Amendemnt_0006_0006.pdf
PDF 138 KB Posted
- Attached to
- Friant Dam Drum Gate Corrosion Project Federal contract opportunity
- Solicitation number
- 140R2022B0005
About this file
This document contains an amendment to a solicitation for the Friant Dam Drum Gate Corrosion Project. The Bureau of Reclamation is seeking to control corrosion and rehabilitate the functionality of the drum gate at Friant Dam. The amendment provides additional questions and answers for offerors. Key details include clarification that rectangular trash rack bars are acceptable, instruction to price the required removal and replacement of a 4-inch drain pipe under CLIN 18, and explanation that interior gate anodes only need to demonstrate continuity and further testing is not required given inaccessibility when water is present. The response deadline remains February 10, 2023 at 1:00 pm Pacific Time. Offerors must acknowledge this amendment by submitting a signed copy of the SF30 form along with their proposal.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R2022B0005_Amd_0006.pdf | ||
| Sol_140R2022B0005_Amd_0005.pdf | ||
| 140R2022B0005_Amend_0005_0005.pdf | ||
| Sol_140R2022B0005_Amd_0004.pdf | ||
| 140R2022B0005_Amd_0004_0004.pdf | ||
| Sol_140R2022B0005_Amd_0003.pdf | ||
| 140R2022B0005_Amendment_0002_0002.pdf | ||
| Sol_140R2022B0005_Amd_0002.pdf | ||
| 140R2022B0005__Amendment_No__0001_0001.pdf | ||
| Sol_140R2022B0005_Amd_0001.pdf | ||
| Solicitation_No__140R2022B0005.pdf | ||
| Sol_140R2022B0005.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R2022B0005 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815
R20
Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation
02/03/20230006
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
11/22/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The Solicitation cited in block 9A above, Friant Dam Drum Gate Corrosion Project is hereby amended.
Purpose: The purpose of this amendment is to incorporate the additionally submitted
Questions and Answers.
The date and time for receipt of offers remains February 10, 2023 at 1:00 pm Pacific Time.
The Offeror must acknowledge this amendment by submitting a signed copy of this SF30 along with their proposal.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Rosana Yousefgoarji
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2022B0005/0006
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Solicitation: 140R2022B0005 Amendment: 00006
140R2022B0005
Friant Dam Drum Gate Corrosion Project
Question and Answer 2
1.Q. Will the Government allow a variation in trash rack design to allow for rectangular bars as opposed to rounded bars? If it must be rounded, each bar will need to be machined as they come rectangular from the mill. This will greatly increase the cost of the trash racks, a design with rectangular designs will be more efficient.
1.A. Yes, rectangular is acceptable. There are a few shapes that are no longer in production relative to the original. The closest off the shelf, dimensional pieces are acceptable.
2.Q. Reviewing the amended pricing sheet, we noticed there is no line item for the required removal and replacement of the 4” drain pipe, ball valve and weighted chain. Where would you like us to put this pricing?
2.A. Please, review Solicitation parts Section B CLIN 18 and See Section C Specifications - 32 22 25
3.Q. After speaking to galvanic corrosion engineers, the proposed installation of anodes may not be ideal for protection of the structure. The anodes must be submerged to work and test properly.
Installing anodes on the inside of the gate which is generally not submerged would not be an ideal placement, and would be impossible to properly test. Similarly, placing anodes on the downstream skinplate would be impossible to test due to the inaccessibility of the anodes when the chamber is filled with water. The only portion of the gate that would be possible to test after installation would be the upstream skinplate when there is water on the gate, but the current plans do not show any anodes being installed at that location. Will the Government require the anodes to be installed on the inside of the gate with this in mind?
3.A. The anodes in the gate interior will not always have water present. However, this interior corner of the drum gate experienced pooling of water previously, according to inspection photos. The anodes will only be active when the gate is in the down position and water pooling is present. The specification only requires continuity verification. We realize that the protected areas are inaccessible when water is present, so further testing beyond continuity is not required. Anodes were not used on the upstream skinplate based on the inspection photos. Photos showed corrosion issues were not present along the skinplate. Therefore, a “hot spot” system was pursued instead of a larger cathodic protection system for the whole gate. If corrosion were to become an issue on the upstream skinplate in the future anodes could be added at a later time.
4.Q. Does the Government know the approximate weight of the gate, or the force required to rotate the gate from the down position to the up position?
Solicitation: 140R2022B0005 Amendment: 00006
4.A. No record found of weight of the gate and forced required to rotate the gate.