This document provides details for a federal contract solicitation for actuator replacement work. The Bureau of Reclamation is seeking proposals to replace collection system actuators, stems, stem covers, radial gate seals and miscellaneous electrical equipment at 16 sites located near Thomasville, Colorado. Interested vendors can view the request for proposal on July 25, 2019 via https://www.fbo.gov. Proposals are due by August 28, 2019. The contract value is estimated between $1 million to $5 million. The solicitation will utilize a small business set-aside and be awarded using best value tradeoff procedures. Evaluation factors include technical plan, company experience, past performance, and price. Subfactors under the technical plan focus on work plan, safety, and schedule. The contract is set aside for small businesses and registered vendors must be active in the System for Award Management database.
Pre-Solicitation Notice for NORTH SIDE / SOUTH SIDE COLLECTION SYSTEM ACTUATOR REPLACEMENT
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_003_posted.pdf | ||
| SF30.pdf | ||
| Amendment_001_(2).pdf | ||
| Solicitation_No._140R6019R0002_-_FINAL.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Solicitation Notice
140R6019R0002
NORTH SIDE / SOUTH SIDE
COLLECTION SYSTEM ACTUATOR REPLACEMENT
Fryingpan – Arkansas Project
Colorado
Construction Work is located in close proximity to Thomasville, Colorado, and approximately 6-10 miles east of Norrie, Colorado 81642, in and around Pitkin County.
Principle components of work include: replacing collection system actuators, stems, stem covers, radial gate seals and miscellaneous electrical equipment at multiple locations with varying levels of access at the following sites:
1.Mormon Creek.
2.Ivanhoe.
3.North Fork.
4.Chapman.
5.Hunter.
6.South Fork.
7.Midway.
8.Carter Creek.
9.No Name.
10.North Cunningham.
11.Granite Creek (No Contractor Access, furnish equipment and components only).
12.Granite Adit.
13.Fryingpan.
14.Middle Cunningham.
15.Sawyer.
16.South Cunningham
A ‘Request for Proposal’ solicitation package is anticipated to be available for viewing through electronic commerce via https://www.fbo.gov on or about July 25, 2019. Interested vendors may also check Bureau of Reclamation's website at https://www.fedconnect.net. Proposals will be due on or about August 28, 2019 at the Bureau of Reclamation's Great Plains Regional Acquisition Office, 2021
4th Avenue North, Billings, Montana. All responsible sources may submit a proposal, which shall be considered by the Bureau of Reclamation. The estimated price range of this acquisition is between https://www.fbo.gov/ https://www.fedconnect.net/
$1,000,000 and $5,000,000. The acquisition will be a Small Business Set-Aside using Request for
Proposal procedures in accordance with Federal Acquisition Regulation, Part 15 – Contracting by
Negotiation. The applicable North American Industry Classification System (NAICS) Code is 238990
– All Other Specialty Trade Contractors. The evaluation factors that will be used include:
FACTOR 1: Technical Plan for Construction –
There are four sub factors within of this evaluation factor: Work Plan, Safety, Schedule and
Manufacturing.
Sub Factor 1A: Work Plan –
Furnish a detailed narrative work plan describing the removal and installation of the equipment. The plan shall address all equipment design, removal, manufacturing, shipping, installation, commissioning, and testing of the equipment and associated components. For all of the listed equipment, manufacturer’s commercial cut sheets or product data sheets must be provided to facilitate confirmation that the proposed equipment’s salient characteristics meet the requirements of the specification.
The more detailed and complete the installation plan/procedures and interrelationships recognized and identified between work items, the more knowledgeable of the complexity of this project the offeror will be perceived to be and will be evaluated more favorably.
Sub Factor 1B: Safety - Provide the following safety information:
1. A detailed description of your company’s safety program. Include information such as safety professional(s) on staff, safety committee, regular consultation, etc. Descriptions of employee safety training or certifications, hazard recognition, abatement methods, and provisions for subcontractor safety shall be included. Include descriptions of any serious, willful, or repeat violations that the company has been either cited for or assessed penalties for over the past five years by Federal or State OSHA. Provide any supporting information that demonstrates how corrective actions occurred to mitigate the issues.
Furthermore, provide a description of any citations or assessed penalties during the past five years by the EPA, Air Quality Management District or any Regional Water Quality
Control Board. Provide any supporting information that demonstrates corrective actions taken. Additionally, list any safety or environmental awards or recognition your company has received during the past five years.
2. Include a job hazard analysis (JHA) which addresses the primary phases of the project.
The JHA will be used to determine the offeror’s understanding of the occupational safety and health issues associated with the project. A general company safety program with references to regulations and/or general references to meeting the safety requirements in the specifications is not acceptable and will result in a lower rating.
3. The Government will evaluate the offeror’s past safety record and experience, using the offeror’s list of safety data, or other information available to the Government. The above factor, and related subfactors, if any, must be addressed in detail. Failure of the offeror to address in detail any of the factor requirements may result in a lower rating for the factor, or the factor may be rated unacceptable
Sub Factor 1C: Schedule –
Furnish a detailed schedule for equipment removal, hazardous material activities, temporary power, installation, commissioning, and testing of the power distribution equipment and associated components. The schedule must address the key submittals that are required prior to mobilizing and commencing onsite work, material procurement and manufacturing lead times. The schedule should detail all activities and work items anticipated identifying timelines for starting and completing each activity within the construction work window identified in Section 01 14 10 of the specifications.
Contractor shall identify their specific planned outages.
Offerors shall assume a Notice to Proceed date of September 15, 2017 for the purpose of preparing this schedule. Schedules that lack detail in work activities presented or omit project activities deemed critical to timely completion of the project within outage periods identified in the specifications will be evaluated less favorably. Offerors whose schedules realistically indicate that they will be able to minimize the length of plant outage will be rated more favorably.
FACTOR 2: Company Experience –
Furnish a list (no more than 5) of Federal, State, local government or commercial projects completed within the last 10 years similar in scope and complexity to the work required under this solicitation.
The projects must clearly demonstrate the ability to successfully accomplish projects in a timely manner, utilize resources, and work with project owners. Similar projects are defined as work involving industrial power distribution and complex work within a short schedule window for completion. Include experience with remote locations and similar equipment.
The following information must be provided for each project:
• Name and location of project.
• Description of work.
• Note whether or not offeror was the prime contractor and what portion of the work was performed by the offeror and what portion was performed by subcontractors.
• Original completion time and date, and actual dates and duration for each project (including modifications).
• Initial contract amount and final contract amount (including modifications).
• Name, address and phone number of CO/owner/COR/point of contact who may verify information for this project.
• Any problems encountered in performance of the work and corrective actions taken.
Owner or other references with incorrect or missing phone numbers and contact names may not be able to be evaluated, which may result in lower ratings as well. If an offeror intends to utilize subcontractors to perform any of the major components of work, all of the above information must be provided for each proposed subcontractor.
This information will be used to assess the offeror’s experience level on recent contracts for similar work. The greater the extent to which the offeror can demonstrate successful completion of projects similar in size and complexity to that required under this solicitation, the more favorably the proposal will be rated. Failure of the offeror to address in detail any of the factor requirements may result in a lower rating.
FACTOR 3: Past Performance –
If an offeror intends on utilizing subcontractors to perform any of the work beyond supplying materials, DUNS numbers shall be submitted on behalf of each proposed subcontractor.
The Government will also use past performance information obtained by other sources than those identified by the offeror. The Government will utilize the Past Performance Information Retrieval
System (PPIRS) database located at http://www.ppirs.gov for obtaining past performance information.
Offerors will be evaluated on the degree to which they have completed similar projects on schedule and without performance problems. Information submitted regarding adverse performance problems will be considered, as well as mitigating circumstances detailed in the proposal for any performance problems identified.
In case of an offeror without a record of relevant past performance or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on pass performance.
FACTOR 4: Price –
List price in Section B, Price Schedule. Price must be listed in the price schedule for each CLIN. Each
CLIN price must be supported with documentation to determine reasonableness in accordance with
WBR 1452.215.83.(e)
The relative importance of the non-price factors is as follows:
FACTOR 1 - Technical Plan for Construction –
• Sub Factor 1A – Work Plan
• Sub Factor 1B – Safety
• Sub Factor 1C – Schedule
FACTOR 2 – Company Experience
FACTOR 3 – Past Performance
FACTOR 4 – Price (Volume III)
Subfactors 1A, 1B, and 1C all of which are significantly more important than Factors 2 through 4.
Factors 2 and 3 are relatively equal in importance, but more important than Factor. All evaluation factors, other than cost or price when combined, are significantly more important than cost and price
(Factor 4).
NOTE 1 - If an offeror intends on utilizing subcontractors to perform any of the work, all of the above information must be provided for each subcontractor.
NOTE 2 - The Government intends to award this contract without conducting negotiations; therefore, failure to submit any of the information addressed above for each of the factors and/or subfactors may result in an unacceptable proposal.
SAM: Effective July 29, 2012, any contractor interested in doing business with the government must register in the System for Award Management (SAM) database prior to award of a contract or agreement. SAM is a federal government owned and operated free website that consolidates the
Central Contractor Registration (CCR), the online representations and certifications application (orca), and the Excluded Parties List System (EPLS).
The vendor’s Duns and Bradstreet number and banking information are required for registration.
Contractors may obtain information on registration and annual confirmation requirements via the SAM website accesses through https://www.sam.gov/portal/public/sam/ or by the Federal Service Desk at 1-
866-606-8220.
Payment requests for the anticipated contract must be submitted electronically through the U.S.
Department of the Treasury’s Internet Payment Platform (IPP) system. The IPP website is located at https://www.ipp.gov. The contractor must use the IPP website to register access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via e-mail ippgroup@bos.frb.org or phone (866) 973-3131. If the contractor is unable to comply with the requirements to use IPP for submitting invoices for payment, the contractor must submit a waiver request in writing to the Contracting Officer with its proposal or bid.
For further information, interested vendors may contact Stormy Gallagher, sgallagher@usbr.gov.
https://www.sam.gov/PORTAL/PUBLIC/SAM/ https://www.ipp.gov/ mailto:IPPGROUP@BOS.FRB.ORG mailto:sgallagher@usbr.gov