This document is an amendment to a solicitation for the Kortes Elevator Modernization BUILD project. The amendment provides revisions to the safety personnel requirements, including changing the required on-site presence of a certified industrial hygienist from once per month to once per week during asbestos and coating activities. It also changes the proposal due date from May 19, 2023 to May 24, 2023 at 1300 Mountain Time and answers two questions about the safety personnel requirements. Offerors must acknowledge receipt of the amendment by the new due date in order to be considered for award of the contract. The solicitation is issued by the Bureau of Reclamation within the Department of the Interior for modernization of the Kortes Elevator at Kortes Dam.

View the file

Other files for this federal contract opportunity

Other files attached to Kortes Elevator Modernization BUILD, newest first.
File Type Posted
Sol_140R6023R0002_Amd_0004.pdf PDF
Amendment_0003_Kortes_Elevator_Modernization_BUILD_0003.pdf PDF
Sol_140R6023R0002_Amd_0003.pdf PDF
SF30_0002.pdf PDF
Sol_140R6023R0002_Amd_0002.pdf PDF
Sol_140R6023R0002_Amd_0001.pdf PDF
Amendment_0001_0001.pdf PDF
R2_Solicitation_140R6023R0002_Kortes_Elevator_Modernization_SITE_VIST__.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140R6023R0002 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Billings MT 59107

R60

PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation

05/18/20230004

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

03/20/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Kortes Elevator Modernization BUILD Pick Sloan Project, WY

See attached for changes incorporated by this amendment.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Linda Melnick

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Solicitation No. 140R6023R0002 Amendment No. 00004

Description of Changes: The following changes are hereby incorporated into and made a part of this solicitation:

1) Remove Specification section 01 35 30 – Contractor’s Onsite Safety Personnel in its entirety and substitute therefor the revised section 01 35 30 – Contractor’s Onsite Safety Personnel.

Receipt of Proposals: The hour and date for receipt of the proposals has changed from May 19, 2023 to May 24, 2023 at 1300 Mountain Time.

Acknowledgement: See Block 11 above regarding how to acknowledge this amendment. The Government must receive the acknowledgement at the place designated for receipt of bids (See Block 10 of the Standard Form 1442).

Third Party: If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.

Solicitation No. 140R6023R0002 Amendment No. 00004

Additional Questions and Answers

15. Section 01 35 30 of the RFP outlines that both a Contractors Onsite Safety Representative and a Part Time Safety and Health Professional is required. Can the Contractors Onsite Safety Representative perform both functions? We anticipate full time support in place with a senior level Safety/IH professional as the Contractors Onsite Safety Representative. We are not clear on what value an additional part time person would bring when we are staffing with a senior position already.

A: Refer to 01 35 30 B3c. No. Contractor Onsite Safety Representative and Part Time Safety and Health/CIH cannot be the same person. Only the Part Time Onsite Safety and Health Professional and/or Certified Industrial Hygienist will be approved as the same person.

16. Section 01 35 30 of the RFP outlines that the Certified Industrial Hygienist is required to make site visits during the start- up of asbestos removal activities and coating removal and application activities. Can you clarify if this is required one time per week or per month?

A: See Revised 01 35 30 Part time Safety and Health Professional and/or Certified Industrial Hygienist are required to be on-site once a week.

NO FURTHER QUESTIONS WILL BE ADDRESSED PRIOR TO PROPOSAL DUE

DATE OF MAY 24, 2023 1300 MST

Kortes Dam Elevator Modernization Amendment 0004

Contractor’s Onsite Safety Personnel

01 35 30 - 1

SECTION 01 35 30

CONTRACTOR’S ONSITE SAFETY PERSONNEL

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. ABIH: American Board of Industrial Hygiene.

B. Asbestos MAP: Asbestos Model Accreditation Plan.

1.03 REFERENCE STANDARDS

A. ASTM International (ASTM)

1. ASTM E1368-00 Visual Inspection of Asbestos Abatement Projects

B. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at https://www.usbr.gov/safety/rshs/index.html

C. Code of Federal Regulations (CFR)

1. 29 CFR Part 1926.32 Definitions

2. 29 CFR Part 1926.1101 Asbestos

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 30-1, Qualifications:

1. Contractor’s Onsite Safety Representative

2. Part-time Onsite Safety and Health Professional

3. Certified Industrial Hygienist (CIH)

a. Asbestos Contractor/Supervisor’s course completion certificate, current certificate for refresher training, state license, as applicable.

b. Copy of current ABIH certificate

01 35 30 - 2

c. Can be same person as Part-time Onsite Safety and Health Professional

4. Competent Person.

5. Independent testing laboratory:

a. NLLAP laboratory accreditation number

b. NVLAP laboratory accreditation number.

c. Name, address, and telephone number.

C. RSN 01 35 30-2, Safety Inspection Reports:

1. Prepare detailed weekly safety inspection reports listing noted deficiencies, digital photos, abatement dates and follow-up action for all jobsite activities.

2. Inspection report shall include findings of jobsite walk-through with Government representative.

D. RSN 01 35 30-3, CIH Reports:

1. Detailed weekly summary report for all asbestos related activities.

a. Summary of exposure monitoring results and sampling activities and interpretation of the data to confirm that the work is being performed in accordance with the approved plans.]

2. Detailed weekly summary report for all coatings removal and application activities.

a. Summary of exposure monitoring results and sampling activities and interpretation of the data to confirm that the work is being performed in accordance with the approved plans.]

3. Detailed weekly summary report for any hazardous agents related to work activities.

a. Summary of exposure monitoring results and sampling activities and interpretation of the data to confirm the work is being performed in accordance with the submitted approval plans.

4. Include noted deficiencies, digital photos, abatement dates and follow-up action.

5. Submit written report to COR within 7 days of the inspection.

1.05 QUALIFICATIONS

A. Contractor’s Onsite Safety Representative:

1. Competent supervisory employee with current safety and health related training, experience and duties on at least three projects of similar nature, size, complexity, and work to be performed as the current project

2. OSHA Construction 30-Hour Training Course including applicable elective subjects, for example Concrete and Masonry Construction; Confined Space Entry;

Cranes, Hoists, Elevators, and Conveyors; Fire Protection and Prevention;

01 35 30 - 3

Materials Handling, Storage, Use and Disposal; Powered Industrial Vehicles;

Safety and Health Programs; Scaffolds; Steel Erection; Tools - Hand and Power;

Welding and Cutting. Current first aid CPR certification.

3. Include resume with current telephone numbers of references, description of safety representative responsibilities, and copies of training certifications.

B. Contractor’s Part-time Onsite Safety and Health Professional:

1. The Contractor shall identify a part-time Safety and Health Professional that is acceptable to Reclamation. The safety professional shall visit the site a minimum of one time per week.

2. Include resume with current telephone numbers of references, description of safety professional responsibilities on similar construction projects, and copies of training certifications, and registration.

3. The individual shall be qualified by virtue of education, training, certification, and experience in which professional status in the construction safety field has been established.

4. Meeting the requirements training and experience requirements of Article 1.04A and:

a. Registered Professional Safety Engineer, Certified Safety Professional (CSP), Associate Safety Professional (ASP), Construction Health & Safety Technician (CHST), Occupational Health and Safety Technologist (OHST) or CIH certified by the Board of Certified Safety Professionals /American Board of Industrial.

b. Knowledgeable of current safety trends, industry practices, and can exercise technical expertise.

5. OSHA Construction 30-Hour Training Course including applicable elective subjects, for example Concrete and Masonry Construction; Confined Space Entry;

Cranes, Hoists, Elevators, and Conveyors; Fire Protection and Prevention;

Materials Handling, Storage, Use and Disposal; Powered Industrial Vehicles;

Safety and Health Programs; Scaffolds; Steel Erection; Tools - Hand and Power;

Welding and Cutting. Current first aid CPR certification.

6. Registered Professional Safety Engineer, Certified Safety Professional (CSP), or CIH certified by the Board of Certified Safety Professionals /American Board of Industrial.

7. Knowledgeable of current safety trends, industry practices, and can exercise technical expertise.

C. Certified Industrial Hygienist (CIH):

1. The Contractor shall identify an individual meeting the following requirements:

a. Certified by the American Board of Industrial Hygiene.

01 35 30 - 4

b. Trained in recognizing complex safety, occupational health, and environmental issues.

c. Knowledgeable of current safety trends, industry practices, and can exercise technical expertise.

d. Demonstrates professional level knowledge of exposure hazards associated with the specific construction activities and can provide best practices on mitigation and/or controls.

2. Include resume, description of CIH responsibilities on similar construction projects and copies of training certifications of the individual proposed as the onsite CIH.

3. For hazardous Materials work, CIH shall be independent from the Contractor.

D. Competent Person:

1. Accredited under any recognized state asbestos program.

2. As defined in 29 CFR 1926.32 and 29 CFR Part 1926.1101.

3. Qualified to perform visual inspections per ASTM E1368.

4. Capable of identifying existing asbestos hazards and selecting appropriate control strategy.

5. Authority to take prompt corrective measures to eliminate hazards

6. EPA Asbestos MAP “Contractor/ Supervisor” Training.

7. On jobsite during asbestos abatement activity.

8. Duties can be performed by CIH, if qualified.

1.06 APPLICATION

A. Designate an employee as the Contractor’s Onsite Safety Representative prior to start of construction and employ Safety Professional for part-time on the job.

1. Safety Professional requirements may be met by retaining appropriate level of services of an acceptable safety consultant.

B. Contractor’s Onsite Safety Representative Authorities, Duties, and Responsibilities:

1. Responsible for effectively implementing the Contractor’s Safety Program.

2. The Safety Representative shall coordinate all emergency response activities.

3. Recommend controls for observed hazards or predicted hazards.

4. Full authorization to correct unsafe acts on the spot, including the authority to stop work to correct safety and health problems.

5. Lead weekly safety meetings at the jobsite.

6. Onsite, during any and all construction activities.

01 35 30 - 5

7. Assemble, review, and sign each Job Hazard Analysis (JHA).

a. Review of JHA with employees.

8. Verify the correct use of respiratory protection and personal protective equipment.

9. Conduct and prepare weekly safety inspections in conjunction with the onsite government representative listing noted deficiencies, their abatement dates, follow up action. The report shall be available for review onsite.

10. Provide direct oversight and assemble a detailed report of all incident reviews, near-misses, accidents, and emergency response or rescue actions.

11. The Onsite Safety Representative may have other non-safety duties.]

C. Contractor’s Part-time Onsite Safety and Health Professional Authorities, Duties, and Responsibilities

1. The Onsite Safety and Health Professional’s job shall be hazard recognition, control and accident prevention.

2. Shall NOT be supervised by the onsite superintendent, but shall report directly to the corporate manager/owner.

3. Provide guidance and oversite to Contractor’s Onsite Safety Representative

4. Shall have full authorization to correct unsafe acts on the spot, including the authority to stop work to correct safety and health problems.

5. Shall visit the site weekly and inspect the site with a Government representative listing noted deficiencies, their abatement dates, and follow up action. The report shall be available for review onsite.

6. Shall participate in the planning and preparation of all activities including but not limited to:

a. Development and approval of JHA.

b. Review of equipment and materials.

c. Employee training.

d. Observing and reporting on activities.

7. Shall participate in the planning, preparation and execution of high exposure activities.

8. Duties include, but are not limited to the following:

a. Before start of construction, identify existing and predictable unsanitary, hazardous, or dangerous conditions.

b. Approve the site-specific Contractor safety and health plans and program prior to submission.

c. Coordinating all elements contained in the Contractor safety and health program and these specifications, including safety training.

01 35 30 - 6

d. May act as the qualified person for supervising erection and accepting final configuration and perform daily checks of fall protection, excavation and scaffolding systems in accordance with the regulatory standards.

e. Review and finalize all incident reviews, near-misses and accident reports in accordance with RSHS Section 3.

f. Attend the Safety Program Review Meeting and Conduct the monthly Joint Safety Policy Meetings in accordance with the RSHS Section 3.]

D. Certified Industrial Hygienist (CIH) Duties:

1. CIH duties include, but are not limited to:

a. Establish work place exposure assessments in accordance with federal, state, and local regulations and standard industrial hygiene practices to ensure personnel exposures are below regulated levels.

b. Review and sign the Asbestos Hazard Abatement Plan, Emissions Monitoring, Waste Characterization, Handling, and Disposal Plans prior to submission.

c. Conduct and/or review and sign all asbestos pre-abatement test results, working level test results, post-abatement test results, and clean-up monitoring in accordance with the submitted plans.

d. Visit the site during start-up of asbestos removal activities and a minimum of one time per {week}{month}during all asbestos clean-up and removal activities to confirm that the work is being performed in accordance with the submitted plans.

e. Conduct final asbestos clearance sampling and submit sample data to the COR prior to asbestos containment removal.]

f. Review and sign the Written Compliance Program for Worker Protection, Containment System Plan, Emissions Monitoring Plan, Waste Characterization, Handling, and Disposal Plan, Heavy Metal Exposure Certifications and Test Results, Working Level Test Results, Post- Construction Test Results, and Certificate of disposal.

g. Conduct and/or coordinate and review and sign all coatings background sampling, surface sampling, waste stream sampling, personal exposure monitoring, area air monitoring, peripheral air monitoring, and clean up monitoring.

h. Visit the site during start-up of coating removal and application activities and a minimum of one time per {week}{month} during all coating removal and application activities to confirm that the work is being performed in accordance with the submitted plans.]

h. Visit the site during start-up of coating removal and application activities and a minimum of one time per week during all coating removal and

01 35 30 - 7 application activities to confirm that the work is being performed in accordance with the submitted plans.

i. Conduct functional testing of engineering controls, critical barriers, containments and secondary containments.

j. Full authorization to correct unsafe acts, stop work, prevent exposures, control contamination, engineering controls and containment failures.

k. Exposure assessments to select or verify personal protective equipment or respiratory protection inside and outside containments.

l. Prepare detailed monthly CIH inspection reports in accordance with RSN 01 35 30-2.

m. Attend the Safety Program Review Meeting in accordance with the RSHS Section 3.]

n. Assist Onsite Supervisor in implementing Hazardous Materials safety and health requirements during the performance of the required work.

o. Available for emergencies.

p. MAP Contractor/ Supervisor training.

q. Direct air monitoring

E. Competent Person:

1. Duties include, but are not limited to:

a. Control entry to and from the Regulated Area.

b. Ensure engineering controls in use are in proper operating condition and are functioning properly.

c. Assure employees wear appropriate PPE, are trained in the use of appropriate methods for exposure control, use proper hygiene methods and decontamination procedures;

d. Supervise employee exposure monitoring required by 29 CFR 1926.1101.

e. Responsible for compliance with Federal, RSN 01 35 10-XX Safety Plan and Asbestos Personnel Protection Plan.

f. Review and sign the Asbestos Personnel Protection Plan.]

1.07 QUALITY ASSURANCE

A. Contractor’s Onsite Safety Representative:

1. The effectiveness of the Contractor’s Onsite Safety Representative in prosecuting the safety program will be subject to continued review and approval by the COR.

2. Should the Contractor’s onsite safety representative’s effort be deemed insufficient the Contractor may be required to provide the services of a qualified, full-time safety and health professional at no additional cost to the Government.

01 35 30 - 8

B. Contractor’s Part-time Onsite Safety and Health Professional:

1. The effectiveness of the Contractor’s Onsite Safety Professional in prosecuting the safety program will be subject to continued review and approval by the COR.

2. Should the Contractor’s part-time safety professional effort be deemed insufficient the Contractor may be required to provide the services of a qualified, full-time Safety and Health Professional at no additional cost to the Government.

C. Certified Industrial Hygienist (CIH):

1. The effectiveness of the Contractor’s Onsite CIH in prosecuting the asbestos and coatings activities will be subject to continued review and approval by the COR.

2. Should the Contractor’s CIH effort be deemed insufficient the Contractor may be required to provide the services of a qualified, full-time CIH during all coatings and asbestos related activities at no additional cost to the Government.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

END OF SECTION