This statement of work outlines technical requirements for a drilling effort in San Diego, California. The selected vendor will drill up to seventeen boreholes of up to forty-two inches in diameter and eighty feet deep, establish concrete bulkheads, and pour concrete of various strengths. Optional tasks may include installing power over ethernet cameras. The vendor must coordinate with various parties and be responsible for equipment, spoils management, safety, and site restoration. Deliverables include a schedule of values, safety plan, progress reports, and as-built documents. The work will occur within one mile of the Otay Mesa Port of Entry as directed by the United States Border Patrol. The period of performance will be discussed at award. The solicitation was issued by the Department of Homeland Security Customs and Border Protection on behalf of the Border Patrol Program Management Office.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 16 Attachment 5 Performance Bond.pdf | ||
| 16 Attachment 3 Contractor Release Form.doc | DOC document | |
| 16 Attachment 2 Wage Determination.pdf | ||
| 16 Attachment 6 Past Experience Form.docx | DOCX document | |
| 16 Attachment 4 Payment Bond.pdf | ||
| 16 6973GH-22-R-00190.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Homeland Security (DHS)
U.S. Customs and Border Protection (CBP)
Statement of Work
For Otay Mesa Borehole Drilling & Technical Services
U.S. Border Patrol
Program Management Office Directorate
(PMOD) Date: June 24, 2022 v.4 ii
Table of Contents
1.0 BACKGROUND
2.0 SCOPE
2.1.1 Base Effort
2.1.1.1 Technical Design and Pre-project Planning
2.1.1.2 Borehole Drilling
2.1.1.3 Bulkhead Construction
2.1.1.4 Concrete Installation
2.1.2 Optional Tasks
2.1.2.1 Optional Task 1: Additional Borehole Drilling
2.1.2.2 Optional Task 2: Additional Borehole Drilling
2.1.2.3 Optional Task 3: Camera and Video Capture Support
2.1.2.4 Optional Task 4: Additional Borehole Drilling
2.1.2.5 Optional Task 5: Change Management Contingency
2.0.1 Mobilization and Demobilization
2.0.2 Surface Marking of Underground Utilities
2.0.3 Spoils
3.0 Applicable Documents
4.0 Specific Tasks
4.1 General Requirements
4.2 Delivery and Inspection Instructions
5.0 Deliverables and Delivery Schedule
5.1 Deliverable Submittals
5.2 Types of Deliverables
6.0 Government Furnished Equipment and Property
7.0 Place of Performance
8.0 Period of Performance
9.0 Security
10.0 Hours of Operation
11.0 General Information
12.0 Questions or Concerns
13.0 Travel
1.0 BACKGROUND
The United States Border Patrol (USBP) requires technical design, engineering, geophysical and geotechnical services to provide the design, planning, management, and execution of all critical tasks required to provide up to seventeen (17) boreholes of up to forty-two (42”) in diameter up to eighty (80’) feet deep. Additionally, the vendor will be required to establish bulkheads to control the flow of concrete and pour concrete of various compressive strengths. Optional tasks that may be required include installation of Power over Ethernet (PoE) cameras.
The completion of the work will also require the rental and operation of several different types of light and heavy equipment that may not be specifically called out in the SOW but should be planned for during the technical design and pre-project planning phase of this effort. Executing the work safely and efficiently will begin with close coordination with CBP/local USBP representatives, property managers, utility locators, DigAlert, concrete/asphalt contractors, drillers, heavy equipment providers and operators, and rental equipment providers. The vendor will be responsible for all aspects of executing the SOW outlined below, including (but not limited to): scheduling deliveries and pickups of equipment, spoils management, vertical and horizontal safety barriers, traffic control, site security, site restoration, final inspection of the completed sites and providing as-built and geotechnical reports. The work will be completed at specific locations as directed by USBP personnel within the Roosevelt easement and within a 1 mile of the Otay Mesa Commercial Port of Entry.
2.0 SCOPE
2.1 Otay Mesa, CA
2.1.1 Base Effort
2.1.1.1 Technical Design and Pre-project Planning
Due to the overall complexity of the project, the contractor will need to execute technical research and design activities in addition to the coordination of multiple suppliers, vendors, and subcontractors (See below) prior to field work taking place. The contractor shall plan for these activities in order to ensure efficient execution of the remainder of the scope once on-site activities begin.
2.1.1.2 Borehole Drilling
The Contractor shall drill four (4) lined boreholes of forty-two inch (42”) diameter up to a depth of eighty feet (80’). Before drilling the boreholes it will be necessary to excavate the borehole locations to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment. There may be unforeseen construction debris below grade (i.e., metal landing mat and/or concrete). This may require concrete/asphalt cutting and restoration to the original condition. The borehole will be lined with government furnished thirty-six inch (36”) diameter corrugated pipe, or other approved material. The corrugated pipe will require welding and will be secured at the surface so as to render the casing self-supporting above the bottom of the borehole. At the conclusion of each work day, the contractor shall secure the worksite with trench plates and bolts if relevant (traffic-rated). At the end of each day, spoils will be positioned as to not hinder any private egress for relevant/impacted businesses. If it is deemed necessary by the government representative and/or local USBP representative, the contractor shall be prepared to provide physical security of the site at all times.
At the conclusion of the work, the corrugated pipe will be removed and retained by the government for future projects, the borehole will be backfilled with the soils reserved from the original drilling (water and/or soil compaction may be necessary), and the surface shall be returned to the original condition. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report.
2.1.1.3 Concrete Installation and Bulkhead Construction
The contractor shall work closely with a local USBP representative and government representative to design and establish a concrete bulkhead using high compressive strength concrete (3000 psi at 28 days). This material will be similar to the concrete used in 2.1.1.4 but the mix/water content may need to be adjusted in order to control the flow of the concrete in the borehole.
The contractor shall pour up to 50 cubic yards of relatively high compressive strength concrete in the work site either at or in a borehole. The concrete will be a custom mix as specified by the government representative and local USBP representative. For the purposes of estimating cost, the contractor shall assume 3000 psi at 28 days although the final specification may vary. Based upon the viscosity (flowability) of the specified concrete formulation, the contractor shall determine the correct method to deliver the concrete to the entire work site. To the extent possible, the delivery method shall be designed so as to entirely fill the work site leaving no voids in the concrete.
Additionally, the contractor shall pour up to 490 cubic yards of relatively low compressive strength concrete in the work site which will be accessible through a second borehole. The concrete will be a custom mix designed for maximum compressive strength while maintaining low viscosity (high flowability). For the purposes of estimating cost, the contractor shall assume 300-350 psi at 28 days although the final specification may vary. Based upon the viscosity (flowability) of the specified concrete formulation, the contractor shall determine the correct method to deliver the concrete to the entire work site. To the extent possible, the delivery method shall be designed so as to entirely fill the work site leaving no voids in the concrete.
2.1.2 Optional Tasks
2.1.2.1 Optional Task 1: Additional Borehole Drilling
The Contractor shall drill three (3) either thirty six inch (36”) or forty-two inch (42”) diameter up to a depth of eighty feet (80’). Before drilling the borehole it will be necessary to excavate the borehole locations to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment. This may require concrete/asphalt cutting and restoration. At the conclusion of the work, the borehole will be backfilled with the spoils reserved from the original drilling (water and/or soil compaction may be necessary) and the surface shall be returned to the original condition. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report.
2.1.2.2 Optional Task 2: Additional Borehole Drilling
The Contractor shall drill three (3) either thirty six inch (36”) or forty-two inch (42”) diameter up to a depth of eighty feet (80’). Before drilling the borehole it will be necessary to excavate the borehole locations to a depth of approximately six (6’) feet to mitigate the potential presence of both surface and underground obstructions that could be damaged or cause damage to the drilling equipment. This may require concrete/asphalt cutting and restoration. At the conclusion of the work, the borehole will be backfilled with the spoils reserved from the original drilling (water and/or soil compaction may be necessary) and the surface shall be returned to the original condition. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report.
2.1.2.3 Optional Task 3: Camera and Video Capture Support
The Contractor shall support the government representative and local USBP representative with the placement of government furnished Power over Ethernet (PoE) wired camera system.
2.1.2.4 Optional Task 4: Additional Borehole Drilling
The Contractor shall drill two (2) technology boreholes to a depth of eighty (80’) feet at specific locations as indicated by USBP/CBP representative. Each technology borehole will be completed by drilling an up to thirty-six (36’) inch diameter precision borehole (given the geology conditions, use the smallest diameter borehole feasible/practical that can accommodate a six (6”) casing), lowering a government-furnished six (6”) inch schedule 40 PVC well casing (glued bell end style) into the borehole with a temporary surface termination at or slightly above the finish grade. The bottom of the casing shall be open/uncapped. At surface termination, the borehole casing shall be temporarily capped to prevent soil intrusion during back fill procedure. The annulus between the casing and the borehole shall be filled with native material which have been sieved to remove any material larger than three (3”) inches. Water may be necessary to reduce voids and promote even settling of the soil. The deviation of the installed technology boreholes shall be confirmed by inclinometer measurements performed by the Contractor and shall not deviate more than 5% from vertical. The method of computing deviation from vertical shall be to divide the closure distance by the measured depth at 1/10th foot depth intervals. The deviation data will be presented in Bull’s Eye plots, Closure plots and in an Excel file. The positions of any/all boreholes will be recorded with sub-centimeter accuracy GPS and this information will be provided as part of the as-built report. At the conclusion of the project, the contractor shall remove as much of the casing as possible and abandon in place the remaining PVC casing. The borehole will then be backfilled with the spoils reserved from the original drilling (water and/or soil compaction may be necessary) and the surface shall be returned to the original condition.
Description of Boreholes
Count PVC Casing
Gov Provided
Precision Drilled (max 5%)
Terminated 12” above grade
Plastic Access Cap
Up to 36” diameter x 80’ with 6” diameter casing
2 Yes Yes Yes Yes No
2.1.2.5 Optional Task 5: Change Management Contingency
Due to the highly unpredictable nature of this work, the Contractor shall establish a change management contingency of up to 10% of the total project costs. This will allow the Contractor to be agile and quickly adapt to urgent needs of the project as needs arise or priorities change. Use of the change management contingency funds will be at the written direction of the CO.
2.0.1 Mobilization and Demobilization
The Contractor shall assume one mobilization and demobilization to support the entire Scope of Work, regardless of equipment type. Mobilization costs shall be included in the base task 2.1.1.1 Technical Design and Pre-project Planning.
2.0.2 Surface Marking of Underground Utilities
Surface marking of any underground utilities must be in place prior to the start of work.
2.0.3 Spoils
All spoils shall be graded within the work area and not removed. Water and/or soil compaction will be required as part of the backfill procedure. If additional spoils remain, they will be transported to the easement and spread accordingly.
3.0 Applicable Documents
3.1 This Statement of Work
4.0 Specific Tasks
The Contractor, in completing these tasks, shall follow the requirements of this SOW, and where not specifically defined, comply with government regulations and industry standards.
4.1 General Requirements
4.1.1 General Information
4.1.1.1 No utilities will be provided by the Government.
4.1.1.2 The Contractor’s material/product selection, installation means and methods shall only be completed by qualified personnel.
4.1.1.3 Damage to property owned by others and caused by the Contractor shall be repaired by the Contractor and shall be returned to its original condition.
4.1.2 Contractor shall:
4.1.2.1 Follow all Federal, State, and Local codes during the completion of this project. Refer to Section
3.0 Applicable Documents.
4.1.2.2 Survey areas with the Contracting Officer’s Representative (COR) or authorized Facility Point of Contact (POC) to verify final location of all work prior to work commencing.
4.1.2.3 Protect and safeguard the site from all damage. Any corrective action to repair damaged areas shall be the responsibility of the Contractor.
4.1.2.4 Provide all temporary sanitary facilities, such as, hand wash and portable toilets.
4.1.2.5 Provide environmental protection measures as necessary to prevent polluting discharges of any type, or to be a source of nuisance or interference to operations or other Government personnel in the proximity of the work.
4.1.2.6 Be fully responsible for securing and payment of any necessary State or local permit or other form of approval documentation. In the event that no such permit or documentation is required, the Contractor shall attest to that fact in writing.
4.1.2.7 Workers shall be aware of, and consent to, either being under constant physical escort or video surveillance by closed circuit cameras at all times.
4.1.2.8 Be responsible for all temporary services and/or other accommodations, as well as, all direct and indirect management effort and expenses required to execute this project.
4.1.2.9 Obtain prior approval from the COR/POC and local USBP representative prior to commencing with any on-site work.
4.1.2.10 Provide trucks for proper disposal of all construction debris and spoils. Truck waiting locations on site shall be coordinated with the COR/POC prior to arriving on site.
Contractor shall be responsible for the proper disposal of waste/debris associated with this project.
4.1.2.11 Be responsible to secure its equipment and materials stored on site.
4.2 Delivery and Inspection Instructions
4.2.1 The Government:
4.2.1.1 Reserves the right to refuse equipment not meeting the aforementioned requirements
4.2.2 The Contractor shall:
4.2.2.1 Be responsible for the delivery, offloading and mobilization of all equipment to be used for this project.
4.2.2.2 Be responsible for conducting a physical check of the equipment, jointly with the COR/POC, to determine that all mechanical and safety inspections have been performed on each piece of equipment and proof of those inspections are up to date.
4.2.2.3 Document all discrepancies and shall be responsible for either repair or replacement of any equipment that does not have, or cannot prove, up-to-date safety and mechanical inspections.
5.0 Deliverables and Delivery ScheduleThe following table outlines the deliverables the Contractor shall submit for review and approval.
Item Number Deliverable Title Deliver To Format Frequency
SOW
Referemce
3 Schedule of Values (SOV) COR & USBP
POC
Electronic Via Email
Within five (5) calendar days after issuance of the design NTP
5.2.3
4 Safety, Health and Accident Prevention Plan (Submitted for Informational Purposes Only)
COR & USBP
POC
Electronic Via Email
Within five (5) calendar days after issuance of the design NTP
5.2.4
7 Progress /Daily Reports COR & USBP
POC
Electronic Via Email
Weekly by 4 PM (Local Time) every Friday during performance
5.3.1
8 Post Construction Submittals
COR & USBP
POC
Electronic Via Email
When construction is completed
5.4
5.1 Deliverable Submittals
All submittals shall be provided through a Material Approval Submittal (or Contractor format) process and submitted to the Contracting Officer’s Representative (COR) in a Portable Document Format (PDF) file format. Unless noted otherwise, all deliverables shall be in electronic format and provided no less than fifteen (15) calendar days prior to the proposed drilling.
5.1.1 Additional Deliverable Requirements
5.1.1.1 Submittal information shall relate specifically to the requirements, and components required for the work and activities described in Section 4 of this SOW for the project. If the contract provides for the submission of shop drawings, samples, lists and descriptive data for approval, it is important that these be transmitted as early as possible in order to allow time for review and approval. In order to expedite the review for approval, the Contractor shall ensure that the submittals are clearly marked to properly identify the specific items proposed.
5.1.1.2 General statements relating to the methods of work to be completed and material manufacturer’s generic or booklet type information will be returned without review.
5.1.1.3 The Contractor shall allow the Government seven (7) calendar days (after receipt of submittal information) for review and action relative to submittals.
5.1.1.4 Submittal information returned to the Contractor shall be corrected and resubmitted to the Government within five (5) calendar days of Contractor receipt of returned submittal.
5.1.1.5 Failure, on the part of the Contractor, to provide acceptable submittal information within the time frames defined herein shall not be cause for a contract time extension.
5.2 Types of Deliverables
5.2.1 Schedule of Values (SOV)
The Contractor shall submit within five (5) calendar days after NTP issuance the SOV that will provide sufficient breakdown of all unit costs related to individual tasks listed in this SOW. This SOV shall be submitted with each payment request.
5.2.2 Safety, Health and Accident Prevention Plan
The Contractor shall prepare and submit a Task Specific Accident Prevention Plan and Task Specific Safety Plan. This plan shall be submitted within five (5) calendar days after NTP issuance. This plan shall be provided for information only.
5.2.3 Progress Reports/Daily Reports
The Contractor shall prepare reports and shall transmit the reports to the COR/POC and local USBP government via email by 4:00 pm (Local Time) each Friday, or prior to the weekly progress meeting if one is held.
5.2.4 Post – Construction Submittals
5.2.4.1 Contractor shall provide one (1) set of as-built drawings per affected property in hard copy format and one complete (1) set in electronic (PDF) format to the COR/POE. Each drill hole shall be labeled on a scale map showing the GPS coordinates, known depth.
5.2.4.2 The Contractor shall provide one electronic PDF copy of all the following that apply, but not limited to: waste/debris disposal documents associated with the tasks of this SOW within fifteen
(15) calendar days after construction is complete.
5.2.4.3 All post-construction submittals shall be provided to the Contractor and approved by the Government before final Government acceptance of completion of the tasks in this SOW.
Electronic copies must be delivered on CD or DVD; USB Flash Drive (Thumb Drive) is not acceptable.
6.0 Government Furnished Equipment and Property
• The Government will provide afore mentioned construction materials, such as corrugated pipe and Schedule 40 six (60”) inch bell PVC, as well as the PoE Camera System.
7.0 Place of Performance
Otay Mesa, CA
8.0 Period of Performance
Schedule and mobilization expectations will be discussed at time of award.
9.0 Security
9.1 Security Requirements
The work to be performed under this SOW is categorized as unclassified. The Contractor shall be responsible for its employees following all the laws of the United States or other governing bodies affecting operations at all sites. This shall include regulations imposed by the CBP.
9.1.1 Security – Work Clearance
9.1.1.1 All Contractor personnel shall be subject to the security provisions and requirements of the facility. Work on the site may incur time constraints associated with security compliance activities, i.e., personnel and vehicle inspections, etc. The Contractor shall ensure that security compliance activities are properly factored into the work schedule and cost proposals. The Contractor shall coordinate with security officials at the facility regarding all applicable security/safety requirements.
9.1.1.2 All personnel entering in or working on federal property will be screened and checked for criminal history and proper immigration status. Personnel who do not meet the minimum standards will not be allowed on the job site.
9.1.1.3 If an individual does not clear vetting, the Government cannot disclose (for privacy reasons) the specific results of the vetting process.
9.1.1.4 The Contractor shall submit the following information to the applicable CBP Sector/Station Security Manager for each employee (including subcontractor personnel) having access to the site, no less than ten (10) working days prior to work start:
• Individual's full name
• Date of birth (DOB)
• Place of birth (POB)
• Driver's Licenses Number and State
• SSN, Passport Number, or Alien Registration Number
• On a case-by-case basis, the Contractor may be asked to furnish photocopies of the driver license or state identification card and the social security number or alien registration number in order to help verify and/or resolve conflicting information resulting from the security screening process.
9.1.1.5 Should any Contractor employee, Subcontractor employee, or any other person working on behalf of the Contractor (through further investigation) be found unfit to work on a CBP site, that person shall be removed from the site and barred from returning to the project site.
9.1.1.6 Contractor shall provide the required information showing proof of personnel security screening within ten (10) calendar days of receiving the notice of contract award. The personnel information shall be included in a protected Word attachment to an email. A separate email with the password for the Word document shall be sent after the initial email.
9.1.1.7 The Contractor shall submit all required information for access and security clearances required by CBP.
9.2 Physical Security
The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for Contractor use. At the close of each workday, Government facilities, equipment, and materials under Contractor control shall be secured.
10.0 Hours of Operation
This site is accessible at all times between 7:00 am to 5:00 pm (Pacific Time), Monday thru Friday. Any work performed outside these hours will require at least five (5) business days advance notification and approval. The Contractor will not be required to work on the weekends or Federal Holidays, but may do so with approval from the Contracting Officer. Up to fifty percent (50%) of this scope will be performed outside of normal business hours (5:00 pm to 8:00 pm). If this is the case, a government representative and local USBP representative will coordinate with the contractor at time of award or as the need arises.
11.0 General Information
11.1 Safety and Environmental
• The Contractor shall conduct work and maintain the work site in such a manner as to not be the cause of any adverse environmental issues to the surrounding environment, CBP, or personnel in or around the immediate area.
• The Contractor shall comply with all OSHA requirements. The Contractor shall provide a Site Safety and Health Officer (SSHO) and be on-site at all times when work is being performed.
• The Contractor shall be required to wear personal protective equipment (PPE) such as hard hats, safety glasses, reflective vests, safety shoes and long pants within the work perimeter at all times. All equipment operators shall be licensed and/or certified to operate equipment and have all the necessary safety training.
• All Contractor accidents, involving injuries or property damage that occur during the performance of this contract shall be reported to the COR within four (4) hours of the Contractor being aware of the occurrence. COR will notify local USBP of all incidents or accidents as they occur.
11.2 Other/Meetings
• Other - In the event that the necessary materials or methods of installation are not defined by direction or documents provided for this project, the Contractor shall utilize industry standards for any such material or installation method.
• Meetings – The Contractor shall be required to attend the following meetings.
o The Contractor shall attend a job walk-through prior to commencement of any activities.
This meeting will consist of a one-half (1/2 day) meeting at the project site. The designated Contractor Project Superintendent/ Manager, as well as key Subcontractors and trades, are required to attend this meeting.
o Prior to project completion, the Contractor shall conduct a preliminary punch list walk-through on the works and forward the punch list to the COR/POC for review (pre-final inspection) o The Contractor shall conduct a final punch list walk-thru at the completion of the project (final inspection). The final walk-thru shall be attended by the Contractor’s key personnel, site staff, and the COR, Government POC, and local USBP representative.
11.3 Points of Contact
Notwithstanding the Contractor’s responsibility for management during performance, the administration of this contract will require coordination between CBP, USBP and the Contractor.
The Contracting Officer (CO) will appoint the COR to assure orderly performance of the tasks and provide technical direction. The COR/POC is:
12.0 Questions or Concerns
All technical questions and concerns shall be directed to the COR/POC. All contractual questions shall be directed to the CO/Contract Specialist.
The types of actions within the purview of the COR/POC authority:
• Assure that the Contractor performs the technical requirements of the contract
• Assure that the Contractor perform inspections necessary in connection with performance of the contract
• Maintain both written and oral communications with the Contractor concerning the aspects of the contract within his/her purview
• Issue interpretations of technical requirements
• Monitor the Contractor’s performance under the contract and notify the Contractor and CO of any deficiencies observed
• Coordinate Government-Furnished Property or Data availability and provide for site entry of Contractor personnel (if required)
The COR/POC is not empowered to make any commitments or changes which affect the contract price, delivery or other items and conditions. Any such proposed changes shall be brought to the immediate attention of the CO for action. The acceptance of any changes by the Contractor without specific approval and written consent of the CO shall be at the Contractor’s risk.
13.0 Travel
All travel performed for this effort will be in accordance with Federal Travel Regulations (FTR) and will be reimbursed at actual cost. All travel must be approved by the Contracting Officer (CO) prior to performance.
| 1.0 BACKGROUND |
| 2.0 SCOPE |
| 2.1.1 Base Effort |
| 2.1.1.1 Technical Design and Pre-project Planning |
| 2.1.1.2 Borehole Drilling |
| 2.1.1.3 Concrete Installation and Bulkhead Construction |
| 2.1.2 Optional Tasks |
| 2.1.2.1 Optional Task 1: Additional Borehole Drilling |
| 2.1.2.2 Optional Task 2: Additional Borehole Drilling |
| 2.1.2.3 Optional Task 3: Camera and Video Capture Support |
| 2.1.2.4 Optional Task 4: Additional Borehole Drilling |
| 2.1.2.5 Optional Task 5: Change Management Contingency |
| 2.0.1 Mobilization and Demobilization |
| 2.0.2 Surface Marking of Underground Utilities |
| 2.0.3 Spoils |
| 3.0 Applicable Documents |
| 4.0 Specific Tasks |
| 4.1 General Requirements |
| 4.1.2 Contractor shall: |
| 4.2 Delivery and Inspection Instructions |
| 4.2.2 The Contractor shall: |
| 5.0 Deliverables and Delivery ScheduleThe following table outlines the deliverables the Contractor shall submit for review and approval. |
| 5.1 Deliverable Submittals |
| 5.1.1 Additional Deliverable Requirements |
| 5.2 Types of Deliverables |
| 5.2.2 Safety, Health and Accident Prevention Plan |
| 5.2.3 Progress Reports/Daily Reports |
| 5.2.4 Post – Construction Submittals |
| 6.0 Government Furnished Equipment and Property |
| 7.0 Place of Performance |
| 8.0 Period of Performance |
| 9.0 Security |
| 9.1.1 Security – Work Clearance |
| 9.2 Physical Security |
| 10.0 Hours of Operation |
| 11.0 General Information |
| 11.2 Other/Meetings |
| 11.3 Points of Contact |
| 12.0 Questions or Concerns |