This document contains answers to questions from a site visit for the Monroe School HVAC Upgrade federal contract opportunity numbered 140P6022R0003. Key details include that the roof does not have a warranty, cranes can be parked on the north grass lot with material under the wheels to spread load and avoid ruts, the elevator should be used to access the basement, work can take place during normal hours unless pre-arranged, the building will remain occupied during construction, and ladders accessing the roof can be removed and later reinstalled. Shutdowns of the building will need to be pre-arranged and occur after hours. Insulation specifications are referenced in an attached document. The opportunity is for the Monroe School HVAC Upgrade through the Department of the Interior National Park Service Midwest Region.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BRVB - Monroe School HVAC Upgrade 36324 - 140P6022R0003 Site Visit Questions and Answers

1. Who has the roof warranty.

NO WARRANTY

2. Would we be able to park a crane on the grass lot to the north to get the units in and out of the attic?

YES, WITH MATERIAL UNDER WHEELS TO SPREAD LOAD OF CRANE TO AVOID DEEP RUTS

3. Is there a specific entrance/exit you would like us to use to get the HP in/out of the basement?

ELEVATOR

4. Will all this work take place during normal working hours?

YES - UNLESS PRE-ARRANGED

5. Will the building be occupied during construction?

YES

6. Are we able to remove those ladders going to the roof? We might need more space to move things around in the attic.

YES, WITH LADDERS REINSTALLED AS EXIST

7. If we have to do a shutdown of the building will it need to be after hours?

YES - PRE-ARRANGE WITH COTR

8. Is there an insulation spec you can provide?

SEE BELOW FOR INSULATION SPECIFICAITON