This document contains an amendment to a solicitation for the Kortes Elevator Modernization BUILD project. The amendment provides revisions to the solicitation including removing and replacing the SF1442 form. The project involves modernizing elevators at the Kortes BUILD facility. The Bureau of Reclamation and Department of the Interior are the contracting agencies. The response due date remains May 12, 2023 at 1300 MT and offerors must acknowledge receipt of the amendment by that time. The amendment addresses questions from potential offerors regarding items like the period of performance, use of cranes during construction, cable requirements, security devices, and enclosure ratings.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0004_For_Kortes_Elevator_Build_0004.pdf | ||
| Sol_140R6023R0002_Amd_0004.pdf | ||
| Amendment_0003_Kortes_Elevator_Modernization_BUILD_0003.pdf | ||
| Sol_140R6023R0002_Amd_0003.pdf | ||
| Sol_140R6023R0002_Amd_0002.pdf | ||
| Sol_140R6023R0002_Amd_0001.pdf | ||
| Amendment_0001_0001.pdf | ||
| R2_Solicitation_140R6023R0002_Kortes_Elevator_Modernization_SITE_VIST__.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R6023R0002 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Billings MT 59107
R60
PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation
03/20/20230002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/20/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Kortes Elevator Modernization BUILD Pick Sloan Project, WY
See attached for changes incorporated by this amendment.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Linda Melnick
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
X 1
Solicitation No. 140R6023R0002 Amendment No. 00002
Description of Changes: The following changes are hereby incorporated into and made a part of this solicitation:
1) Remove the SF1442 in its entirety and substitute therefor the revised SF1442.
Receipt of Proposals: The hour and date for receipt of the proposals remains as May 12, 2023 at 1300 MT.
Acknowledgement: See Block 11 above regarding how to acknowledge this amendment. The Government must receive the acknowledgement at the place designated for receipt of bids (See Block 10 of the Standard Form 1442).
Third Party: If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.
5/12/2023
Q & A for Amendment 0002 Kortes Elevator Modernization Build
3. The period of performance listed on the solicitation for the Kortes Elevator Modernization is 8/9/23 to 5/1/23. Given the remote location and road closures you mentioned during the teams meeting I was curious if this date could be shifted to a period of time when winter weather wasn’t an issue. We have concerns regarding site accessibility as well as safety for our crews when transiting 60+ miles to and from Casper.
A: The period of performance is listed in F.1 52.221-10 Commencement, Prosecution and Completion of Work. The SF 1442 has been updated to remove the POP and to reflect the current proposal due date.
4. Does the top of the dam have a crane that could be used to hoist old equipment out and new equipment in? Old machine can be broken down but new machine is best left intact and will weight around 4,000 lbs. with a physical dimension of 40”W x 41”H x 41”D.
A: There is a crane at the top of the dam that is used only for placing and removing bulkhead gates on the intake of each penstock. It does not have the mobility to be used for the project. Any lifting means needed will have to be temporarily constructed or brought in for use on the project.
5. 14 21 00 - 21 Section 2.03 (D) requires 2 Cat5 cables but no traveler exists with cat5 cabling due to the wire size and movement of the traveling cable. Would cat5 equivalent cable be accepted?
A: Yes, a Cat5 equivalent can be evaluated and approved for the same use thru the submittal process.
6.14 21 00 - 21 Section 2.02 (G) requires hardware to be installed for security in both the hall and car. Can you provide details of the card reader or conductor type and quantities required?
A: We are not currently requiring any security devices. As far as we know, security devices are not a standard ASME code requirement, however, these should be addressed if they exist. The intent in this section is to have a controller that has the capability to integrate a standalone security and/or access management system via I/O or similar communication for possible future upgrades or requirements. Deviations from this requirement can be proposed in submittal process.
7. There is no mentioned of seismic devices and I wanted to verify that was correct. Typically counterweight ring and string, at a minimum, is required.
A: This location is in SDC (seismic design category) C with and component importance factor of 1.0 (due to the alternate route via stairs). This excludes this installation from ASME 17.1 – 8.4 seismic requirements as we interpret the language. If there is a standard requirement outside of this, those requirements must be satisfied.
8. Do the car top devices need to be in NEMA 4 enclosures? Car top box, door operator, inspection station, etc.
A: Yes, all electrical components on car top devices and those within the shaft shall be NEMA 4 rated.