Sol_140P9725R0005_Amd_0002.pdf
PDF 91 KB Posted
- Attached to
- RESTORE ELEC. POWER TO COAL CREEK CAMP
- Solicitation number
- 140P9725R0005
About this file
This document is a Standard Form 30 (Amendment of Solicitation/Modification of Contract) for Solicitation 140P9725R0005, which involves restoring electrical power to Coal Creek Camp for the National Park Service Alaska Region. Amendment 0002, effective 06/03/2025, adds a Questions and Answers section to clarify project details. Key clarifications include confirmation that contractors can use both upper and lower roads (lightly maintained trails) for transportation, flexibility for 12-hour workdays including weekends and holidays, and specifics about connecting the existing incinerator circuit to a new disconnect on pole 4a. The period of performance is 07/21/2025 to 08/31/2026, and the contract will result in a firm fixed price order. Vendors can schedule a site visit by contacting Chad Billock, Facility Manager for Gates of the Arctic National Park and Preserve.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P9725R0005_Amd_0004.pdf | ||
| UPDATED_SOW_0004.docx | DOCX document | |
| Sol_140P9725R0005_Amd_0003.pdf | ||
| Sol_140P9725R0005_Amd_0001.pdf | ||
| B08c_Drawings_-_Specifications.pdf | ||
| Sol_140P9725R0005.pdf | ||
| B08d_Wage_Determination.pdf | ||
| B08b_Statement_of_Work.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P9725R0005 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PAK
Anchorage AK 99501-2327 240 W. 5th Ave, Room 114 NPS, ARO - Alaska Regional Office
06/03/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/03/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
An award from this RFP will result in a firm fixed price order.
RFP 140P9725R0005 is hereby amended as follows:
1. Questions and Answers have been added.
2. All other terms and conditions remain unchanged by this amendment.
3. POC for this action is Tyler Groves (MABO LEAD), 907-202-0274.
Questions (Q) & Answers(A):
Q1. Logistically, FLC's intent is to transport equipment and material by barge to Coal
Creek. Then traverse the road into Coal Creek to complete the work. The use of the airstrip
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Tyler Groves
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P9725R0005/0002 is spelled out in the specs, however, is the use of this road also permitted?
A1. Yes, use of the road would be permitted. The contractor should be aware that while classified as a road both the upper and lower road are lightly maintained trails. The upper road currently supports use of an ATV / UTV and the lower road will support larger vehicles and equipment but does involve some careful navigation if more than a UTV.
Q2. While working on these types of projects, FLC typically plans on working a full 12 hr per day schedule to get this project completed in a timely and efficient manner. Do you believe that this schedule will be an issue?
A2. The NPS would be flexible and support alternative work schedules to include 12-hour workdays and schedules that include weekends and holidays as long as we are notified with enough time to staff / plan accordingly.
Q3. The existing incinerator circuit. Is the intent to locate and complete the circuit to the new disconnect on pole 4a?
A3. Correct. The existing line to the incinerator was tied to the service connection on pole 4a as well as the provision for disconnect and auxiliary power inlet.
Q4. Is there any type of specification for the type of anchor to install on the 35-5 pole?
A4. Specifications to meet relevant code requirements. If they have a more focused question I would be happy to try and provide additional detail.
Vendors may schedule a site visit by contacting the following park POC:
Chad Billock (Facility Manager)
Gates of the Arctic National Park and Preserve
Yukon-Charley Rivers National Preserve
Email: chad_a_billock@nps.gov
Office: (907)455-0621
Period of Performance: 07/21/2025 to 08/31/2026
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110