Questions & Responses

• Question: We'd like to know the projected period of performance or rough timeframe when these sessions are to take place

Response: We generally expect these sessions to take place in September, October, or

November dependent on the date of award, and staff and contractor availability.

• Question: It would also be helpful to know level of effort expected in terms of total labor hours and whether all equipment and resources required will be made available.

Response: We anticipate this project may require between 180-200 labor hours in total with different positions working on components in parallel in some cases. The equipment and resources for the meetings will be largely provided by Reclamation.

• Question: Additionally, we would appreciate more detail on instructions for submitting a

Quote in conformance with your expectations and evaluation criteria.

Response: A more detailed set of instructions has been attached as an addendum to

FAR 52.212-1.

File details come from the government source that posted it. Updated .