QA's_19AQMM19R0314.xlsx
XLSX spreadsheet 26 KB Posted
- Attached to
- Rapel Tower Murcielago Federal contract opportunity
- Solicitation number
- 19AQMM19R0314
About this file
Solicitation Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 19AQMM19R0314_A002.pdf | ||
| 19AQMM19R0314.pptx | PPTX presentation | |
| Site_Visit_Sign_in_Sheet_(07AUG2019).pdf | ||
| J-1-2_RT_STRUCTURAL_Revised_S-12.pdf | ||
| J-1-4_RT_ARCHITECTONIC.pdf | ||
| 19AQMM19R0314_A001.pdf | ||
| 19AQMM19R0314_Sections_B-M.pdf | ||
| 19AQMM19R0314.pdf | ||
| J-1-2_RT_STRUCTURAL.pdf | ||
| J-2-1_Bidding_Chart.xlsx | XLSX spreadsheet | |
| J-3-1_Past_Performance_Questionaire_(PPQ).docx | DOCX document | |
| J-3-3_Firm_&_Project_Info.docx | DOCX document | |
| J-3-2_Past_Performance_&_References.xlsx | XLSX spreadsheet | |
| J-1-3_RT_MECANICO.pdf | ||
| J-1-1_TECHNICAL_SPECIFICATIONS.pdf | ||
| J-1-5_RTR_ELECTRICAL.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A's
| Murcielago Rappel Tower Solicitation # 19-AQMM-19-R-0314 Q&A's | |||
| # | Reference | Question | Response |
| 1 | We were unable to make yesterday’s site visit – is it possible to request another visit date? Or would you allow us to coordinate a quick directly with someone from the Academy? | FAR 15.201(f) states: After release of the soliciation, the contracting officer must be the focal point of any exchange with potential offers. In order to prevent an unfair competitive advantage only one site visit will be held for this requirement. | |
| 2 | 2. Given that the site is in a very remote location, is it possible to rent barrack space from the Academy for our workforce? | No it is not posible to rent an area at the Police Academy, contractor has to take care of his workinng crew renting some space out of the academy or installing a provisional construction camp in the plot beside the site of construction. | |
| 3 | 3. Will we be given a laydown area on Academy grounds and near the jobsite? | Yes the area beside the projects site can be used by the contractor, but it is needed to clarify at at the end of the project the contractor shall return the area as it was before its use. | |
| 4 | Please provide the window and doors details, including information such as materials, accessories to be installed and dimensions to consider. | Please refer to specifications section C16.2 and drawings T-A-07, T-A-08 and T-A-09. | |
| 5 | Related with the DBA, on previous solicitations there was a fixed amount to be considered on this item, please clarify if in this project there is a fixed amount to calculate this insurance. | Please use a $10,000 fixed amount for CLIN 0002 DBA when preparing proposals. This amount will be adjusted up/down after award as necessary. This is covered in Slide 10 of the powerpoint presentation. | |
| 6 | Please provide the construction detail for the project’s stairs. | Please use the corrected drawing S-12. | |
| 7 | In the meeting for this solicitation it was indicated that the floor below had to of a soft(shock absorbend) rubber material, that probably had to be imported. |
Do you have any specification on this material?
| That is not correct. The anchoars for the climbing wall detailed in drawing T-A-11 will require to buy with anticipation because is not a commun material for construction, so mabe it will need to import some materials from overseas. | ||
| 8 | when is the proposal due on this solicitation? I can not find it anywhere. | Block 13 of the SF1442 indicates proposals are due by 10 AM Local Time (Eastern Standard Time) on September 10, 2019. |