140P8321Q0054 Slip Lining Project Q&A Amendment 2 Spring Canyon Campground, Lake Roosevelt NRA (LARO
Question (Q) and Answers (A) received on/before 08/30/2021
NOTE: For the remaining period, we will accept and answer questions only if they have a profound impact on pricing or project execution.
Q1. I was wondering about the two 6" Sewer line Dig ups. Do you have photos of the two dig up locations and if you had a depth of where they would be. I noticed on the southern loop Pipes were pretty deep and if in that location I would need shoring and all that for that depth.
A1: The point repair dig up locations have not been identified. This was put into the solicitation with the expectation that at least two places of the lines would need to be repaired that will be identified by the initial inspection of each line when the selected contractor begins the work.