B09_Solicitation_Amendment_3_Attach_1_Clarity_on_Diversion_Box_0003.pdf
PDF 149 KB Posted
- Attached to
- THRO LIFT STATION Construction Project Federal contract opportunity
- Solicitation number
- 140P6325B0003
About this file
This document is a clarification memorandum for the Theodore Roosevelt National Park Lift Station Project, specifically addressing details about a custom diversion box for the drain field. The diversion box is specified to be constructed using 4500 psi concrete, with dimensions and penetrations as shown in project plans, and referenced under specification 33 05 16 for material requirements and details. An example from Oldcastle is noted as a similar reference, and the document emphasizes that the diversion box must be built precisely according to the provided plans. The memorandum is signed by Contractor Officer Joseph Kirk, with a digital signature dated May 15, 2025.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Solicitation_Amendment_3_Attach_2_Oldcastle_example_0003.pdf | ||
| Sol_140P6325B0003_Amd_0003.pdf | ||
| Sol_140P6325B0003_Amd_0002.pdf | ||
| Sol_140P6325B0003_Amd_0001.pdf | ||
| B09_Solicitation_Amendment_Attach_1_Questions_and_Answer_0001.pdf | ||
| Sol_140P6325B0003.pdf | ||
| B08_Solicitatoin_Attach_5_Drawings_013125_-.pdf | ||
| B08_Solicitation_Attach_3_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| B08_Solicitatoin_Attach_1__Specifications_013125_-.pdf | ||
| B08_Solicitation_Attach_2_Specifications_Submittal_List_013125_.xls | XLS spreadsheet | |
| B08_Solicitation_Attach_7__Specifications_Septic_Flow_Calculations_102824_-_Copy.pdf | ||
| B08_Solicitation_Attach_4_Wage_Determination.pdf | ||
| B08_Solicitation_attach_6_Bid_Schedule.xlsx | XLSX spreadsheet |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Theodore Roosevelt National Park Lift Station Project
Clarity on Diversion Box for Drain Field.
The diversion box it was designed to be a custom concrete box with the dimensions and penetrations as shown in the plans built with 4500 psi concrete per the plan note. This structure would fall under and reference specification 33 05 16 for further material requirements and details.
It is similar to the attached from Oldcastle
See attachment for the example.
The Diversion box is a custom concrete box. Needs to be built per plan.
Contractor Officer Joseph kirk
| 2025-05-15T17:49:48-0600 | |
| JOSEPH KIRK |