Amendment0006_0006.pdf

PDF 65 KB Posted

Attached to
INDE - IDS ALARM REPLACEMENT Federal contract opportunity
Solicitation number
140P4323Q0073
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This document contains questions and answers regarding Amendment 0006 to Solicitation 140P4323Q0073 for an INDE Alarm Replacement for the Department of the Interior National Park Service Northeast Region. The amendment provides clarification that the number of alarm panels is 20, with Pemberton and New Hall controlled by the same panel. It also requests that bidders provide optional expansion modules and associated costs if recommended, as well as keypad access if needed for functionality. The contractor will be responsible for passing a Tier 1 background check by NPS, and the service maintenance agreement covers only the 20 installed panels for the duration of the purchase order awarded. Replacement devices should be provided if existing ones are incompatible with existing zones/alarms.

View the file

Other files for this federal contract opportunity

Other files attached to INDE - IDS ALARM REPLACEMENT, newest first.
File Type Posted
Sol_140P4323Q0073_Amd_0006.pdf PDF
Sol_140P4323Q0073_Amd_0005.pdf PDF
Amd0004_0004.pdf PDF
A05_INDE_IDS_PWS-Amd4_0004.pdf PDF
Sol_140P4323Q0073_Amd_0004.pdf PDF
Amd0003_0003.pdf PDF
Sol_140P4323Q0073_Amd_0003.pdf PDF
PPIs-Amd0002_0002.pdf PDF
Sol_140P4323Q0073_Amd_0002.pdf PDF
Sol_140P4323Q0073_Amd_0001.pdf PDF
A05_INDE_IDS_PWS_0001.pdf PDF
A05_INDE_IDS_PWS.docx DOCX document
B03_WD_INDE_2015-4233_Rev27_6_30_23.pdf PDF
Sol_140P4323Q0073.pdf PDF
A06_INDE_MAP_Panel_Locations.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDE Alarm Replacement 140P4323Q0073 Amendment 0006

Questions 43 - 48

43. The number of panels is 20. The breakout of zones in Amendment-0004, PDF page 6 has Pemberton

& New Hall separated, they are controlled by the same panel.

44. If additional expansion modules are recommended to be provided - please include as an option with a cost separated.

45. Include keypad access if it's recommended and will not function otherwise.

46. The contractor will be responsible for passing the Tier 1 background check initiated by NPS.

47. The Service Maintenance Agreement will cover only the 20 panels that are to be installed by the contractor for the duration of the purchase order awarded for this requirement.

48. Yes, if the existing devices do not work with the existing zone/alarms, provide a change order for replacement.