U.S. Department of Justice
Federal Bureau of Prisons Administrative Division
Field Acquisition Office Grand Prairie, Texas 75051
May 8, 2019
ATTN: ALL BIDDERS
RE: Clarification Set Number One
Solicitation 15B50219B00000001 FCC Beaumont, Texas Repair Storm Hurricane Electrical
Dear Bidders, In reference to the above solicitation, enclosed are clarifications. These clarifications are for informational purposes only.
If you have any questions, feel free to contact me at (972) 352-4641 or e-mail at dpatton@bop.gov
Sincerely, Douglas V. Patton Contracting Officer Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, Texas 75051
Enclosure cc: File
SCS, FCC Beaumont COR, FCC Beaumont Facility Manager, FCC Beaumont Regional Facilities Administrator, SCRO
CLARIFICATION SET NUMBER ONE
SOLICITATION NUMBER 15B50219B00000001
REPAIR STORM HURRICANE ELECTRICAL
FCC BEAUMONT, TEXAS
Question # 1. Type of cable copper or aluminum. We know it's copper I would like to confirm for bidding purposes. Copper #2 (SEE AMENDMENT ONE)
Question # 2. Type of shielding on the Wire? (Reference SOW-DESCRIPTION OF WORK, page 7) The shielding is 15kw rated insulation on conductors. Clarification
Question # 3. The specifications don't mention power outage or Contractor to provide temporary power which will definitely have to happen during this project, it will require multiple generators from us is that acceptable? Yes, the contractor to provide multiple generators if needed.
(SEE AMENDMENT ONE)
Question # 4. Power will have to be disconnected multiple times, in order to connect the generators, for a MAXIMUM of two hours. Contractor will work with the institution to schedule appropriate times for that to happen is that acceptable? (Reference SOW-CONTRACTOR RESPONSIBILITIES) page 6, item #5). Yes, it is acceptable and mandatory for contractors to work with the institution when power needs to be shut off. Clarification
Question # 5. Can you provide us with the electrical one line diagram? We required this in order to know which Transformer and which Sectionalizer box Supply which MDP (main distribution panel). Yes (SEE AMENDMENT ONE)
Question # 6. Can we have the load analysis of each MDP and its sub-panels marked with loads that CANNOT be disconnected due to security? One load is feed with 250 kva 13,200v – 480v transformer. The other load is feed with a 500kva 13,200v – 480v transformer (SEE
AMENDMENT ONE)
Question # 7. Are you able to provide drawings of the new Galvanized Metal stands that will be built by the institution? No, drawings will not be provided. The stands will be boxed in at the bottom with one side left open for installation purposes. Clarification
Question # 8. Is the contractor responsible to mount the metal stands on the existing pads or will that be done by the institution? (Reference SOW-DESCRIPTION OF WORK, page 7, last paragraph) Metal stands will be furnished and installed by the institution. Clarification
Question # 9. Would it be possible to add an additional 90 days for completion of the project?
(180 days) No. Not possible to add any time to completion of project. See additional information at question #18 below. Clarification
Question # 10. Would you allow the multiple temporary generators to be set on top of the roof?
We would take full responsibility for any roof damage, and required Crane to load and off load.
No, temporary generators are to be set on the ground. Clarification
Question #11. Will temporary power be supplied by the contractor while the new circuits are ran?
Yes, the contractor must supply temporary power to the institution while the new circuits are being ran. In addition, FCC Beaumont will need the contractor to submit a proposed schedule/timeline of how temporary power will be utilized and time frames involved before full power is ultimately restored. (SEE AMENDMENT ONE)
Question #12. How far is the Remote Utility Building from the Unicor Building? The Remote Utility Building is approximately 400 to 500 feet from the Unicor Building. (SEE
AMENDMENT ONE)
Question #13. Will a tool inventory be conducted in the morning upon contractor’s arrival to the job site and in the evening upon contractor’s departure from the job site? Yes, tool inventory will be conducted in the morning prior to the contractor beginning work and in the afternoon after the contractor has concluded work for the day. (Reference SOW-STORAGE OF MATERIALS, TOOLS AND EQUIPMENT, page 2). Clarification
Question #14. Will the contractor be able to deliver required materials thru the rear gate utilizing some type of motorized vehicle, such as a truck or forklift? Yes, the contractor will be able to deliver required materials thru the rear gate utilizing some type of motorized vehicle, such as a truck or forklift. Vehicles are subject to security searches conducted by BOP personnel in accordance with security requirements and BOP policy. (Reference SOW-SUMMARY, page 1, third paragraph). Clarification
Question # 15. Do we replace transformer? Transformers are not being replaced or purchased by the contractor. One of the transformers on-site will be exchanged with an identical one (provided by FCC Beaumont) during the raising process. (SEE
AMENDMENT ONE)
Question # 16. Conduit size was not specified. Does that means we are only replacing wire from point to point? (Reference SOW-CONTRACTOR RESPONSIBILITIES, page 6, item #3).
Contractor will determine conduit sizing per NEC Code. Clarification
Question #17. Provide photos inside of the existing pad-mounted switchgear of the connections as well as the conduits. YES (SEE AMENDMENT ONE)
Question #18. We feel 90 does not provide an adequate amount of days to complete the project.
From our past experience, it can take up to 90 days for clearance paperwork to be fully processed.
We feel the project requires 120-150 days to complete. See page 11 of the solicitation at clause FAO-0009 Contract Security, The FCC Beaumont anticipates 7 calendar days for security clearances, therefore, 90 calendars has been determined sufficient for the performance period. Clarification
END OF CLARIFICATIONS
| CLAR SET ONE COVER |
| CLARIFICATION SET NUMBER ONE |
| 2019-05-08T13:57:42-0500 | |
| DOUGLAS PATTON |