About this file

Summary

This solicitation document is for design services for the Buckman Water Reclamation Facility (WRF) Upgrades issued by Jacksonville Electric Authority (JEA) in Jacksonville, Florida. JEA is soliciting qualifications for professional engineering and permitting services to upgrade significant infrastructure at the Buckman WRF, including rehabilitation of influent pump stations, primary clarifiers, Talleyrand Avenue lift station, vacuum truck unloading facility, potable water and gravity sewer improvements, sludge receiving pump station, and grit removal system improvements. The scope of work encompasses surveys, geotechnical investigations, process and hydraulic modeling, design of bypass systems, permitting activities, site work including stormwater and landscaping design, structural and mechanical design across multiple disciplines, construction phase services, and coordination with a Construction Manager at Risk (CMAR) firm. A mandatory pre-response meeting is scheduled for September 1, 2026, at 11:00 a.m. via Microsoft Teams, followed by a mandatory in-person site visit on September 2, 2026, at 10:00 a.m. at 221 Buckman Street, Jacksonville, Florida 32206. Responses are due by October 6, 2026, at 12:00 p.m. EST via the Zycus Supplier Network platform. JEA intends to award one contract and will evaluate responses using the Consultants' Competitive Negotiation Act (CCNA) methodology based on professional qualifications without considering price initially. Evaluation criteria include professional staff experience (25 points), design approach and workplan (40 points), company experience (30 points), and use of Jacksonville Small and Emerging Business (JSEB) firms (5 points).

Respondents must be registered on JEA's Qualified Proposers List in the Water Wastewater Treatment Plant Systems and Pump Stations category (Class III and IV) to meet minimum qualifications. The contract will be structured as a fixed-fee arrangement negotiated after selection, with the initial year at firm-fixed pricing and subsequent years eligible for Consumer Price Index (CPI) adjustments capped at 3 percent annually. Insurance requirements include workers' compensation, commercial general liability of $1,000,000 per occurrence/$2,000,000 aggregate, automobile liability, professional errors and omissions coverage, and excess/umbrella liability. JEA encourages but does not require the use of JSEB-certified subcontractors; however, respondents not certified as JSEB may earn additional points (up to 4 points) by subcontracting to JSEB firms at varying percentages of work. The contract is contingent upon lawfully appropriated funds and may be renewed at JEA's discretion for two additional one-year periods. All responses remain confidential until the opening date of October 6, 2026, at 2:00 p.m., when they will be publicly announced via Microsoft Teams.

View the file

Other files

File Type Posted
1412211678 Addendum 2 - Additional Site Visit.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation

For Participation in

Design Services for the Buckman WRF Upgrades

JEA

Jacksonville, FL

Solicitation Number 1412211678

Mandatory Pre-Response Meeting via Microsoft Teams on September 01, 2026, at 11:00am

Meeting URL: https://teams.microsoft.com/meet/296581775754705?p=ryMyo7diIAPz6cEk1l

Meeting ID: 296 581 775 754 705

Meeting Passcode: qy6cZ6yR

Dial In: 321-558-7338

Phone conference ID: 549 421 38#

Those planning to attend via Microsoft Teams should send contact information to: mcdomv@jea.com 48 hours prior to the Pre-Response Meeting to have contact information documented.

Mandatory Site Visit – September 02, 2026, at 10:00am

Location: 221 Buckman Street, Jacksonville Fl, 32206

Personal Protective Equipment (PPE) Required: Safety Shoes, Safety Glasses, Safety Vest

Responses are due on October 06, 2026, by 12:00 PM EST

All Responses shall be submitted through JEA’s E-Procurement and Contract Management Portal which is provided by Zycus Supplier Network which can be accessed at https://zsn.zycus.com/guest. Instructions on how to login to

Zycus is provided below in this Solicitation. LATE RESPONSES MAY BE REJECTED.

JEA will publicly open all Responses received from qualified Respondents on the Due Date October 06, 2026, at

2:00pm via Microsoft Teams.

For more information please contact the JEA Buyer at:

Marline McDonald, mcdomv@jea.com, 904-760-6614 https://teams.microsoft.com/meet/296581775754705?p=ryMyo7diIAPz6cEk1l mailto:mcdomv@jea.com https://zsn.zycus.com/guest mailto:mcdomv@jea.com

1.2) Scope of Work

JEA is soliciting qualifications for professional engineering and permitting services for the Buckman Water

Reclamation Facility Upgrades. The Buckman Water Reclamation Facility needs some significant infrastructure upgrades. Below is a list of the various facilities that need to be either rehabilitated or constructed:

• Influent Pump Station Rehabilitation

• Primary Clarifiers 1-8 Structural Rehabilitation

• Talleyrand Ave Lift Station Rehabilitation

• Vacuum Truck Unloading Facility (Dewatering Pad) Upgrade & Expansion

• Potable Water and Gravity Sewer Improvements

• Sludge Receiving Pump Station

• Grit Removal System Improvements

For further information on the work please refer to the Scope of Services for Engineering Design Services for the

Buckman WRF Upgrades.

The scope for the work may include, but is not limited to:

• Surveys

• Geotechnical investigations

• Process modeling and hydraulic modeling

• Design bypass system, drawings and specifications

• Permitting activities and applications for construction

• Site work including stormwater, paving, grading, and landscaping design

• All supporting discipline design including structural, architectural, HVAC, plumbing, fire protection, electrical and I&C

• Services during construction

• Coordination with CMAR firm who will be responsible for constructing the improvements

• Compliance with the JEA project delivery management system including design phase drawings, specifications, and calculations.

Capitalized terms used in this Solicitation without definition shall have the definitions given to them in Section 2 of this Solicitation.

1.3) Background

JEA owns, operates and manages the electric system established by the City of Jacksonville, Florida since 1895. In June

1997, JEA also assumed operation of the water and sewer system previously managed by the city. JEA is located in

Jacksonville, Florida, where we proudly serve an estimated 541,076 electric, 407,161, water and 30,460 reuse water customers. JEA is Florida's largest community owned utility and the eighth largest municipal in the United States.

1.4) Invitation - Submitting a Response

Respondents that meet the Minimum Qualification stated herein are invited to submit a Response to this Solicitation to perform the Work. A complete copy of this Solicitation, the Technical Specifications, forms and all other documents referenced in this Solicitation are on JEA’s E-Procurement and Contract Management Portal which is provided by

Zycus Supplier Network which can be accessed at https://zsn.zycus.com/guest/genericRegister/JEA074. Instructions on how to login to Zycus is provided below in this Solicitation.

All Responses are due at the time indicated on the title page of this Solicitation. Section 1 of this Solicitation are the instructions for submitting a Response for this Solicitation. Section 2 of this Solicitation contain the definitions and commercial contract terms associated with this procurement.

A Contract will be presented to the Respondent awarded this Work and the Contract will incorporate by reference this entire Solicitation and all associated Addenda. A sample of the JEA Contract can be found on jea.com.

https://zsn.zycus.com/guest/genericRegister/JEA074

All documentation submitted with a Response must reference the Solicitation Title and Number stated herein. All

Responses must be made on the appropriate forms and formats as specified by this Solicitation and uploaded to JEA’s procurement platform.

All Responses should be delivered electronically to JEA via the Zycus platform. An automated, detailed auditing system provides sealed Response integrity. Responses remain sealed on the platform until the Close Date & Time

(Due Date & Time).

A Respondent shall be solely responsible for timely delivery of its Response to the Zycus Supplier

Network. Respondents are strongly encouraged to acquire log in credentials early as possible. Additionally

Respondents are encouraged to submit Responses early to ensure uploading process goes smoothly. If Respondent is not able to submit its Response via Zycus, then please email the Response to the JEA Buyer identified in the

Section below titled "Questions".

Responses are due by the time and on the date stated on the cover page of this Solicitation. LATE RESPONSES

MAY BE REJECTED.

1.5) Zycus Instructions

I. How to Log into Zycus

A. New Users – Zycus

1. New Users will need to register to login. Registration will require Company name, address, phone, contact, title, phone and email address. Also, it is recommended users use Google Chrome to access Zycus.

2. Note if the company is already doing business with JEA, you may find the company is already registered in Zycus.

To find out if you are registered, try entering your email address in the New User Registration screen. If you receive a message stating “Email ID already registered”, log in as an Existing User Log-in”. If you don’t know your password, enter your email address and click on “Forgot Password”.

B. Existing Users or New Users with Previously Registered Emails

1. Once the user has a login on the sourcing platform select “Existing User Log-in”, the user may navigate to the solicitation by selecting the icon for the applicable solicitation.

II. How to Submit a Response Using Zycus

1. Once logged in, users will see all JEA Sourcing Events, then select the applicable event.

2. Once in the Sourcing Event. The Sourcing Event has prompts for actions required to respond to the solicitation.

3. For the user to proceed to submit a Response to JEA using Zycus, the user will be required to provide its acceptance of the of the Zycus iSource Terms & Conditions associated with the work. Such Terms and Conditions may cover non-disclosure, safety, cyber security, Invitation for Bid contract terms, etc.

4. Once all terms are accepted, additional Solicitation information will be available for viewing and submitting a

Response by selecting “Confirm Participation”. JEA will then have a record indicating the company intends to submit a Response.

5. A user then can respond to each section of the Solicitation, once completed with each section, select “Save”. Note each section has a red, yellow, and green light code. Items will turn green once completed. Yellow and red lights mean there is additional action required. Users may also note under each tab, there are multiple questions to respond to, scroll down the list to ensure all questions are answered.

6. In most Solicitations, JEA will provide Technical Specifications, pricing tables in Excel which the user will need to download. Additionally, Excel pricing tables may need to be uploaded once completed to as part of the Response.

Users can download the required attachments by selecting the “Buyers Attachments” icon.

7. Once the required forms are uploaded and saved, the section light will turn green. Once all sections are completed and green lighted, the User may select “Submit Response”.

8. Once the user selects “Submit Response”, the user will receive a “Success” pop-up when submitted.

9. Once submitted users may recall and modify submitted documentation and submit information until the Response

Due Date and Time.

10. Zycus does not automatically transfer a pricing submission from the qualifying round into live auction setting for award consideration. Each user shall manually re-submit its qualifying Response into the live auction environment for consideration of award.

1.6) Questions

All Questions must be submitted in writing to the JEA Buyer listed herein at least five business days prior to the opening date. Questions received within five business days prior to the opening date may not be answered.

1.7) Pre-Response Meeting

There will be a mandatory Pre-Response meeting associated with this Solicitation at the date and time listed on the cover page of this Solicitation. All interested Respondents are required to attend the Pre-Response meeting. Those planning to attend the Microsoft Teams teleconference may email their name and contact information to the JEA

Buyer listed herein at least 48 hours prior to the Pre-Response meeting to facilitate roll call. A Respondent must only sign in representing one company, unless otherwise agreed to by JEA in writing.

1.8) Mandatory Site Visit in Person

There will be a mandatory Site Visit. All interested Respondents may be required to sign in at the beginning of the meeting. A Respondent shall only sign in representing one company, unless otherwise specified by JEA. The PPE required for this visit are safety shoes, safety vest and safety glasses.

PLEASE BE AWARE DUE TO JEA SIGN IN AND/OR SECURITY PROCEDURES IT MAY TAKE UP TO

FIFTEEN (15) MINUTES TO OBTAIN ACCESS TO A JEA FACILITY. PLEASE PLAN ACCORDINGLY SO AS

TO ARRIVE TO THE PRE-BID MEETING ON TIME.

➢ Site Visit Meeting Date: September 02, 2026

➢ Site Visit Meeting Time: 10:00am

➢ Site Visit Meeting Location: 221 Buckman Street, Jacksonville Fl, 32206

1.9) Opening of Responses

All Responses received shall be publicly announced and recorded via Microsoft Teams at the date and time indicated on the cover page of this Solicitation.

The details for the Microsoft Teams will be on jea.com at the following website: https://www.jea.com approximately

48 hours before the Response opening.

At the opening of Responses, a JEA representative will publicly open each Response that was received prior to the

Date and Time, except for those Responses that have been properly withdrawn. JEA has the right to waive irregularities or informalities in the Responses to the extent allowable under applicable laws.

1.10) Alternate Provisions and Conditions

Terms and conditions found in Responses that are contrary to requirements found in this Solicitation, including, but not limited to, the Contract terms and conditions contained in Section 2 of this Solicitation and any requirements found in the Technical Specifications attached as an exhibit or attachment to this Solicitation, will be rejected and are of no force and effect. However, JEA reserves the right to negotiate different terms and conditions and requirements if JEA determines that such terms and conditions and requirements are in the best interest of JEA.

1.11) Minimum Qualifications

Respondent must meet the following Minimum Qualifications to be considered eligible to have its Response evaluated by JEA. Respondents that are working or have worked for JEA in the past 2 years involving similar work must submit

JEA as a reference. JEA reserves the right to ask for additional back up documentation or additional reference projects to confirm the Respondent meets the requirements stated below.

JEA may reject Responses from Respondents not meeting all of the following Minimum Qualifications:

I. The Respondent must be on JEA’s Qualified Proposers List (QPL) in the following category: WE1–

Water Wastewater Treatment Plant Systems and Pump Stations (Class III and IV)

➢ Visit https://www.jea.com/About/Procurement/Become_a_Vendor/Qualified_Proposers/ to learn how to become qualified prior to the Response Due Date

Any Respondent whose contract with JEA was terminated for default within the last two years shall have its

Response rejected.

1.12) Number of Contracts to be Awarded

JEA intends to Award one (1) Contract for the Work. JEA reserves the right to Award more than one Contract based on certain groupings of the Work items, or JEA may exclude certain Work items, if JEA determines that it is in its best interest.

1.13) Insurance Requirements

Prior to JEA issuing a Purchase Order to the Company to begin the Work, the Company shall submit a certificate of insurance (COI) that is in compliance with amounts and requirements as indicated in this Solicitation. Note that the

COI shall specifically indicate JEA as additional insured on all required insurance except Worker's Compensation and

Professional Liability (if applicable). Furthermore, waiver of subrogation must be provided for all required insurance in favor of JEA, including its board members, officers, employees, agents, successors, and assigns.

1.14) Optional Use of Small and Emerging Business Program

It is at the Respondent's option as to whether it chooses to subcontract with a JSEB firm. JEA encourages the use of

JSEB firms; however, the Respondent is not required to utilize a JSEB to be awarded a Contract under this

Solicitation.

For more information regarding the JSEB program, please contact Bill Hickey, JEA, Manager of Supplier Diversity

Programs and Procurement Services, hickwj@jea.com or jsebprogram@jea.com.

1.15) Basis of Award - Highest Evaluated

JEA will use the Selection Criteria listed below to evaluate the Responses. JEA may make its Award decision based solely upon the information submitted in the Responses. JEA may also choose to have one or more Respondent make presentations to representatives of JEA. It is always in the best interest of the Respondent to provide informative, concise, well-organized technical and business information relative to the Work, in both the initial submittal of its

Response and in any subsequent submittals.

Please note, JEA may reject Responses that request material changes or take exceptions to JEA commercial terms and conditions.

Responses will be scored and ranked by a committee of evaluators. Each evaluator will individually score the

Responses using the evaluation matrix attached to this Solicitation. Using these scores, each evaluator will rank the

Responses using "1" for the Response receiving the highest number of points from the matrix. Responses with an equal number of points will receive the same numerical ranking. JEA will total the numerical rankings for each

Response and consider the Response with the lowest total to be the most highly qualified Response. Any tie will be https://www.jea.com/About/Procurement/Become_a_Vendor/Qualified_Proposers/ broken using the total of the matrix scores of all evaluators. If a tie persists, the tie will be broken in accordance with the JEA Procurement Operational Procedures.

1.16) Evaluation Methodology for CCNA Engineering Services

JEA shall evaluate the Respondent's qualifications, rank the qualifications from all Respondents, and negotiate a

Contract for the Work in accordance with Florida Statute, Section 287.055, known as the Consultants' Competitive

Negotiation Act ("CCNA").

In evaluating the qualifications, JEA will not consider price, but may consider factors including, but not limited to, the

Respondent's professional personnel, past performance, whether the Respondent is a Jacksonville Small and Emerging

Business (JSEB); recent, current and projected workloads of the Respondent, and volume of work previously awarded to each Respondent by JEA. JEA may also request interviews or presentations from the Responders during its selection. Interviews or presentations, if any, will be evaluated and up to twenty-five (25) points will be added to the

Respondents written Response evaluation score.

After approving the rankings of all the Respondents, JEA will enter into negotiations with the best ranked Respondent.

During negotiations, JEA will consider detailed information regarding the Respondent's hourly rates, and scope of the

Contract.

If JEA and the Company are unable to negotiate a satisfactory Contract, JEA will formally terminate the negotiations with the Respondent and undertake negotiations with the next ranked Respondent. JEA will Award the Contract to the highest-ranking qualified Respondent that successfully completes Contract negotiations with JEA.

1.17) Selection Criteria

The following criteria will be used by JEA to evaluate and rank Responses from Respondents who meet the Minimum

Qualifications specified in this Solicitation.

1.18) Phase 1 Selection Criteria

1.19) Professional Staff Experience

Maximum score for this criterion is: 25 POINTS

A. Team Members

Company shall provide a maximum of six (6) resumes of the professional staff to be assigned to perform the "Work".

The resumes provided shall identify the Overall Project Manager, Design Manager, Instrumentation/Controls EOR, and three (3) other resumes at the discretion of the Company that will be supporting on this project. Company shall identify who will be spending the most billable hours on the design of the upgrades with one of the resumes and designate them the Project Engineer. Company should include a one (1) page explanation for the other roles identified on how they will be supporting the project. Persons whose resumes are submitted on must actually perform the Work unless Company receives prior approval by the JEA Project Manager. If the Company submits a resume of a subcontractor that is employed by a JSEB firm, please note this on the resume.

At a minimum, each resume shall present the Team Member's name, role, years of service with Company, applicable professional registrations, education, and work experience. Resumes shall also identify any specialty or technical process expertise related to potable reuse projects. In demonstrating experience, Proposer must indicate the position

/role the individual had in the specific key project referenced.

B. Organizational Chart

Finally, Respondent shall provide an organizational chart delineating company's personnel responsibilities and functions associated with the Work. If applicable, this chart shall also delineate any responsibilities and functions of subcontractor(s) and/or JSEB firm(s).

Points will be awarded as described on the Evaluation Matrix attached to this Solicitation.

Resumes shall be no more than two (2) pages in length: single sided, and on 8.5" by 11" sized paper. If more than two pages are submitted, only the information contained on the first two pages will be evaluated by JEA. No more than six

(6) resumes will be evaluated.

1.20) Design Approach and Workplan

Maximum score for this criterion is: 40 POINTS

Company should provide the following:

1. Provide an overview of the Company’s technical methodology for delivering this project. Highlight key factors such as innovation, constructability, operational efficiency, and regulatory compliance.

• Design elements and considerations.

• What tools and methodologies have you used for design deliverables with JEA and CMAR in the past?

• Detail Company’s experience with permitting wastewater projects in the state of Florida. Include project types, and outcomes that demonstrate familiarity with diverse regulatory rulings.

2. Describe Company’s approach to working with a Construction Manager at Risk (CMAR). Include specific strategies for:

• Designing to budget

• Identifying and implementing cost savings opportunities.

• Developing and executing startup and commissioning procedures.

• Facilitating value engineering and risk mitigation throughout the design and construction phases.

• Design reviews and receiving feedback on design.

3. Describe Company’s approach to managing scope, schedule, and budget, examples from reference projects of similar size and complexity are encouraged.

• Define how each resume supports the specific needs and scope of this project.

• Provide a high-level milestone schedule that outlines each phase of the design process, along with the following additional key milestones. At each milestone, describe your goals/targets for the progression of design/construction.

o Design o Permitting o Construction (in coordination with CMAR) o Technical/innovation concepts or practices that will benefit the project cost and schedule o Working within an operating plant that has other ongoing construction (MOPO) o Startup and commissioning o Hazard and risk management.

Points will be awarded as shown on the Evaluation Matrix attached to this Solicitation.

Respondents’ response above should be limited to no more than ten (10) pages, 1-sided, single-spaced, on 8.5 x

11 sized paper. Please use your own form for this Section. Responses that are longer than ten (10) pages will not be evaluated after page ten (10). The project schedule may be on 11 x 17 sized paper and is not included in the ten (10) page limit.

1.21) Company Experience

Maximum score for this criterion is: 30 POINTS

Respondents that are working or have worked for JEA in the past 2 years involving similar work must submit JEA as a reference.

Company shall provide the following:

1. A summary of Four (4) similar projects. The examples should be able to demonstrate that Company’s experience and knowledge qualify them to complete the necessary work in a successful manner. Reference projects shall be no more than two (2) pages single sided, and on 8.5" by 11" sized paper. The four reference projects should be completed through the design phase.

• For each similar project list any proposed Team Members and their role on that project. This does not need to be the same role proposed for this RFP.

• Company shall identify if they were a subconsultant to another engineering firm and note their particular role and responsibilities if yes. If Company acted as the prime, identify if any roles or responsibilities were executed by other subconsultants.

• Company shall identify how the referenced project was delivered (CMAR, DBB, DB) and if applicable who the selected contractor was.

• The types of key projects may consist of the following but not limited to wastewater projects or similar projects that demonstrate the team’s capabilities

• Company should describe any working relationship with subcontractors that will be used for this project

• Company should provide detailed information to describe how Company managed the engagements to realize project budgetary goals, timetables and quality control objectives.

• Reference project used must have finished the design stage. Company shall identify the project stage—i.e.

bidding, percent construction completed, construction completed, etc.

• Company shall include the following as applicable:

o Year engineering was completed o Engineering fee o Construction cost

• Company shall include a project reference and contact information (email and phone number) for each project

2. Company is requested to provide information on prior Collaborative Delivery project experiences for similar scale projects in which they have participated in the past five (5) years.

Respondent's response to above should be limited to no more than eight (8) pages, 1-sided, single- spaced, on 8.5 x 11 sized paper. Please use your own form for this Section. Responses that are longer than eight (8) pages will not be evaluated after page eight (8).

1.22) Use of Jacksonville Small and Emerging Business (JSEB) Program Business

Maximum Score: 5 Points

Respondent shall indicate (Yes or No) whether the Respondent is certified as a Jacksonville Small and Emerging

Business Program (a “JSEB”) as defined by Jacksonville Ordinance 2004-602; Chapter 126, Part 6A and 6B.

Respondent shall also indicate whether it intends to subcontract any services to JSEB certified firms. Points in this category will be assigned as follows:

If Respondent is not a certified JSEB, the Respondent must list any JSEB certified subcontractors on the Subcontractor

Bid Form that it intends to utilize in the performance of this Work. The listing should include names of the JSEBs, the scope of work the JSEBs will provide, and the percentage dollar amount of the work being subcontracted. Points will be awarded based on the amount of work that will be conducted by JSEB firms.

The points will be awarded as follows:

I. Respondent is a JSEB = 5 pts.

Respondent is not a JSEB but will subcontract Work to JSEBs:

Non-JSEB with JSEB partner:

I. Greater than or equal to 5% of work = 4 pts.

II. Greater than or equal to 4% of work, but less than 5% of work = 3 pts.

III. Greater than or equal to 3% of work, but less than 4% of work = 2 pts.

IV. Greater than or equal to 1% of work, but less than 3% of work = 1 pt.

V. Less than 1% = 0 pts.

1.23) Tie

In the event of a tie score, any tie will be broken using the total points for all evaluators. If a tie persists, the tie will be broken in accordance with the JEA Procurement Operational Procedures.

1.24) Subcontractors use for the Performance of the Work

The Respondent must list the names of the major Subcontractors that it intends to use for this Work, unless the Work will be self-performed by the Respondent. The Subcontractors must be listed on the Subcontractors Form which is available at jea.com. Failure to submit this form with the Response may result in rejection of Respondent's Response.

The Respondent shall not use Subcontractors other than those shown on the Subcontractor Form unless it shows good cause and obtains the JEA Representative's prior written consent.

If the Respondent plans to use Subcontractors to perform over 50% of the Work, the Respondent shall obtain JEA's approval at least five days prior to the Response Due Date. Failure to obtain JEA approval may result in rejection of the Respondent's Response.

1.25) Shipping, Freight, And Travel--F.O.B. Destination

The Respondent shall include the price for travel, shipment of materials and equipment in its pricing shown on its

Response unless otherwise stated herein. The shipment of all materials shall be F.O.B. Destination.

If the Solicitation allows for travel expenses to be billed separately, then all the Respondent’s travel expenses will be reimbursed in accordance with JEA's Contractor Travel Policy.

1.26) Required Forms to be Submitted

The following forms must be completed and submitted to JEA at the timeframes stated below. The Respondent can obtain the required forms, other than the Response Form by downloading them from JEA.com.

A. The following forms are required to be submitted with the Response:

I. Response Form- This can be found in Appendix B of this Solicitation

II. List of JSEB/Subcontractor Certified Firms (if any)

1.27)

If the above listed forms are not submitted with the Response by the Response Due Time and Date, JEA may reject the

Response.

B. JEA also requests the following documents to be submitted prior to Contract execution. A Response will not be rejected if these forms are not submitted at the Response Due Date and Time. However, failure to submit these documents prior to Contract execution could result in Response rejection.

I. Conflict of Interest Certificate Form - This form can be found at JEA.com

II. Insurance certificate

III. W-9

IV. Evidence of active registration with the State of Florida Division of Corporations (www.sunbiz.org)

V. Any technical submittals as requires by the Technical Specifications

1.28) Addenda Issuance

JEA may issue Addenda prior to the opening of Responses to change or clarify the intent of this Solicitation. The

Respondent is responsible for ensuring it has received all Addenda prior to submitting its Response and must acknowledge receipt of all Addenda by completing the Confirmation of Receipt of Addenda. JEA will post Addenda when issued online at JEA.com. Companies must obtain Addenda from the JEA.com website. It is the responsibility of each Respondent to ensure it has received and incorporated all Addenda into its Response. Failure to acknowledge receipt of Addenda may be grounds for rejection of a Response.

1.29) Contract Execution and Start of Work

Within 30 days from the date of Award, JEA will present the successful Respondent with the Contract. Unless expressly waived by JEA, the successful Respondent must execute a Contract for the Work within 10 days after receiving the Contract from JEA. If the Respondent fails to execute the Contract or associated documents as required, JEA may cancel the Award with no further liability to the Respondent and retain any bid security or bond.

Upon JEA's receipt of the executed Contract, certificate of insurance, and recorded Payment and Performance bonds

(if applicable), JEA will issue a PO, in writing and signed by an authorized JEA representative as acceptance of the

Response and authorization for the company to proceed with the Work, unless otherwise stated in the Contract or PO.

For Construction Services: In the event that JEA intends to authorize the successful Respondent to proceed with administrative work only, or with only a portion of the Work, then the PO shall state the specific limitations of such authorization and JEA will issue a separate written Notice to Proceed to authorize the Respondent to begin Field Work, when applicable, or to perform the remainder of the Work, or any portion thereof. The Respondent shall ensure that it is prepared to begin Field Work upon receipt of Notice to Proceed. Any Work performed outside of this partial authorization shall be at the Respondent's risk and JEA shall have no obligation to pay for such Work.

1.30) Ex Parte Communication

Ex Parte Communication is defined as any inappropriate communication concerning a Solicitation between any officers, employees or other representatives of Respondent and a JEA representative during the time in which the

Solicitation is being advertised through the time of Award. Examples of inappropriate communications include private communications concerning the details of the Solicitation in which a company becomes privy to information not available to the other Respondents. Social contact between companies and JEA Representatives should be kept to an absolute minimum during the Solicitation process.

Ex Parte Communication is strictly prohibited. Failure to adhere to this policy will disqualify the noncompliant

Respondent. Any questions or clarifications concerning this Solicitation must be sent in writing via email to the JEA

Buyer at least five business days prior to the opening date. If JEA determines that a question should be answered or a requirement should be clarified, JEA will issue an Addendum to the Solicitation.

1.31) Conflict of Interest

This conflict-of-interest policy applies to all JEA construction projects ("Project"). Any company bidding the construction phase of a Project cannot at the time of Response/bid submittal, be affiliated with or have any direct or indirect ownership interest in the architect/engineer ("Designer") of record. The company will also be prohibited from bidding if the Designer has any direct or indirect ownership interest in the Contractor. Should JEA erroneously award a contract in violation of this policy, JEA may terminate the contract at any time with no liability to company, and company shall be liable to JEA for all damages, including but not limited to the costs to rebid the Project. The purpose of this policy is to encourage bidding and eliminate any actual or perceived advantage that one Respondent may have over another.

1.32) Certifications and Representations of the Company

By signing and submitting its Response, the Respondent certifies and represents as follows:

A. That the individual signing the Response is duly authorized to contractually bind the Respondent to the terms and conditions of this Solicitation and the Contract. Respondent shall provide satisfactory evidence of such authority within three days of JEA’s request.

B. That every aspect of the Response and the detailed schedule for the execution of the Work are based on its own knowledge and judgment of the conditions and hazards involved, and not upon any representation of JEA. JEA assumes no responsibility for any understanding or representation made by any of its representatives during or prior to execution of the Contract unless such understandings or representations are expressly stated in the Contract and the

Contract expressly provides that JEA assumes the responsibility.

C. That, if successful, the Respondent will be registered to conduct business in the State of Florida and in active status with the Florida Division of Corporations at the time of execution of a Contract.

D. That the Respondent maintains in active status any and all licenses, permits, certifications, insurance, bonds and other credentials including, but not limited to, all licenses necessary to perform the Work. The Respondent also certifies that, upon the prospect of any change in the status of applicable licenses, permits, certifications, insurances, bonds or other credentials, the Respondent shall immediately notify JEA of status change.

1.33) Ethics

By submitting a Response, the Respondent certifies that its Response is made without any previous understanding, agreement or connection with any other person, firm, or corporation submitting a Response for the same Work other than as a Subcontractor or supplier, and that the Response is made without outside control, collusion, fraud, or other illegal or unethical actions. The Respondent shall comply with all JEA and City of Jacksonville ordinances, policies and procedures regarding ethics.

The Respondent shall submit only one Response to this Solicitation. If JEA has reasonable cause to believe the

Respondent has submitted more than one Response for the same Work, other than as a Subcontractor or sub-supplier, JEA shall disqualify the Response and may pursue debarment actions.

The Respondent shall disclose the name(s) of any public officials who have any financial position, directly or indirectly, in Respondent or its Response by completing and submitting the Conflict-of-Interest Certificate Form available at jea.com. Failure to fully complete and submit the Conflict-of-Interest Certificate will disqualify the

Response. If JEA has reason to believe that collusion exists among the Respondents, JEA shall reject any and all

Responses from such Respondents and will proceed to debar the Respondents from future JEA Awards in accordance with the JEA Procurement Code.

JEA is prohibited by its Charter from awarding contracts to JEA board members, officers or employees, and is prohibited from awarding contracts in which a JEA officer or employee has a financial interest. JEA shall reject all

Responses from JEA board members, officers or employees, as well as all Responses in which a JEA officer or employee has a financial interest.

In accordance with Florida Statutes Sec. 287.133, JEA shall reject Responses from any persons or affiliates convicted of a public entity crime as listed on the Convicted Vendor list maintained by the Florida Department of Management

Services. JEA shall not make an Award to any officer, director, executive, partner, shareholder, employee, member, or agent active in management of the Respondent listed on the Convicted Vendor list for any transaction exceeding

$35,000 for a period of 36 months from the date of being placed on the Convicted Vendor list.

JEA shall also reject any Responses from any persons or affiliates that are listed on State of Florida’s Suspended

Vendor List, the City of Jacksonville’s Disqualified Vendor List, JEA’s Suspended Vendors list, or have had a contract with JEA terminated for default within the last two (2) years.

1.34) JEA Publications

Applicable JEA publications are available at jea.com.

1.35) Mathematical Errors

In the event of a mathematical error in calculation of the prices entered on the Response, the Unit Prices will prevail.

The corrected price utilizing the Unit Prices quoted by Respondent will be used to determine if the Company is awarded a Contract for the Work and the corrected pricing will be used throughout the Term.

1.36) Modification or Withdrawal of Responses

The Respondent may modify or withdraw its Response at any time prior to the Response Due Date and Time by giving written notice to JEA's Chief Procurement Officer by submitting an updated Response. JEA will not accept modifications submitted by telephone, telegraph, email, or facsimile, or those submitted after the Response Due Date and Time. The Respondent may not modify or withdraw its Response for a period of 90 days following the opening of

Responses.

1.37) Notice of Prohibition Against Considering Social, Political, or Ideological Interests

Pursuant to Section 287.0501, Florida Statutes, JEA may not:

(i) Request documentation of or consider a vendor’s social, political, or ideological interests when determining whether a vendor is a responsible vendor; or

(ii) Give preference to a vendor based on the vendor’s social, political, or ideological interests.

1.38) Prohibition Against Contingent Fees

The Respondent warrants that it has not employed or retained any company or person, other than a bona fide employee working for the Respondent, or an independent sales representative under contract with the Respondent, to solicit or secure a contract with JEA, and that it has not paid or agreed to pay any person, company, corporation, or other individual, other than a bona fide employee working solely for the Respondent, or an independent sale representative under contract with the Respondent, any fee, commission, percentage, gift, or any other consideration, contingent upon or resulting from the Award or the Contract. If a breach or violation of the provisions occurs, JEA shall have the right to terminate the Contract without liability, and at its discretion, to deduct from the Contract Price, or otherwise recover, the full amount of such fee, commission, percentage, gift or consideration.

1.39) Protest of Solicitation and Award Process

Any protests regarding this Solicitation must be filed in writing and in accordance with the JEA Procurement Code, as amended from time to time. The JEA Procurement Code is available online at www.jea.com.

1.40) Availability Of Response After Opening

In accordance with the Florida Public Records Law, Florida Statutes, Chapter 119, copies of all Responses are available for public inspection thirty (30) days after the opening of Responses or on the date of Award announcement, whichever is earlier. Respondents may review opened Responses once they are available for public inspection by contacting the designated JEA Buyer or JEA's Public Records custodian whose contact information can be found at jea.com. JEA will post a summary of the Response results immediately after the Response opening.

1.41) Reservation of Rights of JEA

This Solicitation provides potential Respondents with information to enable the submission of written offers. This

Solicitation is not a contractual offer or commitment by JEA to purchase products or services. JEA reserves the right to reject all Responses, and to waive informalities if JEA deems such action to be in its best interest. JEA may reject any Responses that it deems incomplete or irregular including, but not limited to, Responses that omit a price on any one or more items for which prices are required, Responses that omit Unit Prices if Unit Prices are required, Responses that offer equal items when the option to do so has not been stated, and Responses that fail to include a Bid

Bond, where one is required. JEA reserves the right to cancel, postpone, modify, reissue and amend this Solicitation at its discretion. JEA reserves the right to cancel or change the date and time announced for opening of Responses at any time prior to the time announced for the opening of Responses. JEA may Award the Contract in whole or in part.

JEA may award multiple or split Contracts if it is deemed to be in JEA's best interest.

1.42) Sunshine Law

Article I, Section 24, Florida Constitution, guarantees every person access to all public records and Chapter 119, Florida Statutes, provides a broad definition of public records. JEA is subject to these laws and related statutes

("Florida's Public Records Laws"). All Responses to this Solicitation or RFI are public record and available for public inspection unless specifically exempt by law.

If a Respondent believes that any portion of the documents, data or records submitted in response to this Solicitation or RFI are exempt from Florida's Public Records Law, Respondent must (1) clearly segregate and mark the specific sections of the document, data or records as "Confidential," (2) cite the specific Florida Statute or other legal authority for the asserted exemption, and (3) provide JEA with a separate redacted copy of its Response (the "Redacted Copy").

The cover of the Redacted Copy shall contain JEA's title and number for this Solicitation or RFI and Respondent's name and shall be clearly labeled "Redacted Copy." Respondent should only redact those portions of records that

Respondent claims are specifically exempt from the Florida Public Records Laws. If Respondent fails to submit a redacted copy of information it claims is confidential, JEA is authorized to produce all documents, data and other records submitted to JEA in answer to a public records request for such information.

In the event of a request for public records to which documents that are marked as confidential are responsive, JEA will provide the Redacted Copy to the requestor. If a requestor asserts a right to any redacted information, JEA will notify Respondent that such an assertion has been made. It is Respondent's responsibility to respond to the requestor to assert that the information in question is exempt from disclosure under applicable law. If JEA becomes subject to a demand for discovery or disclosure of Respondent's redacted information under legal process. JEA shall give

Respondent prompt notice of the demand prior to releasing the information (unless otherwise prohibited by applicable law.) Respondent shall be responsible for defending its determination that the redacted portions of its Response are not subject to disclosure.

By submitting a Response to this Solicitation or RFI, Respondent agrees to protect, defend, and indemnify JEA from and against all claims, demands, actions, suits, damages, losses, settlements, costs and expenses (including but not limited to reasonable attorney fees and costs) arising from it relating to Respondent's determination that the redacted portions of its Response to this Solicitation or RFI are not subject to disclosure.

IF THE COMPANY HAS QUESTIONS REGARDING THE APPLICATION OF

CHAPTER 119, FLORIDA STATUTES, TO THE COMPANY'S DUTY TO

PROVIDE PUBLIC RECORDS RELATING TO THIS CONTRACT, CONTACT

THE CUSTODIAN OF PUBLIC RECORDS AT:

JEA

Attn: Public Records

225 North Pearl Street

Jacksonville, FL 32202

Ph: 904-665-8606 publicrecords@jea.com

1.43) Scrutinized Companies

Pursuant to Section 287.135(2), Florida Statutes, a company is ineligible to, and may not, bid on, submit a proposal for, or enter into or renew a contract with an agency or local government entity for goods or services of:

(1) Any amount if, at the time of bidding on, submitting a proposal for, or entering into or renewing such contract, contractor is on the Scrutinized Companies that Boycott Israel List, created pursuant to Section 215.4725, Florida Statutes, or is engaged in a boycott of Israel; or

(2) One million dollars or more if, at the time of bidding on, submitting a proposal for, or entering into or renewing such contract, contractor:

i. Is on the Scrutinized Companies with Activities in Sudan List or the Scrutinized Companies with Activities in the Iran Petroleum Energy Sector List created pursuant to Section 215.473, Florida Statutes; or

ii. Is engaged in business operations in Cuba or Syria.

Pursuant to Section 287.135(3)(a)4, Florida Statutes, JEA may terminate this Contract at JEA’s option if this Contract is for goods or services in an amount of one million dollars or more and the Company:

(1) Is found to have submitted a false certification under Section 287.135(5), Florida Statutes.

(2) Has been placed on the Scrutinized Companies with Activities in Sudan List or the Scrutinized Companies with Activities in the Iran Petroleum Energy Sector List created pursuant to Section 215.473, Florida Statutes.

(3) Is engaged in business operations in Cuba or Syria.

Pursuant to Section 287.135(3)(b), Florida Statutes, JEA may terminate this Contract at JEA’S option if this Contract is for goods and services of any amount and Company:

(1) Is found to have been placed on the Scrutinized Companies that Boycott Israel List; or

(2) Is engaged in a boycott of Israel.

1.44) Truth in Negotiation Certificate

Respondent understands and agrees that execution of the Contract by Respondent shall be deemed to be simultaneous execution of a truth-in-negotiation certificate under this provision to the same extent as if such certificate had been executed apart from the Contract, such certificate being required by Section 287.055, Florida Statutes. Pursuant to such certificate, Respondent hereby states that the wage rates and other factual unit costs supporting the compensation hereunder are accurate, complete and current at the time of contracting. Further, Respondent agrees that the compensation hereunder shall be adjusted to exclude any significant sums where JEA determines the contract price was increased due to inaccurate, incomplete or noncurrent wage rates and other factual unit costs, provided that any and all such adjustments shall be made within one year following the completion date of the Contract

1.45) Defined Terms

Words and terms defined in the section entitled "Definitions" of this document are hereby incorporated by reference into the entire document.

2) Contract Terms and Conditions 2.1) Contract Document Terms and Conditions

Section 2 of this Solicitation contains JEA’s general terms and conditions that will govern the Contract awarded under this Solicitation. The Contract Documents will incorporate by reference all of the terms and conditions of this

Solicitation, including all Technical Specifications, Appendices, Exhibits, Schedules and Forms included with this

Solicitation. An example of the Contract that the Company will be required to execute is available for review at jea.com.

2.2) Definitions

Capitalized words and terms used in this Solicitation shall have the meaning given to them in this Section 2. The

Technical Specifications to this Solicitation may define additional words and terms where necessary to clarify the

Work. Unless otherwise stated in this Solicitation or the Contract Documents, definitions set forth in Technical

Specifications shall apply only within the Technical Specifications.

2.3) Acceptance

JEA's written notice by the Project Manager to the Company that all Work as specified in the Contract, or a portion of the Work as specified in a Task or Work Order, has been completed to JEA's satisfaction. Approval or recognition of the Company meeting a Milestone or interim step does not constitute Acceptance of that portion of Work. Acceptance does not in any way limit JEA's rights under the Contract or applicable laws, rules and regulations.

2.4) Addendum/Addenda

An amendment to the Solicitation which is issued by JEA before the Response Due Date and Time.

2.5) Anniversary Date

The date which is twelve (12) months after the effective date of the Contract, and each date which is twelve (12) months after an Anniversary Date that occurs while the Contract is in effect.

2.6) Award

The written approval of the Contract by JEA’s Awards Committee and Chief Executive Officer.

2.7) Change Order

A written order issued by JEA after execution of the Contract, authorizing an addition, deletion, or revision of the

Work, or an adjustment in the Contract Price or the Contract Time. Change Orders do not authorize expenditures greater than the maximum indebtedness shown in the Contract. A Change Order that involves a material change to the

Contract may require a Contract Amendment.

2.8) Company

The legal person, firm, corporation or any other entity with whom JEA executes the Contract.

2.9) Company Representative

The individual responsible for representing the Company in all activities concerning the fulfillment and administration of the Contract.

2.10) Contract

The written agreement executed by JEA and the Company which describes the rights and obligations of JEA and the

Company with respect to the Work and incorporates all of the Contract Documents.

2.11) Contract Amendment

A written document signed by JEA and the Company issued after the execution of the Contract which authorizes an addition, deletion or revision of the Scope of Work, or the Contract Price, the Term or any other provision of the

2.12) Contract Documents

Contract Documents means the executed Contract, this Solicitation, all documents required by or submitted in connection with this Solicitation or the Contract, and any written Change Orders, contract amendments and Purchase

Orders executed by JEA.

2.13) Contract Price

The total amount payable by JEA to the Company during the Term in accordance with the terms and conditions of the

2.14) Contract Time

The number of calendar days or the period of time from when the written Purchase Order is issued to the Company, to the date Company has agreed to complete the Work, as set forth in the Contract Documents.

2.15) Defect

Work that fails to reach Acceptance, or Work that fails meet the…