About this file

This document is an amendment to a solicitation for the Friant Dam Drum Gate Corrosion Project being conducted by the Department of the Interior Bureau of Reclamation. The amendment extends the offer submission deadline from January 20, 2023 to February 10, 2023. It also notifies bidders that a second pre-proposal site visit will take place on January 13, 2023 for interested parties to gain a better understanding of the work requirements and site conditions. Hard hats and closed toe shoes are required for the site visit. Any questions must be submitted in writing by January 20, 2023. The project scope involves controlling corrosion and rehabilitating the drum gate functionality at Friant Dam to protect it for years to come.

View the file

Other files for this federal contract opportunity

Other files attached to Friant Dam Drum Gate Corrosion Project, newest first.
File Type Posted
Amendemnt_0006_0006.pdf PDF
Sol_140R2022B0005_Amd_0006.pdf PDF
140R2022B0005_Amend_0005_0005.pdf PDF
Sol_140R2022B0005_Amd_0005.pdf PDF
Sol_140R2022B0005_Amd_0004.pdf PDF
Sol_140R2022B0005_Amd_0003.pdf PDF
140R2022B0005_Amendment_0002_0002.pdf PDF
Sol_140R2022B0005_Amd_0002.pdf PDF
140R2022B0005__Amendment_No__0001_0001.pdf PDF
Sol_140R2022B0005_Amd_0001.pdf PDF
Solicitation_No__140R2022B0005.pdf PDF
Sol_140R2022B0005.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140R2022B0005 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815

R20

Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation

01/06/20230004

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

11/22/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The Solicitation cited in block 9A above, Friant Dam Drum Gate Corrosion Project is hereby amended.

Purpose: The purpose of this amendment is to 1) incorporate the Questions and Answers as well as the attached Site Visit Attendance List, 2) to notify all concerned that the date for the second Site Visit will be Friday, January 13, 2023, and 3) extend the offerors due date from 20 January 2023 to 10 February 2023.

Second Site Visit:

An organized site visit has been scheduled for January 13, 2023 at 10:00 a.m. Interested

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Rosana Yousefgoarji

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140R2022B0005/0004 bidders shall make arrangements to attend the site visit by contacting Darrin Williams, (559)

289-9463 or email dwilliams@usbr.gov. Section L

FAR Part 52.236-27 Site Visit Alt I (Feb 1995) contains detailed information on the site visit.

Please email Darrin the list of attendees with their driver¿s license.

Prospective bidders are strongly encouraged to attend the pre-bid site visit to gain a better understanding of the work requirements and site conditions.

Hard hats are required. Attendees do need to wear long pants, closed toe shoes, and safety vests.

Any questions asked at the site visit must be submitted in writing. Questions must be submitted to the solicitation point of contact, within a reasonable time to allow for a reply prior to the bid due date. Section L FAR Part

52.214-6 Explanation to Prospective Bidders (Apr

1984) specifies oral explanations or instructions given before the award of Contract will not be binding.

The date and time for receipt of questions is

January 20, 2023 at 10:00 am.

The date and time for receipt of offers is hereby

CHANGED from January 20, 2023 at 1:00 pm Pacific

Time to February 10, 2023 at 1:00 pm Pacific Time.

The Offeror must acknowledge this amendment by submitting a signed copy of this SF30 along with their proposal.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

T]NITED STATES DEPARTMENT OF THE INTERIOR

BUREAUOF RECLAMATION

Interior Region 10 - Califomia-Great Basin

MEETING ATTENDANCE RECORD

Friant Dam Drum Gate Corrosion Project (140R2022R0005) - Pre-Proposal Site Visit loblo^"^ Tr,,,( gqq.LlTc- tt1'to *nYh r^ p g 11'r-'@ grcct, <o,,'"''.A;Vl^.,-,p,-.--ksr) 7qq-z<*< t)l ;u 14 a: 1&2L, (c'r,-''4Yl,tu .l*., < tzl< )

{-e,€vlt/'., J f:t 6€A ttok, _ ttl^ I ait'1€. Ll-Lt 5@ a-l lW a'b) t"'{','1 Co-"\,n t 4/t/

14^ r,lrr,.t ! t'lr-.-zr:r-.- t)t(l-r,L [a,*t-,":"- /1tA- g+L' - o?,t:4 M 4,elOror"- < @' JF t'z"* te.r.*J .. .tt E fi4wu- f,itettw,-v^-"<

*^J - U qgh-,t- - t rVt*\/ ltr- yY3-V;/ 1 ^h^e[ r^, n@ k{,nn, ^ - u.l^ ., u ^6"^"tlLof{ t.l^, ll,"l,^, ^ lr,[,/^ !^;,1,"r

4(d-Jzz-yt8s 1) ru, L. l. b ^u,?

li e- o t r,y' L. t) ITrr,rll Du l.,a,q1 /,r,y'. fiurL €f3 nt q-flY€-it l^*t. r qsr_e J t n eJ,+.c_.a.--- J

.-l* Id "-.l b T-o-s r- -J-A /ta.r,+- 15t -541-6frd 5Ug\@G: ce *rua,,lPiJran, . <5t'\<#86^^r^ Rrs Eo3 -{zz-q"\30

U ( nlor- (u-\v'r,or.! Lo N4 Vtlcf/6 e.-LotE PA ,rnrtNC. co tu-t

Ltt q7t.2r( > <_) \-.,, €qYssr^tftu 'c--5.r-^ \-K<

Date: December 6,2022 Time: 10:00AM PDT Location: Friant Dam - Friant, CA

EMAILNAME ORGANIZATION PHONE

Solicitation No.: 140R2022B0005 Amendment: 0004 Answer & Questions Q. 1. Will it be possible to get access to the inside of the flood tube to inspect it and the condition of the Butterfly Valve?

A.1. At current reservoir elevation, it is not possible to get access to inspect the inside of the flood tube and the Butterfly Valve.

Q.2. What is the anticipated lake water level during construction?

A.2. Refer to section 01 14 12 - Work Restrictions for required lake water level during construction.

Q.3. What is the weight of the gate?

A.3. The total weight of the drum gate cannot be located in available Reclamation records.

Q.4. What is the anticipated timeframe where the BOR would like the construction to start. Will it be delayed due to a heavy snow or water year?

A.4. Per Table 01 14 12A, the anticipated time frame for construction range from September to February. Construction should began early in this time frame to allow for completion of tasks before reservoir rises above allowable construction elevation. Wet water years, preventing construction, could delay the project, where the agreement for period of performance will need to be extended between the Contractor and Reclamation.

Q.5. Is there a preferred water access point for assembling a floating plant to facilitate trash rack replacement?

A.5. There are multiple access points along the shores of Lake Millerton. Coordination will need to be made with California State Parks to allow for assembly of a floating plant to facilitate trash rack replacement.

Q.6. With the Holidays upcoming, could we get a bid extension to at least January 20th?

A.6. Per Amendment 0003 for 140R2022B0005, the bid due date has been extended to January 20th, 2023.

Q.7. Can you kindly send over the Site Walk Attendees List?

A.7. Yes, please see the attached.

Answer & Questions

Q.8. Is there a bulkhead for the supply pipe/butterfly valve work?

A.8. There is no bulkhead between the reservoir and the supply pipe/butterfly valve.

Q.9. If there is not a bulkhead, work would have to take place when lake levels are below the elevation of the supply pipe. Will the contract be extended if lake levels don’t drop below that elevation during the original period of performance?

A.9. Refer to section 01 14 12 - Work Restrictions for required lake water level during construction. Wet water years, preventing construction, could delay the project, where the agreement for period of performance will need to be extended between the Contractor and Reclamation.

Q.10. For the trash rack removal, the contractor is to drill out the upper portion of the existing anchor that is perpendicular to the concrete surface. Does the image below accurately depict this requirement?

A.10. The concept shown is correct. Depth will need to be checked against anchor manufacturer.

Q.11. Are the new anchors supposed to be installed in the drilled out portion as shown above, in the same location as the original anchors without the diagonal portion?

A.11. Yes. The new anchors will be in the same location to match the bolt pattern shown on the drawings of the trash rack.

Q.12. Is there a requirement for the size of anchors to be installed?

A.12. Anchors should match the size of the existing anchors as shown in Section A-A on drawing 214-D- 5822.

Answer & Questions

Q.13. Is there a deadline to submit questions? Will questions be answered with an addendum?

A.13. The questions were required to be submitted by December 23, 2022.

Q.14. Will the Government move the bid date to January? It has been difficult to receive quotes or positive responses from subcontractors, citing the lack of personnel and time due to the holidays.

A.14. Per Amendment 0003 for 140R2022B0005, the bid due date has been extended to January 20th, 2023.

Q.15. If using a marine plant to remove and reinstall the trash rack, will we be able to install and use anchors in the face or pier of the dam?

A.15. Anchors can be installed on the dam, upstream face of the dam, and dam piers to remove and reinstall the trash rack. Details of anchors installation should be provided to the Contracting Officer Representative from Reclamation and approved prior to any execution.

Q.16. How has the trash rack been removed in the past

A.16. The trash rack has never been removed. The current trash rack is original to the Dam.

Q.17. Will the Government distribute the photos that were shown at the site visit?

A.17. There will be no additional photos provided with the photos in Specifications No. 20-C0901

Q.18. When replacing the seals on the gate, does the contractor need to replace all parts of the seal to include the spring brass leaves?

A.18. Yes, all parts of the seal are to be replaced including spring brass, rubber seals, filler blocks, ,fasteners, etc. The existing clamp bars and seal guards are to be reused.

Q.19. Will the contractor be responsible for removing the boat barrier that is resting on top of the gate?

A.19. Contractor will be responsible for removing the boat barrier that is resting on top of the gate during construction.

Q.20. Is there a weight capacity for the downstream catwalk?

Answer & Questions A.20. The total weight capacity for the downstream catwalk was not available in Reclamation records.

Q.21. Our main estimator who was to attend this site visit tomorrow has contracted the Covid Virus over the weekend and will not be able to attend this site visit. Is there any possibility for us to fly out on a later date to visit the project site in order for us to submit a thorough price proposal for this solicitation?

A.21. There will be an additional site visit on January 10th, 2023.

Q.22. There are structural steel material dimensions called out for use in fabrication of the trash rack that are no longer standard production items. These items can be custom milled at a premium expense.

For example we have found 3 items (potentially more) that are no longer standard: L6x3-1/2x17.4# Bulb Angle, FB 1-3/8 x 6” Flat Bar, and 13/16” Radius Trash Bar. Please confirm that the Bureau would request that any items that are no longer standard production dimensional items for the trash rack can be replaced with approximate dimensional steel items that are available “off the shelf”.

A.22. Yes, "off the shelf" steel that most closely matches the dimensions of the original trash rack. The bolt pattern, trash rack bar spacing, and overall dimensions should remain as shown on the drawings.

Q.23. Is there a deadline for further questions? Will there be an amendment with questions/answers?

A.23. Yes, and with the second site visit, question submission will be required no later than January 20, 2023 at 10:00am.