Contractor Solicitation Questions.docx
DOCX document 13 KB Posted
- Attached to
- REPLACE AUTOMATIC TRANSFER SWITCH CONTROLS
- Solicitation number
- 15B30221Q00000019
About this file
This solicitation is seeking proposals to replace the automatic transfer switch controls at the Federal Correctional Complex in Coleman, Florida. The work includes acquiring and installing a programmable logic controller-based automatic transfer switch. Proposals are due by noon on May 3, 2021 and must be submitted via email to the points of contact listed. The contract will be a firm fixed-price awarded to the lowest price technically acceptable offer. The North American Industry Classification code is 335313 and it is set aside for small businesses with a size standard of $7.5 million. All work must meet the generator manufacturer's approval and training requirements. Components will be procured, tested, and installed in accordance with industry standards and codes. Faith-based and community-based organizations may submit proposals equally with other organizations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| (12a) 3D3T Drawing.pdf | ||
| 9(a) - 15B30221Q00000019_Updated.pdf | ||
| NCIC Form.pdf | ||
| 9 - 15B30221Q00000019.pdf | ||
| 7 - STATEMENT OF WORK.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Questions
1. The awarded contractor is being asked preserve the integrity of the functioning components. What are those components? A drawing or photo of the panel would be easiest way to determine this.
The solicitation was updated on 4/29/21 to include the following statement:
"As to the drawing, there are designations on the switchgear that are not detailed in the notes. The designation of "52" is a reference to the actual breaker that will be controlled and operated by the PLC this breaker is a GE POWER VAC BREAKER / TYPE: VB1 13.8-500 3 / with a 48v DC trip and close coil these are ran on an existing battery bank. All the breakers that are to be controlled are typical and of this type. The other designation is the "R1" this signifies the protective relay that is on each individual breaker. These are a: GE DFP100 / MODEL#DFP14A1M110FB . These are typical as well."
The statement referenced; "preserve the integrity of the functioning components" means not to physically destroy anything as items are being removed. Any components that are removed should remain intact, as well as the component it was attached to. In essence, don't just start cutting, smashing and yanking things to remove them. Care should be taken as to label connections/wires so the reassembly can be made easier for the contractor.