This document is a Statement of Work for the emergency replacement of the air chillers on the Motor Vessel Fort Jefferson, which is a 110' supply ship servicing the Dry Tortugas National Park. The vessel is berthed in Key West, Florida and the work must be performed by a Dometic-qualified contractor located in the Florida Keys.

The Statement of Work requires the contractor to remove and dispose of the existing 2 chillers, control panel, pumps, and related components, and to provide and install 3 new Dometic 230V 3-phase VARX72 chillers along with a new control panel, pumps, and other necessary components. All work must be performed in a manner approved by Dometic and will be subject to inspection by a government representative who will remain on-site during the performance of the work.

View the file

Other files

File Type Posted
Questions_and_Answers_0002.pdf PDF
Sol_140P5424Q0065_Amd_0002.pdf PDF
Photos_0001.pdf PDF
Sol_140P5424Q0065_Amd_0001.pdf PDF
Sol_140P5424Q0065.pdf PDF
SCA_Wage_Rates.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NPS M/V FORT JEFFERSON

Ships AC Chiller Emergency Replacement, Scope of Work:

MV Fort Jefferson (MVFJ)

MVFJ is a 110’ Supply ship servicing the Dry Tortugas National Park. She was built in 2004 in Morgan City LA, by Swiftships. All aluminum hull, powered by triple Caterpillar 3412 mains.

MVFJ is berthed at US Coast Guard Base in Key West FL and transits 70 nm to the Dry Tortugas.

Vessel is in saltwater conditions and open seas. MVFJ also serves as a research vessel. She will berth up to 8 researchers from various scientific fields in support of Dry Tortugas National Park. MVFJs air handlers were upgraded in cyclic shipyard project 2023.

Presently MVFJs Air Chillers have suffered catastrophic failure. They will need to be replaced by an authorized local Dometic dealer. They must be Dometic brand to complete the full capacity of the already existing Dometic air handlers.

Work on Chiller System be complying and compatible with existing Dometic air handlers. Dometic, equipment replacements must be performed by Dometic Qualified Technicians. Work to be preformed at the berthing of the MVFJ in Key West FL, 100 Trumbo Road, Key West, Florida 33040.

Work to be performed as follows:

Remove & dispose of existing:

• 2 Chillers

• Control Panel

• Pump switch

• Saltwater pump

• Circulating pump

Provide and install:

• Dometic 230 V 3 Phase, VARX72 Chiller, qty 3

• Chiller Base

• Control Panel

• Platinum package

• Pump Switch 3 ph.

• Saltwater pump P100M-1171D-375-1T,

• Circulating Water Pump P100M-1171D-400-1 1/2 T

All work shall be accomplished by the vendor’s own work force in a manner approved by Dometic Contractor must be located or have satellite facility within the Florida Keys.

Contractor shall permit inspection of work in progress at any time during normal working hours by the Contracting Officer or his/her representative. A government representative will remain on site during the performance of the work.