Amend_2_QandA_on-before_08302021_0002.pdf

PDF 101 KB Posted

Attached to
Amendmen 0002 SLIP LINING PROJECT AT LARO
Solicitation number
140P8321Q0054
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P8321Q0054 Slip Lining Project Q&A Amendment 2 Spring Canyon Campground, Lake Roosevelt NRA (LARO

Question (Q) and Answers (A) received on/before 08/30/2021

NOTE: For the remaining period, we will accept and answer questions only if they have a profound impact on pricing or project execution.

Q1. I was wondering about the two 6" Sewer line Dig ups. Do you have photos of the two dig up locations and if you had a depth of where they would be. I noticed on the southern loop Pipes were pretty deep and if in that location I would need shoring and all that for that depth.

A1: The point repair dig up locations have not been identified. This was put into the solicitation with the expectation that at least two places of the lines would need to be repaired that will be identified by the initial inspection of each line when the selected contractor begins the work.

File details come from the government source that posted it. Updated .