2-2026.04.30 NCC Fowler Center Luthier Expansion Bid Permit Set - DRAWINGS.pdf
PDF 21 MB Posted
- Attached to
- NCC Fowler Luthier Expansion
- Solicitation number
- Not on record
- Issued by
- Northampton County, Pennsylvania
About this file
NCC Fowler Luthier Expansion - Bid Set Documents
This is a comprehensive architectural and engineering bid/permit set for the Fowler Luthier Expansion project at Northampton Community College, located at 511 E. Third Street, Bethlehem, Pennsylvania 18015. The project encompasses complete renovation of approximately 10,363 square feet across basement and first floor levels, including selective demolition of interior walls, doors, finishes, ceilings, and associated mechanical, electrical, and plumbing components, followed by installation of new walls, flooring, paint, ceilings, casework, finishes, and MEP systems. The scope includes work in specialized areas such as spray booths, buffing rooms, sanding stations, audio labs, storage areas, and teaching spaces designed for luthier fabrication and guitar repair instruction. Electronic sealed bids via PennBid are due no later than 10:00 AM prevailing time on May 21, 2026, with public bid opening immediately following. The Request for Information (RFI) deadline is May 12, 2026 at 4:00 PM. Project documents became available April 30, 2026 at www.PennBid.net at no cost to prospective bidders.
The bid contract is structured as a single prime general construction contract encompassing mechanical, plumbing, fire protection, and electrical work, with bid security required at 10 percent of the base bid amount in the form of a bid bond. Successful bidders must furnish both a Performance Bond and Payment Bond, each equal to 100 percent of the contract amount with satisfactory corporate surety appearing on the Treasury Department's current Circular 570 list and authorized to conduct business in Pennsylvania. The project manual specifies compliance with the 2021 International Building Code, Pennsylvania Uniform Construction Code, and applicable fire and mechanical codes. Construction is classified as Use Group B (Business) with Type 2A construction, requiring fire-rated systems and full sprinkler coverage. Contractor responsibilities include all demolition, site coordination, protection of existing conditions to remain, equipment installation per manufacturer specifications, and comprehensive final testing and commissioning of all mechanical, plumbing, fire protection, and electrical systems. Bidders must verify all existing conditions and dimensions on-site prior to submission, as the contractor assumes responsibility for any discrepancies between drawings and field conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-2026.04.30 NCC Fowler Center Luthier Expansion Bid Permit Set - PROJECT MANUAL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXISTING PARTITION
TO REMAIN
EXISTING PARTITION
TO BE DEMOLISHED
NEW PARTITION &
TYPE SYMBOL
1t
CEILING TYPE
CEILING HEIGHT
BUILDING SECTION
DESIGNATION
A101
1 Ref
R e f
1 Ref
R e f
SHEET REFERENCE
ELEVATION NAME/NUMBER
Symbols Legend Abbreviations
CLG CEILING
COL COLUMN
CONC CONCRETE
CONST JT CONSTRUCTION JOINT
CONT CONTINUOUS
CPT CARPET
CTR CENTER
D
D.F. DRINKING FOUNTAIN
DEMO DEMOLITION
DIA DIAMETER
DIM DIMENSION
DN DOWN
DR DOOR
DTL DETAIL
DWG DRAWING
E
E EAST
E.I.F.S. EXTERIOR INSULATION FINISH SYSTEM
E.J. EXPANSION JOINT
E.W.C. ELECTRIC WATER COOLER
EA EACH
ELEC ELECTRIC(AL)
ELEV ELEVATOR
A/C AIR CONDITIONING
A.C.M. ALUMINUM COMPOSITE MATERIAL
A.C.T. ACOUSTICAL CEILING TILE
A.F.F. ABOVE FINISHED FLOOR
A.W.C. ACOUSTIC WALL COVERING
ABV ABOVE
ADD'L ADDITIONAL
ALT ALTERNATE
ALUM ALUMINUM
ANOD ANODIZED
APPROX APPROXIMATE(LY)
AVG AVERAGE
B
BD BOARD
BLDG BUILDING
BRG BEARING
BSMT BASEMENT
BTM BOTTOM
BTWN BETWEEN
BUR BUILT-UP ROOFING
BW BOTH WAYS
C
C.I.P. CAST-IN-PLACE
C.J. CONTROL JOINT
C.L. CENTER LINE
C.M.T. CERAMIC MOSAIC TILE
C.M.U. CONCRETE MASONRY UNIT
C.T. CERAMIC TILE
EQ EQUAL
EQUIP EQUIPMENT
EXIST EXISTING
EXP EXPANSION
EXT EXTERIOR
F
F.E. FIRE EXTINGUISHER
F.E.C. FIRE EXTINGUISHER CABINET
F.F.E. FINISH FLOOR ELEVATION
FD FLOOR DRAIN
FDN FOUNDATION
FIN FL FINISH FLOOR
FL FLOOR
FT (') FOOT
FTG FOOTING
G
G.W.B. GYPSUM WALLBOARD
GALV GALVANIZED
H
H.M. HOLLOW METAL
HCP HANDICAP(PED)
HT HEIGHT
HORIZ HORIZONTAL
I
IN INCH(ES)
INCL INCLUDE(S)
INFO INFORMATION
INSUL INSULATION (INSULATED)
INT INTERIOR
J
JAN JANITOR
JT JOINT
L
LAV LAVATORY
LTG LIGHTING
M
M.B. MARKER BOARD
M.O. MASONRY OPENING
MAINT MAINTENANCE
MAS MASONRY
MAT'L MATERIAL
MAX MAXIMUM
MDF MEDIUM DENSITY FIBERBOARD
MDO MEDIUM DENSITY OVERLAY
MECH MECHANICAL
MEP MECHANICAL, ELECTRICAL, PLUMBING
MFR MANUFACTURER
MIN MINIMUM
MIR MIRROR
MISC MISCELLANEOUS
MR MOISTURE RESISTANT
MTD MOUNTED
MTL METAL
N
N.I.C. NOT IN CONTRACT
N.T.S. NOT TO SCALE
O
O.C. ON CENTER
O.D. OUTSIDE DIAMETER
OH OVERHEAD
OPNG OPENING
OPP OPPOSITE
ORIG ORIGINAL
P
P LAM PLASTIC LAMINATE
P.B. PIN BOARD
PERF PERFORATED
PERIM PERIMETER
PL PLATE
PLAS PLASTER
PLBG PLUMBING
PLWD PLYWOOD
PNL PANEL
PREFAB PREFABRICATED
PREFIN PREFINISHED
PT PAINT
PTD PAINTED
Q
Q.T. QUARRY TILE
QLTY QUALITY
QTY QUANTITY
R
R RISERS (STAIR)
r RADIUS
R.D. ROOF DRAIN
R.O. ROUGH OPENING
R.W.C. RAIN WATER CONDUCTOR
REINF REINFORCE(D)(ING)(MENT)
REQ'D REQUIRED
REV REVISION, REVISED
RFRIG REFRIGERATOR
RM ROOM
RUB RUBBER
S
S.A.B. SOUND ATTENUATION BLANKET
S.G.T. STRUCTURAL GLAZED TILE
S.P.R. SINGLE- PLY ROOFING
S.S.M. SOLID SURFACE MATERIAL
SCHED SCHEDULE
SECT SECTION
SEP SEPARATE
SF SQUARE FOOT
SHWR SHOWER
SIM SIMILAR
SPEC SPECIFICATIONS
SPEC'D SPECIFIED
SQ SQUARE
SS STAINLESS STEEL
STD STANDARD
STL STEEL
STOR STORAGE
STRUC STRUCTURAL
SUSP SUSPEND(ED)
T
T TREAD
T & G TONGUE AND GROOVE
T.E.S. TACTILE EXIT SIGN
T/ TOP OF
T/CONC TOP OF CONCRETE
T/FTG TOP OF FOOTING
T/JST TOP OF JOIST
T/STL TOP OF STEEL
T/WALL TOP OF WALL
TB TACK BOARD
T.B.R. TO BE REMOVED
THRES THRESHOLD
TLT TOILET
T.S. TACK STRIP
TYP TYPICAL
TZ TERRAZZO
U
U.H. UNIT HEATER
U.O.N. UNLESS OTHERWISE NOTED
U/S UNDERSIDE OF
V
V.T. VINYL TILE
VAR VARIES
VAT VINYL ASBESTOS TILE
VCT VINYL COMPOSITION TILE
VERT VERTICAL
V.I.F. VERIFY IN FIELD
VWC VINYL WALL COVERING
W
W.B. DRY ERASE WHITE BOARD
W.C. WATER CLOSET
W.W.F. WELDED WIRE FABRIC
W/ WITH
W/O WITHOUT
WD WOOD
WGT WEIGHT
WIN WINDOW
Y
YD YARD
VIEW REFERENCE SYMBOLS
DETAIL
WALL SECTION DESIGNATION
INTERIOR ELEVATION
SHEET REFERENCE
DETAIL NUMBER
SHEET REFERENCE
DETAIL NUMBER
SHEET REFERENCE
DETAIL NUMBER
A101
SHEET REFERENCE
ELEVATION NAME/NUMBER
BUILDING ELEVATION
Ref
1R e f
1 R e f
Ref
DRAWING SYMBOLS
ROOM IDENTIFICATION
ROOM NUMBER
AREA (WHERE
APPLIES)
DOOR SYMBOL & NUMBER
WINDOW TYPE INDICATOR
WINDOW TYPE
DESIGNATION
CEILING IDENTIFICATION
PARTITIONS
NEW DOOR/FRAME
PARTITION TYPE
DESIGNATION
STRUCTURAL GRID IDENTIFICATION
0 GRIDLINE
DESIGNATION
LEVEL ELEVATION
LEVEL NAME
VERTICAL
DATUM
T.O.S. HP: 40'-0"
POINT ELEVATION
VERTICAL
DATUM
DESCRIPTION
EXISTING DOOR/FRAME
EXISTING DOOR
TO BE DEMOLISHED
DOORS
A
A300
A350
A500
FOS FACE OF STUD
FRT FIRE RATED TREATED
MCJ MASONRY CONTROL JOINT
SYS SYSTEM
Corridor
417 SF
XX
X'-X"
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :0
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
G001
Cover Sheet
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
Northampton Community College
Owner:
NORTHAMPTON COMMUNITY COLLEGE
511 E. Third St.
Bethlehem, PA 18015 CONTACT: William S. Smith
TELEPHONE: (610) 861-4109
EMAIL: wssmith@northampton.edu
Architect:
MKSD, LLC
1209 Hausman Rd., Suite A Allentown, PA 18104 CONTACT: Nick Hewes
TELEPHONE: (610) 366-2081
EMAIL: nsh@mksdarchitects.com
511 E. Third St.
Bethlehem, PA 18015
Drawing List: Location Map: Site / Campus Map:
G001 Cover Sheet
G002 Code Information and Life Safety Plans
G003 Temporary Partition and Egress Locations
AD100 Basement Demolition Plan
AD101 First Floor Demolition Plan
A100A Basement New Work Plan, Partition Types
A101A First Floor New Work Plan, Door Schedule, & Interior Elevations
A350 Plan & Section Details
A400 Basement & First Floor RCPs
A701 Finish Plans & Schedules
A800 Basement & First Floor Equipment Plans
M000 Mechanical Legend, Abbreviations, & Symbols
M100 Basement Mechanical Ductwork Demolition Plan
M101 First Floor Mechanical Ductwork Demolition Plan
M102 Basement Mechanical Piping Demolition Plan
M103 First Floor Mechanical Piping Demolition Plan
M200 Basement Mechanical Ductwork New Work Plan
M201 First Floor Mechanical Ductwork New Work Plan
M300 Basement Mechanical Piping New Work Plan
M301 First Floor Mechanical Piping New Work Plan
M400 Partial Basement Mechanical Room Plan
M500 Mechanical Details
M600 Mechanical Schedules
P000 Plumbing Legend, Abbreviations, & Symbols
P100 Basement Plumbing Demolition Plan
P101 First Floor Plumbing Demolition Plan
P200 Basement Plumbing New Work Plan
P201 First Floor Plumbing New Work Plan
P300 Plumbing Schedules & Details
FP000 Fire Protection Legend, Abbreviations, Symbols, & Details
FP100 Basement Fire Protection Demolition Plan
FP101 First Floor Fire Protection Demolition Plan
FP200 Basement Fire Protection New Work Plan
FP201 First Floor Fire Protection New Work Plan
E000 Electrical Legend, Abbreviations, & Symbols
E100 Basement Electrical Demolition Plan
E101 First Floor Electrical Demolition Plan
E200 Basement Lighting Plan - New Work
E201 First Floor Lighting Plan - New Work
E300 Basement Power, Telecom, Fire Alarm Plan - New Work
E301 First Floor Power, Telecom, Fire Alarm Plan - New Work
E400 Electrical Details and Schedules
MEP Engineer:
HB Engineers
2900 Hamilton Blvd #200 Allentown, PA 18103 CONTACT: Thom Hoffman
TELEPHONE: 610-395-0101
EMAIL: thoffman@hbengineers.com
Fowler Luthier Expansion
No. Date Description
958 SF
Lacquer & UV
Spray Room
324 SF
UV Curing &
Filling
179 SF
Storage
149 SF
Storage
127 SF
Office
009 474 SF
Trad. Filling & Oil
Finish
374 SF
Finish Sanding
344 SF
Buffing
570 SF
Plastics
103 SF
Sound Booth 1 004A
399 SF
Storage/Inventory
223 SF
Storage/Inventory
272 SF
Maintenance
Office
159 SF
Audio Lab
103 SF
Sound Booth 2 004B
47 SF
Sink 012A
330 SF
Corridor 0-A
347 SF
Corridor 0-B
Maximum Travel Distance = 300'-0" Travel Distance = 97'-4"
Maximum Travel Distance = 300'-0" Travel Distance = 104'-7"
Department Legend
Business
CIRCULATION
Storage
437 SF
Corr.
0-C
1436 SF
Student
Workshop
213 SF
Student
Workshop
Storage
963 SF
Guitar Tech Lab
538 SF
Main Luthier
Assembly
209 SF
Guitar Repair &
Setup
356 SF
Reception
132 SF
Entrance
EXISTING
EXISTING
EXISTING
EXISTING
EXISTING
Existing Stair Exit Capacity = 280 Occs.
Existing Stair Exit Capacity = 280 Occs.
Maximum Travel Distance = 300'-0" Travel Distance = 75'-3"
Maximum Travel Distance = 300'-0" Travel Distance = 91'-6"
Maximum Travel Distance = 300'-0" Travel Distance = 88'-3"
Department Legend
Business
CIRCULATION
Storage
NOT IN SCOPE
BASEMENT
PROJECT SCOPE
NOT IN SCOPE
FIRST FLOOR
PROJECT SCOPE
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :0
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
G002
Code Information and Life Safety Plans
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
Use Group Classification (IBC 2021 Ch 3) B - Business
Construction Type (T601) Type 2A
Existing Building Height 6 stories, existing to remain Existing Building Area 6 stories, existing to remain
Area of Renovation Total Basement Level Area of Work 5,941 SF Total First Floor Area of Work 4,422 SF
Fire Protection Systems Automatic Sprinkler System (Section 903) Existing - modified as needed from modified spaces Manual Fire Alarm (Section 907) Existing - modified as needed from modified spaces Fire Extinguishers (Section 906) Use Extinguishers rated 2A:60B:C - 10lb, spaced as shown on Plans, with a max travel distance of 150'-0" between Extinguishers
Exit Access Travel Distance (T1017.2) With Sprinkler System= 300 ft
Number of Exits Required (T1006.2.1, T1006.3.1) 3 min, provided
Corridor Fire-Resistance Rating (T1020.2) With Sprinkler System= 0 hour
Fire Resistance Rating Requirements (T601) Structural Frame 1 HR (2 HR existing) Exterior Bearing Wall 1 HR (2 HR existing) Interior Bearing Wall 1 HR Interior Non-Bearing Wall 0 HR Floor Construction 1 HR Roof Construction 1 HR
Interior Wall and Ceiling Finish Requirements (T803.13) Exit Enclosures & Exit Passageways Class B Corridors Class C Rooms and Enclosed Spaces Class C
Design Occupant Load (T1004.5) Calculated By Use - See Life Safety Plan Business Group 1 Occupant per 150 SF gross
TOTAL: 66 occupants
Egress Width per Occupant Served (Section 1005) 0.2" per occupant for other egress components 0.2" per occupant: 56 occupants x .2" = 11.2" required
36" Doors = 34" clear width - Complies
CODE INFORMATION: Municipality: City of Bethlehem
All construction has been designed to meet the provisions of the Pennsylvania Uniform Construction Code (UCC). The UCC Administration and Enforcement regulation has adopted the following codes for use throughout the Commonwealth of Pennsylvania, effective 1/1/2026.
Pennsylvania Uniform Construction Code International Existing Building Code 2021 (IEBC 2021) including all appendices & resource information
International Building Code 2021 (IBC 2021) excluding chapter 1 (most of its requirements are incorporated in Chapter 403 of the UCC regulation). Chapter 27 (Electrical) requires that all electrical components, equipment and systems in buildings and structures covered by the IBC comply with the requirements of NFPA 70-2017, National Electrical Code
Chapter 11, International Building Code 2021 Accessibility Requirements
International Energy Conservation Code 2021 (IECC 2021)
International Fire Code 2021 (IFC 2021) only to the extent referenced in Chapter 35 of the IBC 2021
International Mechanical Code 2021 (IMB 2021)
International Plumbing Code 2021 (IPC 2021)
American National Standard Accessible and Usable Buildings and Facilities 2009 (ICC A117.1-2009)
Project Summary:
This project includes the complete existing fitout demolition and subsequent renovation of a 4,422 sf Luthier Lab & Fabrication space on the 1st Floor of the project building and a 5,941 sf Luthier Fabrication space in the Basement of the project building. The project includes no change of use group and no renovations to the existing shell building.
1. All work shall be installed and erected in accordance with building and safety codes mandated by federal, state and local government laws, ordinances and regulations; industry standards and the requirements and rules and regulations of all public utilities. All local permits and fees shall be paid by the installing Contractor unless otherwise noted.
2. Prior to submitting a proposal, contractor/bidder shall have carefully examined the site and be familiar with the actual conditions and existing improvements, equipment and their locations: and Contractor/bidder understands that the actual conditions and existing structures, improvements, equipment and their locations may be different from that depicted on the plans and specifications provided.
In submitting a bid and entering into an agreement, Contractor/bidder relies upon its examination of the site and the actual conditions at the site. Any and all additional labor/material/equipment that may be required as a result of Contractor/bidder's failure to follow these requirements shall be provided by the Contractor/bidder at no additional cost to the Owner.
3. Contractor shall field verify all conditions and dimensions at the job site prior to start of work and shall be responsible to notify the Architect of any and all discrepancies in writing. If discrepancies occur between drawings and/or project manual and no addenda are issued to clarify the discrepancies, the more expensive or greater quantity option(s) shall be included in the work.
4. Contractor to make every effort to coordinate or schedule activities to minimize areas of disruption occurring at any one time. Contractor shall coordinate interruption of any services affecting the adjoining areas with the Owner.
5. It shall be the responsibility of the Contractor(s) to coordinate their work with other Contractor(s) working on the project and for sharing shop drawings and installation instruction. Any labor and material required in order to make a system operable and/or required for proper installation shall be made at no additional cost regardless if specified or not.
6. General Contractor shall provide necessary concealed blocking for support as required for complete installation at no additional cost.
7. Contractor(s) are to verify depth/height of any items installed and make appropriate adjustments for a complete installation.
8. Any damage to site and or buildings caused as a result of the construction process shall be repaired and/or made new by the Contractor causing the damage as determined by the Architect/Owner.
9. Where a fire rated or sound rated partition/wall is called for, all voids between the partition and adjoining surface shall be sealed accordingly with rated barrier materials by the Contractor installing the partition (or in existing partitions) as approved by the Architect/Owner.
10. Any item passing through a fire rated or sound rated partition shall be sealed accordingly with rated barrier materials by the Contractor installing the item.
11. Where patching is called for, the finish shall match existing adjacent. If no new finish is scheduled or if finish cannot match existing, the Contractor shall install new finishes to closest logical point (i.e.
corner, joint, column, etc.) To blend with existing at no additional cost.
12. Where a partition/wall or item is removed that contains active piping, ductwork, wiring, and/or controls necessary for adjacent items which are to remain functioning, the Contractor for that trade shall relocate those items at no additional cost.
13. Contractor to provide adequate protection of all existing finishes/building elements to remain during entire construction period.
14. Owner supplied equipment to be ADA compliant.
15. Owner to submit product data to the contractor for all Owner supplied equipment prior to the submittal of associated shop drawings for coordination purposes.
16. All exterior dimensions shall be noted to the exterior face of stud or masonry. All interior dimensions shall be noted to the interior face of finish. Any and all dimensional discrepancies shall be brought to the Architect's attention, in writing as soon as discrepancy is known.
GENERAL NOTES:
1/8" = 1'-0"1 Life Safety Plan - Basement 0' 4' 8'2' 16'
N
1/8" = 1'-0"2 Life Safety Plan - First Floor
Occupancy Schedule - Basement
Occupancy Number Name Area
Occupant Load
Factor Occupants
014 Data 151 SF
151 SF 0
Business 003 Lacquer & UV Spray Room 958 SF 150 SF 7
Business 006 UV Curing & Filling 324 SF 150 SF 3
Business 008 Storage 149 SF 150 SF 1
Business 009 Office 127 SF 150 SF 1
Business 010 Trad. Filling & Oil Finish 474 SF 150 SF 4
Business 004 Audio Lab 159 SF 150 SF 2
Business 005 Finish Sanding 374 SF 150 SF 3
Business 011 Buffing 344 SF 150 SF 3
Business 012 Plastics 570 SF 150 SF 4
Business 004A Sound Booth 1 103 SF 150 SF 1
Business 013 Maintenance Office 272 SF 150 SF 2
Business 004B Sound Booth 2 103 SF 150 SF 1
Business 012A Sink 47 SF 150 SF 1
Business 108 Room 25 SF 150 SF 1
4029 SF 34
CIRCULATION 0-A Corridor 330 SF 0 SF
CIRCULATION 0-B Corridor 347 SF 0 SF
CIRCULATION 0-C Corr. 437 SF 0 SF
1115 SF 0
Storage 007 Storage 179 SF 300 SF 1
Storage 001 Storage/Inventory 399 SF 300 SF 2
Storage 002 Storage/Inventory 223 SF 300 SF 1
801 SF 4
6096 SF 38
Occupancy Schedule - First Floor
Occupancy Number Name Area
Occupant Load
Factor Occupants
Business 105 Student Workshop 1436 SF 150 SF 10
Business 106 Guitar Tech Lab 963 SF 150 SF 7
Business 103 Main Luthier Assembly 538 SF 150 SF 4
Business 104 Guitar Repair & Setup 209 SF 150 SF 2
Business 101 Reception 356 SF 150 SF 3
Business 100 Entrance 132 SF 150 SF 1
3634 SF 27
CIRCULATION 1-A Corridor 564 SF 0 SF
564 SF 0
Storage 102 Student Workshop Storage 213 SF 300 SF 1
213 SF 1
4412 SF 28
R E
F
5' - 0"
Provide ICRA system to temporarily partition off areas of construction
Provide secure door at temporary entrance to classroom suite; coordinate lockset with Owner
Provide emergency egress doors in ICRA system
Provide ICRA system to temporarily partition off areas of construction
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :1
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
G003
Temporary Partition and Egress Locations
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
1/8" = 1'-0"1 First Floor Temporary Partition Plan 0' 4' 8'2' 16'
N
No scope of work in hatched areas
4 5
4 5
4 5
4 5
4 5
4 5 4 5 4 5 4 5 4 5
4 54 5
4 5
4 5
4 5 4 5
5 5
4 5
4 5
1 16
Window sill height above plan cut
Window sill height above plan cut
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :1
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
AD100
Basement Demolition Plan
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
0' 4' 8'2' 16'
N
1/8" = 1'-0"1 Basement Demolition Plan
GENERAL DEMOLITION NOTES:
A. - The demolition work indicated is intended to assist the Contractor and give general information. It is recommended that the Contractor visit the Project site prior to bidding to fully acquaint themselves with the extent of all demolition work, which is necessary to complete the alterations and new construction as described in the Contract Documents. All demolition work required shall be included in the contract price. The Contractor will not be entitled to any claims for additional compensation related to required demolition.
B. - The Contractor shall verify all conditions and dimensions with the contract scope of work and notify the Architect immediately in writing of any deviation from Contract Documents necessitated by field conditions or items not covered.
C. - Dashed lines on the demolition plans represent walls, doors, soffits, casework, equipment, etc. to be removed. Patch and repair existing adjoining areas to remain.
D. - Demolition item number indicates general area but does not show every occurrence.
E. - Demolition work shall be performed in a safe and acceptable manner to authorities having jurisdiction and the Owner.
F. - Prior to demolition, Contractor shall review above ceiling conditions and areas below construction to confirm building components and equipment that are required to be preserved. Contractor shall notify Architect immediately of any such instances.
G. - Prior to demolition of any existing construction the Contractor must verify that it is not supporting construction to remain. Notify the Architect before demolition if an item is questionable. The Contractor shall provide all temporary shoring, scaffolding, etc. Which are necessary to prevent deflection, subsidence, collapse, or any other type of damage.
H. - Prior to demolition, Contractor shall review all items to be demolished with Owner to identify which items are to be salvaged and remain as Owner's property or temporarily stored for reuse and/or reinstallation.
I. - All trades shall be responsible for all cutting associated with the work done under their trade.
J. - All trades shall be responsible for patching adjacent surfaces & existing walls after demolition to match existing/receive new finishes & equipment. Patching shall match adjacent work in finish, structural qualities, coursing 0f masonry, and other characteristics. Patched surfaces to comply with fire and smoke resistant partition/barrier ratings, acoustical ratings, and other performance criteria.
K. - All masonry infill to be "toothed" into existing masonry assemblies where being exposed after construction.
L. Existing materials scheduled to remain may be temporarily removed if necessary for new work, but must be reinstalled in their previous locations in equal or better condition.
M. - Contractor shall schedule the construction activities in order maintain the security of the building throughout the construction.
N. - The Contractor shall maintain a safe means of egress during demolition work and provide temporary separation of work areas from other occupied areas of the building including dust partitions, walk-off mats, temporary filters, etc.. Fire alarm and smoke detection system to remain operational at all time. Protect smoke detectors as required and in conformance with codes and local authorities having jurisdiction.
O. - Contractor to provide temporary partitions/dust protection which maintains the existing ratings. Proposed locations to be reviewed with Owner and Architect prior to start of work.
Demolition Notes - Basement
Number Note
1 Remove existing wall in its entirety. Patch and prepare adjacent surfaces for new work.
2 Remove existing door in its entirety, including door frame and associated hardware. Prior to demolition, confirm intent to salvage or discard with Owner.
3 Salvage existing door, frame, sidelight, and all associated hardware for reuse in new work.
4 Remove existing floor and wall base finish. Patch, level, and prepare floor substrate to receive new finish.
5 Remove existing ceiling, all associated hangers or fasteners, and existing light fixtures. Ref 'E' dwgs.
6 Remove any existing suspended acoustical ceiling panels, decorative suspended wood ceiling elements, and existing light fixtures. Ref 'E' dwgs.
7 Salvage (2) existing suspended wood ceilings and integrated lighting for reuse in new work.
8 Remove and dispose of existing spray booth.
9 Remove existing casework and plumbing fixture. Patch and prepare adjacent surfaces for new work.
10 Salvage existing casework and plumbing fixture for reuse in new work. Relocate plumbing lines for new work. Ref 'P' dwgs.
11 Remove existing casework. Patch and prepare adjacent surfaces for new work.
12 Salvage existing display case components and return to Owner.
13 Salvage existing refrigerator and return to Owner.
14 Salvage existing casework and return to Owner.
15 Relocate existing custom desk. Coord. location with owner.
16 Remove existing vision panel in its entirety. Patch and prepare adjacent surfaces for new work.
17 Remove remaining portion of wall below demolished vision panel to create new framed opening.
18 Remove existing areas of water-damaged drywall.
19 Remove existing window in its entirety. Patch and prepare adjacent surfaces for new work.
20 Remove existing soffit in it's entirety, patch and prepare adjacent surfaces to receive new work/finishes
21 Remove and salvage existing vision panel to create opening for temporary door; reinstall vision panel prior to substantial completion.
R E
F
No scope of work in hatched areas
4 5
Extent of floor finish demolition work (Demo note 4)
Extent of floor finish demolition work (Demo note 4)
8' - 0"
Extent of floor finish demolition work (Demo note 4)
Extent of ceiling demolition work (Demo note 5)
Extent of ceiling demolition work (Demo note 5)
See 'M' demo dwgs
See 'M' demo dwgs
Extent of ceiling demolition work (Demo note 6)
See 'M' demo dwgs
See 'M' demo dwgs
See 'M' demo dwgs
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :1
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
AD101
First Floor Demolition Plan
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
1/8" = 1'-0"1 First Floor Demolition Plan 0' 4' 8'2' 16'
N
Demolition Notes - First Floor
Number Note
1 Remove existing wall in its entirety. Patch and prepare adjacent surfaces for new work.
2 Remove existing door in its entirety, including door frame and associated hardware. Prior to demolition, confirm intent to salvage or discard with Owner.
3 Salvage existing door, frame, sidelight, and all associated hardware for reuse in new work.
4 Remove existing floor and wall base finish. Patch, level, and prepare floor substrate to receive new finish.
5 Remove existing ceiling, all associated hangers or fasteners, and existing light fixtures. Ref 'E' dwgs.
6 Remove any existing suspended acoustical ceiling panels, decorative suspended wood ceiling elements, and existing light fixtures. Ref 'E' dwgs.
7 Salvage (2) existing suspended wood ceilings and integrated lighting for reuse in new work.
8 Remove and dispose of existing spray booth.
9 Remove existing casework and plumbing fixture. Patch and prepare adjacent surfaces for new work.
10 Salvage existing casework and plumbing fixture for reuse in new work. Relocate plumbing lines for new work. Ref 'P' dwgs.
11 Remove existing casework. Patch and prepare adjacent surfaces for new work.
12 Salvage existing display case components and return to Owner.
13 Salvage existing refrigerator and return to Owner.
14 Salvage existing casework and return to Owner.
15 Relocate existing custom desk. Coord. location with owner.
16 Remove existing vision panel in its entirety. Patch and prepare adjacent surfaces for new work.
17 Remove remaining portion of wall below demolished vision panel to create new framed opening.
18 Remove existing areas of water-damaged drywall.
19 Remove existing window in its entirety. Patch and prepare adjacent surfaces for new work.
20 Remove existing soffit in it's entirety, patch and prepare adjacent surfaces to receive new work/finishes
21 Remove and salvage existing vision panel to create opening for temporary door; reinstall vision panel prior to substantial completion.
958 SF
Lacquer & UV
Spray Room
179 SF
Storage
149 SF
Storage
127 SF
Office
474 SF
Trad. Filling & Oil
Finish
374 SF
Finish Sanding
344 SF
Buffing
570 SF
Plastics
103 SF
Sound Booth 1 004A
399 SF
Storage/Inventory
223 SF
Storage/Inventory
272 SF
Maintenance
Office
No scope of work in hatched areas
159 SF
Audio Lab
103 SF
Sound Booth 2 004B
47 SF
Sink 012A
Utility sink w/ integrated eyewash, see 'P' dwgs
330 SF
Corridor 0-A
347 SF
Corridor 0-B
21' - 0"
O P
E N
IN
G
/2
3' - 10" 21' - 0 1/4"
324 SF
UV Curing &
Filling
E001.2
E012
E004.4
E004.1
E001.3
E003.1
E003.3
E003.4
E004.5
E006
E007.2
E011E005
E .1
E -A
E -B
E
E
E
E .1
E .2
E .3
9' - 0"
New fence enclosure on public walkway, to match existing
2 2
151 SF
Data
2' - 0"
Utility sink w/ integrated eyewash, see 'P' dwgs
Install new drywall and paint after removal of existing water-damaged GWB. Prior to refinishing, investigate extent of water infiltration to determine if further remediation is required.
Install new drywall and paint after removal of existing water-damaged GWB. Prior to refinishing, investigate extent of water infiltration to determine if further remediation is required.
See 'M' dwgs
See 'M' dwgs
See 'M' dwgs
See 'M' dwgs
See 'M' dwgs
Patch and paint existing walls after removal of existing abandoned piping.
Existing fire extinguisher
Existing fire extinguisher
Existing fire extinguisher
Existing exterior columns
Line of Finish Floor
Extend of underside of roof/floor deck above
Fiberglass acoustical batt insulation
5/8" GWB, both sides
3-5/8" Metal stud @ 16" O.C.
3-5/8" Metal channel
Wall base, see finish schedule
Finish ceiling, see RCP
Wall finish, see finish schedule
PARTITION TYPE
1" = 1'- 0"
Acoustical sealant, both sides
Deflection track
Partition Notes:
1. All partitions are type 1 unless otherwise noted.
All walls and partitions required to be fire separation assemblies, smoke partitions, or constructed to resist the passage of smoke, shall be sealed at all voids at decks and all annular spaces shall be sealed with approved material for rated application.
2. Provide double 20 ga studs at door openings.
3. Provide diagonal bracing at 6'-0" o.c. min. at all mtl. stud partitions stopping below structure.
4. Partition types do not indicate finish, see finish schedule for finishes.
5. All gwb surfaces within 6'-0" of all lavatory, sink, water closet, shower, mop rack, whirlpool, tub, or other water source shall receive usg sheetrock mold tough ar firecode x (or approved equal). all wet locations shall be painted with epoxy paint from floor to ceiling
6. Provide control joints in the gypsum board where any of the conditions below exist:
A. Where a partition, wall, or ceiling traverses a construction joint (expansion, seismic or building control element) in the base building structure.
B. Where a wall or partition runs in an uninterrupted straight plane exceeding 30 linear feet.
C. In ceilings with perimeter relief, control joints shall be installed so that linear dimensions between control joints do not exceed 50 ft and total area between control joints does not exceed 2500 sq ft.
D. In ceilings without perimeter relief, control joints shall be installed so that linear dimensions between control joints do not exceed 30 ft and total area between control joints does not exceed 900 sq ft.
E. Where ceiling framing members change direction.
F. Where specified by the architect.
NOTE: Where a control joint occurs in an acoustical or fire-rated system, blocking shall be provided behind the control joint by using a backing material such as 5/8" type x gypsum board, mineral fiber, or other tested equivalent.
4 7/8"
Line of Finish Floor
Extend to underside of roof/floor deck above
7/8" horizontal Metal Hat Channels @ 24" O.C., on two-piece Noiseproofing Clips (Basis of Design by Green Glue). Clip spacing per instructions by Green Glue.
(2) Layers of 5/8" GWB
Wall base, see finish schedule
Finish ceiling, see RCP
Noiseproofing sealant (Basis of Design:
Green Glue Sealant)
Noiseproofing Compound (Basis of Design: Green Glue Compound), 2 tubes per GWB sheet
Noiseproofing sealant (Basis of Design: Green Glue Sealant)
Simpson STC Roof Truss Deflection Clip @ Ea. truss at non-bearing walls
PARTITION TYPE
1" = 1'- 0"
Existing wall assembly
Line of Finish Floor
Extend of underside of roof/floor deck above
Fiberglass acoustical batt insulation
(1) layer 5/8" GWB, interior side
3A: 3-5/8" Metal stud @ 16" O.C.
3B: 6" Metal stud @ 16" O.C.
3A: 3-5/8" Metal channel
3B: 6" Metal channel
Wall base, see finish schedule
Finish ceiling, see RCP
Wall finish, see finish schedule
3A
PARTITION TYPE
1" = 1'- 0"
3A: 6 1/2"
3B
PARTITION TYPE
1" = 1'- 0"
3B: 8 7/8"
(2) layers 5/8" GWB, exterior side
Deflection track
NOT IN SCOPE
BASEMENT
PROJECT SCOPE
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :2
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
A100A
Basement New Work Plan, Partition Types
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
0' 4' 8'2' 16'
N
1/8" = 1'-0"1 Basement New Work Plan
1436 SF
Student
Workshop
213 SF
Student
Workshop
Storage
963 SF
Guitar Tech Lab
538 SF
Main Luthier
Assembly
209 SF
Guitar Repair &
Setup
No scope of work in hatched areas
New framed opening, provide a flat aluminum jamb
356 SF
Reception
132 SF
Entrance
Display cabinet
Relocated existing casework & sink
/8
/8
14' - 1" 9' - 11" 10' - 5"
ALIGN
3A Relocated existing door and sidelight
5' - 6 1/2" 16' - 1 1/2" 5' - 2 1/2"
/4
3' - 6" 3' - 2 7/8"
17' - 2 15/16"
7' - 11 1/2"
16' - 2 5/8"
3B
3A
3A
3A
3A
3A3A
3A
3A
Existing door to be relocated
.2
E .1
E107
E .2
VP-01
VP-02
VP-03
VP-01
A101A2
2 2
A101A 3
VP-01
E105.1
See 'M' dwgs
A350
A350
A350
A350
A350
A101A4
A101A
6' - 6 7/8" 8' - 0"
HG
SEE SCHEDULE
S E
E S
C H
E D
U L E
6"
6"
1/4"
TEMPERED
GLASS*
FG
SEE SCHEDULE
S E
E S
C H
E D
U L E
6"
6"
1/4"
TEMPERED
GLASS
S E
E S
C H
E D
U L E
SEE SCHEDULE
8' - 0"
1/4" TEMPERED GLASS
6' - 0"
1/4" TEMPERED GLASS
8' - 0"8' - 0"
1/4" TEMPERED GLASS
3' - 0" 3' - 0" 1' - 6" 1 1/2" OVERHANG
/2
/2
Existing relocated upper cabinet
Existing relocated sink and apron
Existing relocated lower cabinets
SS-1
*All casework components salvaged and relocated from existing location except where noted. See demolition plans.
Existing window
FILLER 3' - 0" 3' - 0" 3' - 0" 2' - 11" FILLER
*All casework components by Owner, installed by GC.
Butcher block countertop, by Owner
(1) existing 35" flammables cabinet, by Owner
(3) existing 36" base cabinets, by Owner
VP-01
5' - 0 1/2"
2"
A101A
5' - 0 1/2"
2"
A101A
Opp
3/4" plywood with laminate finish
5' - 0 1/2"
Display case light fixture, see 'E' drawings
1/4" thick laminated glass with flush mount cabinet pivot hinges and lock
1/2" reveal, painted black
Finished Floor
Gyp. wall board
20 GA. 3 5/8" metal studs at 16" on center
2"
Gyp. wall board
Finished Ceiling
Scheduled base
NOT IN SCOPE
FIRST FLOOR
PROJECT SCOPE
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :2
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
A101A
First Floor New Work Plan, Door Schedule, & Interior Elevations
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
1/8" = 1'-0"1 First Floor New Work Plan 0' 4' 8'2' 16'
N
Frame Types:Door Types:
Door Schedule
Door Number
DOOR FRAME
Hardware - Power / Panic Fire Rating CommentsType Width Height Thickness Material Finish
Frame Type
Frame Material Finish
E001.1 ETR 3' - 0" 7' - 0" 1 3/4" ETR ETR ETR ETR Painted ETR
E001.2 ETR 3' - 0" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E001.3 ETR 3' - 0" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted Storeroom Card Access Read to match existing buildings system
E003.1 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E003.3 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E003.4 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E004.1 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted Classroom
E004.2 ETR 3' - 0" 7' - 0" 1 3/4" ETR ETR ETR ETR Painted ETR
E004.3 ETR 3' - 0" 7' - 0" 1 3/4" ETR ETR ETR ETR Painted ETR
E004.4 ETR 3' - 0" 7' - 0" 1 3/4" ETR ETR ETR ETR Painted Classroom
E004.5 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted Classroom
E005 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E006 ETR 3' - 0" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E007.1 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted Storeroom
E007.2 ETR 3' - 0" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E008 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted Storeroom
E009 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E010 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E011 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted ETR
E012 ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted Classroom Card Access Read to match existing buildings system
E-A ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted Panic Card Access Read to match existing buildings system
E-B ETR 3' - 6" 7' - 0" 1 3/4" ETR Painted ETR ETR Painted Panic Card Access Read to match existing buildings system
100 FG 6' - 0" 7' - 9 1/2" 1 3/4" ALUM Clear 1 ALUM Clear Classroom Card Access Read to match existing buildings system, door and frame to be acoustically rated
105.2 HG 3' - 0" 7' - 0" 1 3/4" ALUM Clear 1 ALUM Clear Classroom Card Access Read to match existing buildings system, door and frame to be acoustically rated
E105.1 ETR 6' - 0" 7' - 9 1/2" 1 3/4" ETR ETR ETR ETR ETR ETR Relocate existing double door and sidelite.
E106.1 ETR 3' - 0" 7' - 9 1/2" 1 3/4" ETR ETR ETR ETR ETR Classroom Relocate existing door and sidelite; Card Access Read to match existing buildings system
E106.2 ETR 3' - 0" 7' - 0" 1 3/4" ETR ETR ETR ETR Painted ETR
E107 ETR 3' - 0" 7' - 9 1/2" 1 3/4" ETR ETR ETR ETR ETR ETR
Vision Panel Types:
1/4" = 1'-0"2 Student Workshop - Elev. 1
1/4" = 1'-0"3 Student Workshop - Elev. 2
1/4" = 1'-0"4 Display Cab. - Elev. 1
1/4" = 1'-0"5 Display Cab. - Elev. 2 1/2" = 1'-0"6 Casework Section - Display Cabinet
Existing GWB-wrapped column
5/8" GWB, both sides
3 5/8" mtl studs @ 16" o.c.
Door jamb, ref.
door schedule
ALIGN ALIGN
Existing GWB-wrapped column
5/8" GWB
3 5/8" mtl studs @ 16" o.c.
ALIGN
1" resilient channel @ 24" o.c.
(2) layers 5/8"
GWB
3/4" plywd. w/ laminate finish
5/8" GWB
3 5/8" mtl studs @ 16" o.c.
(2) layers 5/8"
GWB
1" resilient channel @ 24" o.c.
3/4" plywd. w/ laminate finish
Existing GWB-wrapped column
5/8" GWB
3 5/8" mtl studs @ 16" o.c.
(2) layers 5/8"
GWB
1" resilient channel @ 24" o.c.5/8" GWB
3 5/8" mtl studs @ 16" o.c.
Door jamb, ref.
door schedule
ALIGN
Existing GWB-wrapped column
5/8" GWB
3 5/8" mtl studs @ 16" o.c.
(2) layers 5/8"
GWB
1" resilient channel @ 24" o.c.
Door jamb, ref.
door schedule
5/8" GWB
3 5/8" mtl studs @ 16" o.c.
6" mtl studs @ 16" o.c.
110.00°
70.0 0°
ALIGN
Return GWB to door jamb, both sides, typ.
(2) layers 5/8"
GWB
1" resilient channel @ 24" o.c.
5/8" GWB
6" mtl studs @ 16" o.c.
Existing wall assembly
Existing storefront, new partition to be constructed clear of the existing storefront
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :2
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
A350
Plan & Section Details
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
1 1/2" = 1'-0"1 Detail - Partitions to Column @ Guitar Tech Lab 1 1/2" = 1'-0"2 Detail - Partitions to Column @ Corridor Display Case
1 1/2" = 1'-0"3 Detail - Partitions to Column @ Entrance
1 1/2" = 1'-0"4 Detail - Partitions to Column @ Reception 1 1/2" = 1'-0"5 Detail - Partition to Storefront @ Reception
CEILING NOTES
TYPE 1
TYPE 2
TYPE 3
24"x24" Armstrong 'Ultima Beveled Tegular' #1911, lay in ceiling tile with 15/16" grid
Gypsum Wall Board, Painted.
See Finish Schedule
TYPE 4 Exposed structure, cleaned and painted by Contractor.
See Finish Schedule
CEILING LEGEND
GYPSUM WALL BOARD,
PAINTED, SEE FINISH
SCHEDULE
SUSPENDED ACOUSTICAL
CEILING TILE (ACT)
24"x48 LIGHT FIXTURE, SEE 'E' DRAWINGS
RECESSED LIGHT FIXTURE,
SEE 'E' DRAWINGS
PENDANT LIGHT FIXTURE,
SEE 'E' DRAWINGS
24"x24" LIGHT FIXTURE, SEE 'E' DRAWINGS
PENDANT LINEAR LIGHT
FIXTURE, SEE 'E' DRAWINGS
PENDANT LIGHT FIXTURE,
SEE 'E' DRAWINGS
Existing reinstalled suspended wood ceiling system
ACP ceiling, See ceiling plan for height
2 1/2" Metal framing with 5/8" gypsum wall board on exposed side, paint finish on gypsum wall board
5/8" gypsum wall board (painted), extend gypsum to underside of structure where ACP does not attach to soffit
M
IN6
9' - 0"
9' - 0"
9' - 0"
9' - 0"2
9' - 0"
9' - 0"
9' - 0"
9' - 0"
9' - 0"
9' - 0"
Lacquer & UV
Spray Room
UV Curing &
Filling
Storage
Storage 008 Office
Trad. Filling & Oil
Finish
Audio Lab
Finish Sanding
Buffing
Plastics
Sound Booth 1 004A
Storage/Inventory
Storage/Inventory
Sound Booth 2 004B
Sink 012A
Corridor 0-A
Corridor 0-B
9' - 0"
9' - 0"
9' - 0"
No scope of work in hatched areas
Type 4
Type 4
Type 4
Type 4
Spray booth below
Spray booth below
9' - 0"
A400
9' - 0"
Guitar Tech Lab
Student
Workshop
Student
Workshop
Storage
Main Luthier
Assembly
Guitar Repair &
Setup
Type 4
Type 4
Type 4
Type 4
Reception
Entrance
No scope of work in hatched areas
Type 4
Type 4
9' - 6"
9' - 6"
9' - 6"
9' - 0"
10' - 0"
10' - 0"
A400 3
A400
A400
Outline of desk below, task lighting fixture location to be coordinated w/ desk locations
NOT IN SCOPE
BASEMENT
PROJECT SCOPE
NOT IN SCOPE
FIRST FLOOR
PROJECT SCOPE
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :2
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
A400
Basement & First Floor RCPs
Northampton Community College
Fowler Luthier Expansion
M K
S D
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
1 1/2" = 1'-0"3 Ceiling Detail
0' 4' 8'2' 16'
N
1/8" = 1'-0"1 Basement RCP 1/8" = 1'-0"2 First Floor RCP
LINE LEGEND
ACCENT PAINT
WALL GRAPHIC
FLOOR FINISH
DIRECTION
1436 SF
Student
Workshop
213 SF
Student
Workshop
Storage
963 SF
Guitar Tech Lab
538 SF
Main Luthier
Assembly
209 SF
Guitar Repair &
Setup
No finish scope of work in hatched areas
356 SF
Reception
132 SF
Entrance
564 SF
Corridor 1-A
Floor Legend
EPX-1
ETR
LVT-1
SC
PT-4
PT-2
WG-1
WG-1
PT-5
WG-1
WG-1958 SF
Lacquer & UV
Spray Room
179 SF
Storage
149 SF
Storage
127 SF
Office
474 SF
Trad. Filling & Oil
Finish
374 SF
Finish Sanding
344 SF
Buffing
570 SF
Plastics
103 SF
Sound Booth 1 004A
399 SF
Storage/Inventory
223 SF
Storage/Inventory
272 SF
Maintenance
Office
No finish scope of work in hatched areas
159 SF
Audio Lab
103 SF
Sound Booth 2 004B
47 SF
Sink 012A
330 SF
Corridor 0-A
347 SF
Corridor 0-B
324 SF
UV Curing &
Filling
WG-1
PT-3
ROOM FINISH SCHEDULE LEGEND
F L
O O
R
IN
G
W A
L L
S
C A
S E
W O
R
KLUXURY VINYL TILE (LVT)
LVT-1 Manufacturer: Mohawk Group Product: Secoya 5.0 C2104 Size: 10" x 59" Color: 148 Knotty Oak Installation: Ashlar
CARPET (CPT)
CPT-1 Attic Stock by Owner, installed by GC
WALL BASE (WB)
WB-1 Manufacturer: Roppe
Product: Pinnacle Standard Toe Size: 4" Color: 150 Dark Gray
PAINT (PT)
PT-1 Manufacturer: Benjamin Moore
Color: Baby's Breath 873 (Field)
PT-2 Manufacturer: Sherwin Williams Color: To be selected by the Architect (Accent)
PT-3 Manufacturer: Sherwin Williams Color: To be selected by the Architect (Accent)
PT-4 Manufacturer: Sherwin Williams Color: To be selected by the Architect (Accent)
PT-5 Manufacturer: Sherwin Williams Color: To be selected by the Architect (Accent)
PT-6 Manufacturer: Sherwin Williams Color: To be selected by the Architect (Metal Doors/Frames)
PT-7 Manufacturer: Sherwin Williams Color: High Reflective White 7757 (Ceilings/Soffits)
PT-8 Manufacturer: Sherwin Williams Color: Iron Ore SW 7069 (Exposed ceilings/Structure)
WALL GRAPHIC (WG)
WG-1 To be selected by the Architect
1. GENERAL CONSTRUCTION SCOPE OF WORK INCLUDES ALL DEMOLITION, SUBSTRATE REMOVAL/ RE-CONSTRUCTION, PREPARATION/ PATCH WORK ON EXISTING SURFACES
THAT ARE SCHEDULED TO RECEIVE NEW FINISHES PER MANUFACTURER'S RECOMMENDATIONS.
2. INTERIOR FINISH REQUIREMENTS SHALL MEET APPLICABLE CODES AS OUTLINED IN THE CODE INFORMATION ON THE CODE SHEET.
3. PROVIDE FULL RANGE OF COLORS FOR FINISH SELECTIONS. TYPICAL FOR ALL SELECTIONS.
4. UNLESS NOTED OTHERWISE PAINT MISCELLANEOUS ITEMS INCLUDING, BUT NOT LIMITED TO THE FOLLOWING; ACCESS DOORS/ PANELS, ELECTRICAL PANELS IN THE FINISHED
AREAS, EXPOSED STEEL STRUCTURE/ PIPING, DOOR FRAMES, & SIDELIGHTS. DO NOT PAINT OVER U.L. LABELS, EQUIPMENT INFO, CODE REQUIRED INFORMATION, ETC.
5. ALL EXPOSED CEILINGS TO BE PAINTED.
6. NORTH IN FINISH SCHEDULE MATCHES NORTH IN PLANS.
7. PROVIDE ADA COMPLIANT THRESHOLDS AND TRANSITIONS AT FLOORING MATERIAL CHANGES AS REQUIRED.
8. ACCENT PAINTS NOTED ON FINISH PLAN.
9. GC TO INSTALL OWNER PROVIDED EQUIPMENT & COORDINATE FINAL LOCATIONS WITH OWNER'S IT CONTRACTOR. EQUIPMENT TO INCLUDE, BUT NOT LIMITED TO THE
FOLLOWING: WALL MOUNTED TV'S, COMPUTER MONITORS, AND ALL REQUIRED BRACKETS AND HARDWARE FOR A COMPLETE INSTALLATION.
10. FLOORING FINISH MATERIAL SHALL COVER FLOOR SURFACE OF ENTIRE SPACE, INCLUDING UNDER CASEWORK.
11. ALL FINISH INSTALLATION PATTERNS ON FINISH PLANS ARE FOR GRAPHIC REPRESENTATION ONLY.
12. ALL SPACES WITH EXPOSED CEILINGS TO HAVE PROPOSED FINISHES UP TO UNDERSIDE OF STRUCTURE.
GENERAL FINISH NOTES
SC Sealed concrete
EPOXY CONCRETE (EPX)
EPX-1 Manufacturer: Stonhard
Product: Stonshield HRI Color: To be Selected by Architect Wall Base: 4" Integral
ETR Existing to remain
M
IS
C
SOLID SURFACE (PL)
SS-1 Manufacturer: Corian
Color: Deep Cloud (Student Workshop Casework)
NOT IN SCOPE
BASEMENT
PROJECT SCOPE
NOT IN SCOPE
FIRST FLOOR
PROJECT SCOPE
Floor Finish 1
Location of floor finish change to align beneath door
Floor Finish 2
Transition Notes:
1. At locations where two similar materials (i.e. carpet to carpet or resilient to resilient) with different material thicknesses exist, floor shall be flashed to allow for smooth transition.
2. All transitions at doors shall be centered beneath the door.
3. All transitions to be ADA compliant.
Carpet/LVT to Concrete Transition
2-1/2" rubber transition strip
CPT/LVT
Concrete floor
2 1/2"
Concrete floor
D R
A W
N B
Y
Project Number
Drawing Number c
M
K S
D L L C
MKSD, LLC
1209 Hausman Road Suite A Allentown, PA 18104
610.366.2081 mksdarchitects.com
Silvia A. Hoffman, AIA Todd O. Chambers, AIA Jill P. Hewes, AIA Jessica E. Klocek, AIA a r c h i t e c t s
Project
Client
Project Team
Date
Drawing Title
Revisions
MEP Engineer HB Engineers 2900 Hamilton Blvd #200 Allentown, PA 18103 Project Contact: Thom Hoffman P: 610-395-0101 E: thoffman@hbengineers.com
/2
/2
:0 :2
P
M C
U s e rs
\l s c \D o c u m e n ts
\2
.1
N
C C
F o w le r
L u th ie r
E x p a n s io n
R
C E
N T
R A
L ls c P
E H
S .r v t
A701
Finish Plans & Schedules
Northampton Community College
Fowler Luthier Expansion
A u th o r
04/30/2026
26.103
511 E. Third St.
Bethlehem, PA 18015
04/30/2026 - BID / PERMIT
SET
1/8" = 1'-0"2 First Floor Finish Plan 1/8" = 1'-0"1 Basement Finish Plan
Finish Schedule - Basement
Room Number Room Name Floor Finish
Base Finish Wall Finish Cabinets Countertops Other
0-A Corridor ETR ETR PT-1, PT-3, WG-1
0-B Corridor ETR ETR PT-1
001 Storage/Inventory ETR ETR PT-1
002 Storage/Inventory ETR ETR PT-1
003 Lacquer & UV Spray Room EPX-1 Integral PT-1
004 Audio Lab SC WB-1 PT-1
004A Sound Booth 1 CPT-1 WB-1 PT-1
004B Sound Booth 2 CPT-1 WB-1 PT-1
005 Finish Sanding EPX-1 Integral PT-1
006 UV Curing & Filling EPX-1 Integral PT-1
007 Storage SC WB-1 PT-1
008 Storage SC WB-1 PT-1
009 Office CPT-1 WB-1 PT-1
010 Trad. Filling & Oil Finish EPX-1 Integral PT-1
011 Buffing EPX-1 Integral PT-1
012 Plastics SC WB-01 PT-1
012A Sink SC WB-01 PT-1
013 Maintenance Office ETR ETR ETR
Finish Schedule - First Floor
Room Number Room Name Floor Finish
Base Finish Wall Finish Cabinets Countertops Other
1-A Corridor ETR WB-1 ETR, PT-1 Only new walls receive PT-1;
all other walls ETR.
100 Entrance ETR WB-1 ETR, PT-1 Only new walls receive PT-1;
all other walls ETR.
101 Reception ETR WB-1 ETR, PT-1 Only new walls receive PT-1;
all other walls ETR.
102 Student Workshop Storage SC WB-1 PT-1
103 Main Luthier Assembly…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .