B08 Solicitation Attch 7 (Q and A PULL Window Washing_4Apr22).pdf
PDF 69 KB Posted
- Attached to
- PULLMAN NATIONAL MONUMENT WINDOW WASHING SERVICES Federal contract opportunity
- Solicitation number
- 140P6222Q0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A04_SOW_(PULL_Window_Washing)_Amended_12Apr22_0003.pdf | ||
| Q_A_PULL_Window_Washing_v2_12Apr22_0003.pdf | ||
| Sol_140P6222Q0002_Amd_0003.pdf | ||
| Sol_140P6222Q0002_Amd_0002.pdf | ||
| Sol_140P6222Q0002_Amd_0001.pdf | ||
| B08_Solicitation_Attch_3_(Wage_Determination_2015_5017).pdf | ||
| B08_Solicitation_Attch_1_(SOW).pdf | ||
| B08_Attch_6_(Price_Schedule)_.xlsx | XLSX spreadsheet | |
| B08_Solicitation_Attch_5_(SOW_Map).pdf | ||
| B08_Solicitation_Attch_4_SOW_PULL_window_asbuilts.pdf | ||
| Sol_140P6222Q0002.pdf | ||
| B08_Solicitation_Attch_2_(Experience_Questionnaire).pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. The scope of work indicated that the windows would be cleaned inside and out….to include the storm windows if equipped. It also indicated that the windows with screens would need to be cleaned as well. Could we have this verified? (Verify inside of windows do/do not need to be cleaned as well). Windows should be cleaned inside and out
2. In terms of cleaning the inside windows…if required…is the staff going to be responsible for removing the coverings from the windows that we might have access to clean them? Unclear what coverings are being referred to. Only coverings are motorized shades which can be raised and lowered by the push of a button.
3. For the 10-day service period, is the facility going to be closed to the public? No If not, are we going to have to tape off areas that the contractors will work in? Yes The normal hours of operation are 9 am to 5 pm 7 days a week…which include the same times listed under section
3.3.2 (Work Schedule); Monday thru Friday.
4. SF Form 1449 indicated that there would be no official site visit, but that the building would be accessible for viewing of the work site. Can a different time be scheduled to view the second and third floor areas? Solicitation has been amended to include an official site visit, scheduled for 11 April 2022 at 10:00 am CST. Interested parties should meet at the Pullman National Monument Visitors Center lobby no later than 9:50 am CST.
5. Will there be an extension on the bids since there appears to be contradictions between the staff on site and the scope submitted to the contracting office. The cost is different is we only clean the outside vs. both the outside and inside of windows.
This solicitation deadline has been extended until 18 April 2022 @ 2:00 pm CST due to the addition of the site visit.