140P4224Q0029_Q___A_0001.docx

DOCX document 14 KB Posted

Attached to
FIRE SUPPRESSION REPAIRS AT NEW RIVER GORGE NATION
Solicitation number
140P4224Q0029
Issued by

About this file

This document contains questions and answers related to Solicitation 140P4224Q0029 for fire sprinkler repairs at New River Gorge National Park and Preserve. The contractor has requested an extension to the 10-day period of performance due to lead times for ordering dry pendent sprinkler heads and other equipment. The agency has agreed to extend the period of performance to 45 days. The contractor is responsible for the wiring and connection of the new air compressor. The agency has indicated that an additional site visit can be arranged by contacting the designated point of contact. The solicitation is for fire suppression repairs at the New River Gorge National Park and Preserve, with the Department of the Interior National Park Service Northeast Region as the procuring agency.

View the file

Other files

File Type Posted
140P4224Q0029_Q___A_I_0002.docx DOCX document
Sol_140P4224Q0029_Amd_0002.pdf PDF
Statement_of_Work_-_Fire_Suppression_Repairs_0001.docx DOCX document
Sol_140P4224Q0029_Amd_0001.pdf PDF
Price_Schedule.docx DOCX document
Statement_of_Work_-_Fire_Suppression_Repairs.docx DOCX document
Sol_140P4224Q0029.pdf PDF
Wage_Determination_WD_15-4295_Rev_23_Fayette_County.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P4224Q0029 Fire Sprinkler Repairs at New River Gorge National Park and Preserve

Contractor Questions

1. Our subcontractor responsible for the work has indicated that the 10-day completion timeline is unfeasible due to the following reasons:

The dry pendent sprinkler heads will need to be measured and ordered. Dry pendent sprinkler heads are made to order and can take up to 3 weeks for time of order.

The dry valves and air compressor will take a week or two to receive once they are ordered.

Is there a possibility to extend the period of performance?

Answer: The Period of Performance has been extended to 45 days

2. We would also like to clarify who is responsible for the wiring associated with the disconnection/reconnection of the air compressor.

Answer: The contractor is responsible for the wiring and connection of the compressor.

Per the Statement of Work, “The contractor shall install the replacement compressor in the same location as the existing compressor and connect the new unit to the copper airline that is routed to the dry valve.”

3. Is there an opportunity to arrange another site visit?

Answer: Please contact Matthew Ibbetson at 304-719-7744 to set up a site visit ASAP.