1. Are there drawings from the old system available? See attached.
2. Are there pictures of the system available? See attached.
3. Is there conduit from all exhibits to the control room that can be utilized for new wiring? Yes, should be able to utilize.
4. If no conduit is available, how will cable need to be run? Surface mount, wiremold, etc... There are some cable runs sitting on top of HVAC.
5. If cable needs to be run in the rafter area, will a lift be required for this? If so, what is the ceiling height? Yes, lift will be required to reach the projector location in the gymnasium and top of cabling above it. Approx. 22' in the gymnasium, other projectors should not require a lift.
6. III. A. b. Asks for an electronic scissor lift to install the projector. To be clear, does the projector need a lift, or will the installation work require a lift to reach the projector location? Installation work will require lift to reach the projector location in the gymnasium and top of cabling above it. Other projectors should not require a lift.
7. Can you verify the ceiling height for the projectors? Approx 22' in the gymnasium, other areas up to 12'.
8. Does all the audio go through one audio processor, or does the media player audio go directly to the amp/speakers? Currently to amp/speakers, but new system might require processor.
Additionally, we do have access to the existing programming code.
9. Do they have drawings of the other exhibits as well? We have other drawings, but they are more of a general layout of the building rather than exhibit specs, so I don’t think they would provide any more detail to the exhibits.
10. Do they have drawings of the other exhibits as well? We have other drawings, but they are more of a general layout of the building rather than exhibit specs, so I don’t think they would provide any more detail to the exhibits.