORARY SURFACE
6" 2A COARSE
AGGREGATE COMPACTED
OR MATCH EXISTING,
WHICHEVER IS GREATER
SAW-CUT FULL DEPTH
EXISTING PAVEMENT (TYP.)
2" SUPERPAVE ASPHALT DESIGN,
25.0 MM, PG 64S-22,
4" BITUMINOUS MATERIAL REQUIRED
DURING WINTER MONTHS
REFER TO TRENCH
RESTORATION DETAILS
5' (MIN.)
SCALE:5 NONE
FOR PAVED TOWNSHIP ROADWAY/DRIVEWAY
TYPICAL SURFACE RESTORATION DETAIL
12" WIDE BITUMINOUS
SEAL. PG 64S-22 (TYP.)
SAW-CUT FULL DEPTH
EXISTING PAVEMENT (TYP.)
SAW-CUT FULL DEPTH
EXISTING PAVEMENT
(INITIAL SAW CUT) (TYP.)
6" 2A COARSE AGGREGATE
COMPACTED OR MATCH EXISTING,
WHICHEVER IS GREATER
1-1/2" SUPERPAVE ASPHALT DESIGN,
9.5 MM, PG 64S-22, SRL E, WEARING COURSE
3-1/2" MIN. SUPERPAVE ASPHALT DESIGN, 25.0 MM,
PG 64S-22, BASE OR TO A DEPTH OF EXISTING
BASE COURSE, WHICHEVER IS GREATER
NOTE:
1. FOR USE OUTSIDE OF PENNDOT LEGAL ROW.
REFER TO TRENCH
RESTORATION DETAILS
SCALE:3 NONE
FOR GRASS AREAS
TYPICAL SURFACE RESTORATION DETAIL
6" TOPSOIL AND SEED
ALL DISTURBED AREAS
NOTES:
1. CONTRACTOR SHALL REFER TO PERMANENT SEEDING SCHEDULE LISTED IN
EROSION AND SEDIMENT CONTROL PLAN.
NONE
2' -0
" M
IN
DETECTION TAPE
ER
O
SI
O
N A
N D
S
ED
IM
EN
TA
TI
O N
C O
N
TR
O L
N O
TE
S
ER
O
SI
O
N A
N D
S
ED
IM
EN
TA
TI
O N
4660.002
A
B
2 3
C
D
1 2 3
4 5 6
PROJECT NO.
APPROVED BY:
SCALE:
CHECKED BY:
PREPARED BY:
A
B
D
AT
E R
EV
4 5
IS
SU
ED
F
O R
/R
EV
IS
ED
C
AP
PD
D
DRAWING NO.
Entech Engineering - Printed: Jan. 9, 2026 H:\0004660.002\04-CAD\SheetFiles\ES-501.dwgLa st
E di te d by : s ba pt is ta
/2
1/
BI
D
D
IN
G M
BP
ES-501
PA
LM
ER
T
O W
N
SH
IP
PA
LM
ER
T O
W N
SH
IP
, N O
R
TH
AM
PT
O N
C O
U N
TY
, P
EN
N
SY
LV
AN
IA
N O
R M
A
ST
R
EE
T
SE
W
ER
M
AI
N E
XT
EN
SI
O
N P
R O
JE
C
T
MBP
SC
SAB
AS NOTED
GENERAL PROJECT NOTES
1. REFER TO DRAWING G-001 FOR DRAWING INDEX, GENERAL PROJECT
NOTES AND LEGENDS.
STANDARD NOTES
1. ALL EARTH DISTURBANCES, INCLUDING CLEARING AND GRUBBING AS WELL AS CUTS AND FILLS
SHALL BE DONE IN ACCORDANCE WITH THE APPROVED E&S PLAN. A COPY OF THE APPROVED
DRAWINGS (STAMPED, SIGNED AND DATED BY THE REVIEWING AGENCY) MUST BE AVAILABLE AT
THE PROJECT SITE AT ALL TIMES. THE REVIEWING AGENCY SHALL BE NOTIFIED OF ANY
CHANGES TO THE APPROVED PLAN PRIOR TO IMPLEMENTATION OF THOSE CHANGES. THE
REVIEWING AGENCY MAY REQUIRE A WRITTEN SUBMITTAL OF THOSE CHANGES FOR REVIEW
AND APPROVAL AT ITS DISCRETION.
2. AT LEAST 7 DAYS PRIOR TO STARTING ANY EARTH DISTURBANCE ACTIVITIES, INCLUDING
CLEARING AND GRUBBING, THE OWNER AND/OR OPERATOR SHALL INVITE ALL CONTRACTORS,
THE LANDOWNER, APPROPRIATE MUNICIPAL OFFICIALS, THE E&S PLAN PREPARER, THE PCSM
PLAN PREPARER, THE LICENSED PROFESSIONAL RESPONSIBLE FOR OVERSIGHT OF CRITICAL
STAGES OF IMPLEMENTATION OF THE PCSM PLAN, AND A REPRESENTATIVE FROM THE LOCAL
CONSERVATION DISTRICT TO AN ON-SITE PRE-CONSTRUCTION MEETING.
3. AT LEAST 3 DAYS PRIOR TO STARTING ANY EARTH DISTURBANCE ACTIVITIES, OR EXPANDING
INTO AN AREA PREVIOUSLY UNMARKED, THE PENNSYLVANIA ONE CALL SYSTEM INC. SHALL BE
NOTIFIED AT 1-800-242-1776 FOR THE LOCATION OF EXISTING UNDERGROUND UTILITIES.
4. ALL EARTH DISTURBANCE ACTIVITIES SHALL PROCEED IN ACCORDANCE WITH THE SEQUENCE
PROVIDED ON THE PLAN DRAWINGS. DEVIATION FROM THAT SEQUENCE MUST BE APPROVED IN
WRITING FROM THE LOCAL CONSERVATION DISTRICT OR BY THE DEPARTMENT PRIOR TO
IMPLEMENTATION.
5. AREAS TO BE FILLED ARE TO BE CLEARED, GRUBBED, AND STRIPPED OF TOPSOIL TO REMOVE
TREES, VEGETATION, ROOTS AND OTHER OBJECTIONABLE MATERIAL.
6. CLEARING, GRUBBING, AND TOPSOIL STRIPPING SHALL BE LIMITED TO THOSE AREAS DESCRIBED
IN EACH STAGE OF THE CONSTRUCTION SEQUENCE. GENERAL SITE CLEARING, GRUBBING AND
TOPSOIL STRIPPING MAY NOT COMMENCE IN ANY STAGE OR PHASE OF THE PROJECT UNTIL THE
E&S BMPS SPECIFIED BY THE BMP SEQUENCE FOR THAT STAGE OR PHASE HAVE BEEN
INSTALLED AND ARE FUNCTIONING AS DESCRIBED IN THIS E&S PLAN.
7. AT NO TIME SHALL CONSTRUCTION VEHICLES BE ALLOWED TO ENTER AREAS OUTSIDE THE LIMIT
OF DISTURBANCE BOUNDARIES SHOWN ON THE PLAN MAPS. THESE AREAS MUST BE CLEARLY
MARKED AND FENCED OFF BEFORE CLEARING AND GRUBBING OPERATIONS BEGIN.
8. TOPSOIL REQUIRED FOR THE ESTABLISHMENT OF VEGETATION SHALL BE STOCKPILED AT THE
LOCATION(S) SHOWN ON THE PLAN MAPS(S) IN THE AMOUNT NECESSARY TO COMPLETE THE
FINISH GRADING OF ALL EXPOSED AREAS THAT ARE TO BE STABILIZED BY VEGETATION. EACH
STOCKPILE SHALL BE PROTECTED IN THE MANNER SHOWN ON THE PLAN DRAWINGS. STOCKPILE
HEIGHTS SHALL NOT EXCEED 35 FEET. STOCKPILE SLOPES SHALL BE 2H: 1V OR FLATTER.
9. IMMEDIATELY UPON DISCOVERING UNFORESEEN CIRCUMSTANCES POSING THE POTENTIAL FOR
ACCELERATED EROSION AND/OR SEDIMENT POLLUTION, THE OPERATOR SHALL IMPLEMENT
APPROPRIATE BEST MANAGEMENT PRACTICES TO MINIMIZE THE POTENTIAL FOR EROSION AND
SEDIMENT POLLUTION AND NOTIFY THE LOCAL CONSERVATION DISTRICT AND/OR THE REGIONAL
OFFICE OF THE DEPARTMENT.
10. ALL BUILDING MATERIALS AND WASTES SHALL BE REMOVED FROM THE SITE AND RECYCLED OR
DISPOSED OF IN ACCORDANCE WITH THE DEPARTMENT'S SOLID WASTE MANAGEMENT
REGULATIONS AT 25 PA. CODE 260.1 ET SEQ., 271.1, AND 287.1 ET. SEQ. NO BUILDING MATERIALS
OR WASTES OR UNUSED BUILDING MATERIALS SHALL BE BURNED, BURIED, DUMPED, OR
DISCHARGED AT THE SITE.
11. ALL OFF-SITE WASTE AND BORROW AREAS MUST HAVE AN E&S PLAN APPROVED BY THE LOCAL
CONSERVATION DISTRICT OR THE DEPARTMENT FULLY IMPLEMENTED PRIOR TO BEING
ACTIVATED.
12. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ANY MATERIAL BROUGHT ON SITE IS
CLEAN FILL.
CLEAN FILL IS DEFINED AS: UNCONTAMINATED, NON-WATER SOLUBLE, NON-DECOMPOSABLE,
INERT, SOLID MATERIAL. THE TERM INCLUDES SOIL, ROCK, STONE, DREDGED MATERIAL, USED ASPHALT, AND BRICK, BLOCK OR CONCRETE FROM CONSTRUCTION AND DEMOLITION ACTIVITIES
THAT IS SEPARATE FROM OTHER WASTE AND IS RECOGNIZABLE AS SUCH. THE TERM DOES NOT
INCLUDE MATERIALS PLACED IN OR ON THE WATERS OF THE COMMONWEALTH UNLESS
OTHERWISE AUTHORIZED. (THE TERM "USED ASPHALT" DOES NOT INCLUDE MILLED ASPHALT OR
ASPHALT THAT HAS BEEN PROCESSED FOR RE-USE).
CLEAN FILL AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE: FILL
MATERIALS AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE STILL QUALIFIES
AS CLEAN FILL PROVIDED THE TESTING REVEALS THAT THE FILL MATERIAL CONTAINS
CONCENTRATIONS OF REGULATED SUBSTANCES THAT ARE BELOW THE RESIDENTIAL LIMITS IN
TABLES FP-1A AND FP-1B FOUND IN THE DEPARTMENT'S POLICY "MANAGEMENT OF FILL".
ANY PERSON PLACING CLEAN FILL THAT HAS BEEN AFFECTED BY A SPILL OR RELEASE OF A
REGULATED SUBSTANCE MUST USE FORM FP-001 TO CERTIFY THE ORIGIN OF THE FILL
MATERIAL AND THE RESULTS OF THE ANALYTICAL TESTING TO QUALIFY THE MATERIAL AS
CLEAN FILL. FORM FP-001 MUST BE RETAINED BY THE OWNER OF THE PROPERTY RECEIVING
THE FILL.
ENVIRONMENTAL DUE DILIGENCE: THE APPLICANT MUST PERFORM ENVIRONMENTAL DUE
DILIGENCE TO DETERMINE IF THE FILL MATERIALS ASSOCIATED WITH THE PROJECT QUALIFY AS
CLEAN FILL. ENVIRONMENTAL DUE DILIGENCE IS DEFINED AS: INVESTIGATIVE TECHNIQUES,
INCLUDING, BUT NOT LIMITED TO, VISUAL PROPERTY INSPECTIONS, ELECTRONIC DATA BASE
SEARCHES, REVIEW OF PROPERTY OWNERSHIP, REVIEW OF PROPERTY USE HISTORY,
SANBORN MAPS, ENVIRONMENTAL QUESTIONNAIRES, TRANSACTION SCREENS, ANALYTICAL
TESTING, ENVIRONMENTAL ASSESSMENTS OR AUDITS. ANALYTICAL TESTING IS NOT A
REQUIRED PART OF DUE DILIGENCE UNLESS VISUAL INSPECTION AND/OR REVIEW OF THE PAST
LAND USE OF THE PROPERTY INDICATES THAT THE FILL MAY HAVE BEEN SUBJECTED TO A
SPILL OR RELEASE OF REGULATED SUBSTANCE. IF THE FILL MAY HAVE BEEN AFFECTED BY A
SPILL OR RELEASE OF A REGULATED SUBSTANCE, IT MUST BE TESTED TO DETERMINE IF IT
QUALIFIES AS CLEAN FILL. TESTING SHOULD BE PERFORMED IN ACCORDANCE WITH APPENDIX A
OF THE DEPARTMENT'S POLICY "MANAGEMENT OF FILL".
FILL MATERIAL THAT DOES NOT QUALIFY AS CLEAN FILL IS REGULATED FILL. REGULATED FILL IS
WASTE AND MUST BE MANAGED IN ACCORDANCE WITH THE DEPARTMENT'S MUNICIPAL OR
RESIDUAL WASTE REGULATIONS BASED ON 25 PA. CODE CHAPTERS 287 RESIDUAL WASTE
MANAGEMENT OR 271 MUNICIPAL WASTE MANAGEMENT, WHICHEVER IS APPLICABLE. THESE
REGULATIONS ARE AVAILABLE ON-LINE AT WWW.PACODE.COM
13. ALL PUMPING OF WATER FROM ANY WORK AREA SHALL BE DIRECTED INTO A PUMPED WATER
FILTER BAG AND DISCHARGED TO AN UNDISTURBED VEGETATED AREA.
14. UNTIL THE SITE IS STABILIZED, ALL EROSION AND SEDIMENT BMPS SHALL BE MAINTAINED
PROPERLY. MAINTENANCE SHALL INCLUDE INSPECTIONS OF ALL EROSION AND SEDIMENT BMPS
AFTER EACH RUNOFF EVENT AND ON A WEEKLY BASIS. ALL PREVENTATIVE AND REMEDIAL
MAINTENANCE WORK, INCLUDING CLEAN OUT, REPAIR, REPLACEMENT, RE-GRADING,
RESEEDING, RE-MULCHING AND RE-NETTING MUST BE PERFORMED IMMEDIATELY. IF THE E&S
BMPS FAIL TO PERFORM AS EXPECTED, REPLACEMENT BMPS, OR MODIFICATIONS OF THOSE
INSTALLED WILL BE REQUIRED.
15. A LOG SHOWING DATES THAT E&S BMPS WERE INSPECTED AS WELL AS ANY DEFICIENCIES
FOUND AND THE DATE THEY WERE CORRECTED SHALL BE MAINTAINED ON THE SITE AND BE
MADE AVAILABLE TO REGULATORY AGENCY OFFICIALS AT THE TIME OF INSPECTION.
16. SEDIMENT TRACKED ONTO ANY PUBLIC ROADWAY OR SIDEWALK SHALL BE RETURNED TO THE
CONSTRUCTION SITE BY THE END OF EACH WORK DAY AND DISPOSED IN THE MANNER
DESCRIBED IN THIS PLAN. IN NO CASE SHALL THE SEDIMENT BE WASHED, SHOVELED, OR SWEPT
INTO ANY ROADSIDE DITCH, STORM SEWER, OR SURFACE WATER.
17. ALL SEDIMENT REMOVED FROM BMPS SHALL BE DISPOSED OF IN THE MANNER DESCRIBED ON
THE PLAN DRAWINGS.
18. AREAS WHICH ARE TO BE TOP SOILED SHALL BE SCARIFIED TO A MINIMUM DEPTH OF 3 TO 5 INCHES - 6 TO 12 INCHES ON COMPACTED SOILS -- PRIOR TO PLACEMENT OF TOPSOIL. AREAS TO BE VEGETATED SHALL HAVE A MINIMUM 4 INCHES OF TOPSOIL IN PLACE PRIOR TO SEEDING AND
MULCHING. FILL SLOPES SHALL HAVE A MINIMUM OF 2 INCHES OF TOPSOIL.
19. ALL FILLS SHALL BE COMPACTED AS REQUIRED TO REDUCE EROSION, SLIPPAGE, SETTLEMENT, SUBSIDENCE OR OTHER RELATED PROBLEMS. FILL INTENDED TO SUPPORT BUILDINGS, STRUCTURES AND CONDUITS, ETC. SHALL BE COMPACTED IN ACCORDANCE WITH LOCAL
REQUIREMENTS OR CODES.
20. ALL EARTHEN FILLS SHALL BE PLACED IN COMPACTED LAYERS NOT TO EXCEED 9 INCHES IN
THICKNESS.
21. FILL MATERIALS SHALL BE FREE OF FROZEN PARTICLES, BRUSH, ROOTS, SOD, OR OTHER
FOREIGN OR OBJECTIONABLE MATERIALS THAT WOULD INTERFERE WITH OR PREVENT
CONSTRUCTION OF SATISFACTORY FILLS.
22. FROZEN MATERIALS OR SOFT, MUCKY, OR HIGHLY COMPRESSIBLE MATERIALS SHALL NOT BE
INCORPORATED INTO FILLS.
23. FILL SHALL NOT BE PLACED ON SATURATED OR FROZEN SURFACES.
24. SEEPS OR SPRINGS ENCOUNTERED DURING CONSTRUCTION SHALL BE HANDLED IN
ACCORDANCE WITH THE STANDARD AND SPECIFICATION FOR SUBSURFACE DRAIN OR OTHER
APPROVED METHOD.
25. ALL GRADED AREAS SHALL BE PERMANENTLY STABILIZED IMMEDIATELY UPON REACHING
FINISHED GRADE. CUT SLOPES IN COMPETENT BEDROCK AND ROCK FILLS NEED NOT BE
VEGETATED. SEEDED AREAS WITHIN 50 FEET OF A SURFACE WATER, OR AS OTHERWISE SHOWN
ON THE PLAN DRAWINGS, SHALL BE BLANKETED ACCORDING TO THE STANDARDS OF THIS PLAN.
26. IMMEDIATELY AFTER EARTH DISTURBANCE ACTIVITIES CEASE IN ANY AREA OR SUBAREA OF THE PROJECT, THE OPERATOR SHALL STABILIZE ALL DISTURBED AREAS. DURING NON-GERMINATING MONTHS, MULCH OR PROTECTIVE BLANKETING SHALL BE APPLIED AS DESCRIBED IN THE PLAN.
AREAS NOT AT FINISHED GRADE, WHICH WILL BE REACTIVATED WITHIN 1 YEAR, MAY BE
STABILIZED IN ACCORDANCE WITH THE TEMPORARY STABILIZATION SPECIFICATIONS. THOSE
AREAS WHICH WILL NOT BE REACTIVATED WITHIN 1 YEAR SHALL BE STABILIZED IN ACCORDANCE
WITH THE PERMANENT STABILIZATION SPECIFICATIONS.
27. PERMANENT STABILIZATION IS DEFINED AS A MINIMUM UNIFORM, PERENNIAL 70% VEGETATIVE
COVER OR OTHER PERMANENT NON-VEGETATIVE COVER WITH A DENSITY SUFFICIENT TO
RESIST ACCELERATED EROSION. CUT AND FILL SLOPES SHALL BE CAPABLE OF RESISTING
FAILURE DUE TO SLUMPING, SLIDING, OR OTHER MOVEMENTS.
28. E&S BMPS SHALL REMAIN FUNCTIONAL AS SUCH UNTIL ALL AREAS TRIBUTARY TO THEM ARE
PERMANENTLY STABILIZED OR UNTIL THEY ARE REPLACED BY ANOTHER BMP APPROVED BY THE
LOCAL CONSERVATION DISTRICT OR THE DEPARTMENT.
29. UPON COMPLETION OF ALL EARTH DISTURBANCE ACTIVITIES AND PERMANENT STABILIZATION
OF ALL DISTURBED AREAS, THE OWNER AND/OR OPERATOR SHALL CONTACT THE LOCAL
CONSERVATION DISTRICT FOR AN INSPECTION PRIOR TO REMOVAL/CONVERSION OF THE E&S
BMPS.
30. AFTER FINAL SITE STABILIZATION HAS BEEN ACHIEVED, TEMPORARY EROSION AND SEDIMENT
BMPS MUST BE REMOVED OR CONVERTED TO PERMANENT POST CONSTRUCTION STORM
WATER MANAGEMENT BMPS. AREAS DISTURBED DURING REMOVAL OR CONVERSION OF THE
BMPS SHALL BE STABILIZED IMMEDIATELY. IN ORDER TO ENSURE RAPID RE-VEGETATION OF
DISTURBED AREAS, SUCH REMOVAL/CONVERSIONS ARE TO BE DONE ONLY DURING THE
GERMINATING SEASON.
31. UPON COMPLETION OF ALL EARTH DISTURBANCE ACTIVITIES AND PERMANENT STABILIZATION
OF ALL DISTURBED AREAS, THE OWNER AND/OR OPERATOR SHALL CONTACT THE LOCAL
CONSERVATION DISTRICT TO SCHEDULE A FINAL INSPECTION.
32. FAILURE TO CORRECTLY INSTALL E&S BMPS, FAILURE TO PREVENT SEDIMENT-LADEN RUNOFF
FROM LEAVING THE CONSTRUCTION SITE, OR FAILURE TO TAKE IMMEDIATE CORRECTIVE
ACTION TO RESOLVE FAILURE OF E&S BMPS MAY RESULT IN ADMINISTRATIVE, CIVIL, AND/OR CRIMINAL PENALTIES BEING INSTITUTED BY THE DEPARTMENT AS DEFINED IN SECTION 602 OF
THE PENNSYLVANIA CLEAN STREAMS LAW. THE CLEAN STREAMS LAW PROVIDES FOR UP TO
$10,000 PER DAY IN CIVIL PENALTIES, UP TO $10,000 IN SUMMARY CRIMINAL PENALTIES, AND UP
TO $25,000 IN MISDEMEANOR CRIMINAL PENALTIES FOR EACH VIOLATION.
33. UPON TEMPORARY CESSATION OF AN EARTH DISTURBANCE OR ANY STAGE OR PHASE OF AN
ACTIVITY WHERE A CESSATION OF EARTH DISTURBANCE ACTIVITIES EXCEED 4 DAYS, THE SITE
SHALL BE IMMEDIATELY SEEDED, MULCHED OR OTHERWISE PROTECTED FROM ACCELERATED
EROSION AND SEDIMENTATION PENDING FUTURE EARTH DISTURBANCE ACTIVITIES.
34. UNDERGROUND UTILITIES CUTTING THROUGH ANY ACTIVE CHANNEL SHALL BE IMMEDIATELY
BACKFILLED AND THE CHANNEL RESTORED TO ITS ORIGINAL CROSS-SECTION AND PROTECTIVE
LINING. ANY BASE FLOW WITHIN THE CHANNEL SHALL BE CONVEYED PAST THE WORK AREA IN
THE MANNER DESCRIBED IN THIS PLAN UNTIL SUCH RESTORATION IS COMPLETE.
CONSTRUCTION SEQUENCE NOTES
1. PRIOR TO CONSTRUCTION THE PROPOSED LIMIT OF DISTURBANCE (LOD) SHALL BE DELINEATED
AND STAKED IN THE FIELD.
· RESPONSIBILITY FOR STAGING/LAYDOWN FOR THE PROJECT FALLS ON THE CONTRACTOR.
CONTRACTOR SHALL FINALIZE A LOCATION THAT HAS AN APPROVED E&S PLAN AND/OR IS
LOCATED ON AN AREA THAT IS ENTIRELY EXISTING IMPERVIOUS.
2. INSTALL STABILIZED ROCK CONSTRUCTION ENTRANCES FOLLOWING DETAIL AND
SPECIFICATIONS ON ES-502. VEHICLES AND EQUIPMENT SHALL ENTER AND EXIT ONLY BY MEANS
OF THE STABILIZED ROCK CONSTRUCTION ENTRANCE. IF EXCESSIVE AMOUNTS OF SEDIMENT
ARE BEING DEPOSITED ON ROADWAY, EXTEND LENGTH OF ROCK CONSTRUCTION ENTRANCE BY
50 FOOT INCREMENTS UNTIL CONDITION IS ALLEVIATED OR INSTALL WASH RACK. WASHING THE
ROADWAY OR SWEEPING DEPOSITS INTO ROADWAY DITCHES, SEWERS, CULVERTS, OR OTHER
DRAINAGE COURSES IS NOT ACCEPTABLE.
3. INSTALL ALL PERIMETER BMP'S AS SHOWN ON THE PLANS. PERIMETER BMP'S INCLUDE ALL
PROJECT SILT SOCK AND INLET PROTECTION
4. THE CONTRACTOR WILL INSPECT WEEKLY AND AFTER EACH RAIN EVENT, THE PROJECT'S
EROSION AND SEDIMENTATION CONTROLS DURING THE ENTIRE ACTIVE CONSTRUCTION
STAGES. THE CONTRACTOR WILL BE RESPONSIBLE FOR THE INSTALLATION, OPERATION,
MAINTENANCE, AND REMOVAL OF ALL EROSION AND SEDIMENTATION CONTROLS THROUGHOUT
THE ENTIRE CONSTRUCTION PROJECT.
THE CONTRACTOR MUST IMMEDIATELY REPAIR ANY DAMAGED EROSION CONTROLS (BMPS).
SEDIMENT REMOVED FROM THE BMPS SHALL BE DISPOSED OF IN LANDSCAPED AREAS OUTSIDE
OF STEEP SLOPES, WETLANDS, FLOODPLAINS, OR DRAINAGE SWALES AND IMMEDIATELY
STABILIZED OR PLACED IN TOPSOIL STOCKPILES.
5. CLEAR AND GRUB PROJECT AREA AS NECESSARY.
6. THE CONTRACTOR SHALL THEN PERFORM THE NECESSARY EXCAVATION, BACKFILL, AND
COMPACTION FOR THE SANITARY SEWER INSTALLATION. REMOVE EXISTING SECTIONS AND
STRUCTURES ALONG THE PROPOSED ALIGNMENT AS CONSTRUCTION OF THE NEW SANITARY
SEWER PROGRESSES. TRENCHING WORK WILL BE LIMITED TO THE AMOUNT THAT CAN BE
EXCAVATED, BACKFILL INSTALLED AND STABILIZED WITHIN ONE WORKING DAY. TRENCHING
SHALL CONFORM TO THE FOLLOWING BMP PROCEDURE:
· WHEN CALLED FOR, BACKFILL WITH “SELECT BACKFILL”, IN WHICH CASE SOIL WILL BE
STORED UNTIL PIPE INSTALLATION IS COMPLETE. THIS EXCAVATED MATERIAL WILL BE LAID
UP GRADIENT OF THE OPEN TRENCH DIRECTING DRAINAGE BACK INTO THE TRENCH, THUS
PREVENTING SEDIMENT FROM MIGRATING TO NEARBY DRAINAGE CHANNELS.
· IF EXCAVATIONS NEED TO BE DEWATERED, THE WATER IN THE EXCAVATIONS SHALL BE
PUMPED AND DISCHARGED INTO A PUMPED WATER FILTER BAG OR OTHER APPROVED
FACILITY. DISCHARGE POINTS SHOULD BE ESTABLISHED TO PROVIDE FOR MAXIMUM
DISTANCE TO ACTIVE WATERWAYS.
7. ONCE UTILITY CONSTRUCTION IS COMPLETE, BEGIN ROADWAY RESTORATION. COMPACT THE
ROADWAY SUBGRADE, INSTALL THE STONE FOR GRAVEL ROADWAY, INSTALL TOPSOIL AND
SEED (STABILIZE) ON ALL DISTURBED AREAS. AFTER FINAL STABILIZATION HAS BEEN ACHIEVED, TEMPORARY E&S BMP SHALL BE REMOVED. AREAS DISTURBED DURING REMOVAL OF
TEMPORARY E&S BMPS ARE TO BE IMMEDIATELY STABILIZED.
8. IF CONSTRUCTION IS TERMINATED OR SUSPENDED PRIOR TO CONSTRUCTION COMPLETION, ALL
EXPOSED SOIL AREAS SHALL BE SEEDED WITH TEMPORARY SEEDING AND MULCHED
IMMEDIATELY. SEED FOLLOWING TEMPORARY SEEDING GUIDELINES ON ES-501.
9. AFTER FINAL STABILIZATION HAS BEEN ACHIEVED, TEMPORARY E&S BMPS SHALL BE REMOVED.
AREAS DISTURBED DURING REMOVAL OF TEMPORARY E&S BMPS ARE TO BE IMMEDIATELY
STABILIZED.
NOTE: A COPY OF THE EROSION AND SEDIMENT CONTROL PLAN MUST BE AVAILABLE AT THE
PROJECT SITE DURING CONSTRUCTION UNTIL THE SITE IS STABILIZED.
GROUND COVER (SEE GROUND COVER REQUIREMENTS ON DRAWINGS)
AFTER THE EARTH DISTURBANCE ACTIVITY IS COMPLETED, THE DISTURBED AREA MUST BE
REVEGETATED. THE VEGETATIVE COVER MUST BE A UNIFORM 70% PERENNIAL VEGETATIVE COVER, WITH A DENSITY CAPABLE OF RESISTING ACCELERATED EROSION AND SEDIMENTATION. ANOTHER OPTION IS TO USE AN ACCEPTABLE BMP, WHICH PERMANENTLY MINIMIZES ACCELERATED EROSION
AND SEDIMENTATION.
TEMPORARY SEEDING
TEMPORARY SEEDING WILL BE PERFORMED DURING THE GERMINATION SEASON (APRIL TO
OCTOBER) FOR THE ESTABLISHMENT OF GRASS SEED ON DISTURBED AREAS BEFORE THE
START OF THE DORMANT SEASON. DURING THE NON-GERMINATION SEASON, MULCH SHALL BE
APPLIED TO THE DISTURBED SURFACES AND THE SEED MIXTURE WILL BE ADDED AT THE START
OF THE GERMINATION PERIOD.
· ALL GRASS AREAS DISTURBED BY THE WORK OF THIS PROJECT SHALL BE SEEDED AS
FOLLOWS:
O APPLY AGRICULTURAL LIME AND FERTILIZER AS FOLLOWS FOR TEMPORARY SEEDING:
¨ AGRICULTURAL LIME - 40 POUNDS PER 1,000 SQUARE FEET
¨ FERTILIZER - 12.5 POUNDS PER 1,000 SQUARE FEET
O FERTILIZER SHALL BE A COMMERCIAL TYPE 10-10-10.
O TEMPORARY SEED MIXTURE ANNUAL RYEGRASS -- 1 POUND PER 1,000 SQUARE FEET.
· ALL TEMPORARY SEEDING SHALL BE MULCHED. TEMPORARY SEEDING SHALL BE WATERED
AS REQUIRED TO DEVELOP COVER. NON-POTABLE UTILITY WATER SHALL BE PROVIDED BY
THE CONTRACTOR.
· MULCH SHALL BE STRAW, SHALL BE CLEAN AND FREE FROM NOXIOUS WEEDS, AND SHALL
BE APPLIED AT THE RATE OF 140 POUNDS PER 1,000 SQUARE FEET (3.0 TONS PER ACRE).
O APPLICATION OF MULCH SHALL BE USED IN CONJUNCTION WITH CRIMPING, A
TACKIFIER OR A SIMILAR METHOD IN ORDER TO PREVENT MULCH FROM BEING
WINDBLOWN.
PERMANENT SEEDING
PERMANENT SEEDING SHALL TAKE PLACE IN ALL DISTURBED AREAS AS FOLLOWS:
· UPON COMPLETION OF EARTH DISTURBANCE ACTIVITIES, THE SITE SHALL BE IMMEDIATELY
STABILIZED.
· THE FOLLOWING SHALL BE SPREAD AND WORKED INTO THE TOPSOIL TO A DEPTH OF 2 TO 4
INCHES.
O AGRICULTURAL LIME - 240 POUNDS PER 1,000 SQUARE FEET
O FERTILIZER - 25 POUNDS PER 1,000 SQUARE FEET
·· THE FERTILIZER SHALL BE A COMMERCIAL TYPE 10-20-20.
·· NOTE - IF AGRICULTURAL LIME AND FERTILIZER HAVE BEEN APPLIED PREVIOUSLY
TO THE GROUND WHERE THE PERMANENT SEED IS TO BE APPLIED, THE LIME AND
FERTILIZER RATES SHALL BE REDUCED BY THE AMOUNT BY WHAT HAS BEEN
APPLIED PREVIOUSLY.
· PERMANENT SEED MIXTURE: THE FOLLOWING SEED MIXTURES SHALL BE APPLIED AS
FOLLOWS:
Ø NOTE: AREAS DESIGNATED AS OPEN SPACE/LAWN SHOULD FOLLOW
SPECIES AND SEEDING RATE SPECIFIED IN SEED MIXTURE #2. AREAS
DESIGNATED AS MEADOW SHOULD FOLLOW SPECIES AND SEEDING RATE
SPECIFIED IN SEED MIXTURE #3. EACH VEGETATED AREA WILL BE
SUPPLEMENTED WITH SEED MIXTURE #1, WHICH SERVES AS NURSE CROP
FOR THE OTHER MIXTURES.
O APPLY MULCH TO ALL PERMANENTLY SEEDED AREAS.
O MATERIALS: STRAW, AIR-DRIED AND FREE FROM UNDESIRABLE SEEDS AND COURSE
MATERIALS. APPLICATION: 140 POUNDS PER 1,000 SQUARE FEET.
· APPLICATION OF MULCH SHALL BE USED IN CONJUNCTION WITH CRIMPING, A TACKIFIER OR
A SIMILAR METHOD IN ORDER TO PREVENT MULCH FROM BEING WINDBLOWN.
· EROSION CONTROL BLANKETS SHALL BE USED ON SLOPES 3:1 (H:V) OR GREATER.
MAINTENANCE PROGRAM
EMERGENCY EROSION PROTECTION
IF EROSION DOES OCCUR, THE CONTRACTOR SHALL REPAIR AND RESEED THOSE AREAS OR USE
OTHER STABILIZATION METHODS AS REQUIRED. THE CONTRACTOR SHALL USE JUTE, WOOD FIBER, OR OTHER TIE DOWN FILTER NETTING ON TOP OF THE NEW SEED AS REQUIRED, REGARDLESS OF
THE SLOPE OF THE LAND.
MULCHED AREAS SHALL BE CHECKED WEEKLY AND AFTER EACH RAIN EVENT FOR DAMAGE, UNTIL
THE MULCHING IS NO LONGER NECESSARY FOR PROTECTION AGAINST EROSION. DAMAGED
PORTIONS OF THE MULCH OR TIE DOWN MATERIALS SHALL BE REPAIRED AS SOON AS DISCOVERED.
PERIODIC INSPECTION PROGRAM
THE CONTRACTOR WILL INSPECT THE PROJECT'S EROSION AND SEDIMENTATION CONTROLS
WEEKLY AND AFTER EACH RAIN EVENT UNTIL THE SITE HAS ACHIEVED FINAL STABILIZATION. THE
CONTRACTOR WILL BE RESPONSIBLE FOR THE INSTALLATION, OPERATION, MAINTENANCE, AND
REMOVAL OF ALL EROSION AND SEDIMENTATION CONTROLS. ALL PREVENTATIVE AND REMEDIAL
MAINTENANCE WORK, INCLUDING CLEAN OUT REPAIR, REPLACEMENT, REGRADING, RESEEDING,
REMULCHING, AND RENETTING MUST BE PERFORMED IMMEDIATELY. SEDIMENT THAT HAS BEEN
TRAPPED BY THE COMPOST SOCK WILL BE REMOVED AS REQUIRED, AND IN ALL CASES, BEFORE THE
ACCUMULATION HAS REACHED HALF THE HEIGHT OF THE SOCK. COMPOST SOCK WILL BE
RE-ANCHORED, REPAIRED, OR REPLACED AS NECESSARY. SEDIMENT MUST BE REMOVED FROM SILT
SACKS AFTER EACH RUNOFF EVENT, OR WHEN THE DISTANCE BETWEEN THE GRATE AND THE
SEDIMENT LEVEL IN THE SILT SACK IS REDUCED TO 18". SILT SACKS WILL BE REPAIRED, OR REPLACED AS NECESSARY. ALL OTHER CONTROLS WILL BE INSPECTED ON THE SAME SCHEDULE.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .