This statement of work outlines requirements for a roof replacement project at the National Wildlife Health Center in Madison, Wisconsin. The contractor will be responsible for replacing the roof on the main building, estimated at 33,028 square feet, and overlaying a new roof system on the modular office building, estimated at 2,000 square feet. The main building roof is a single-ply EPDM system with stone ballast that was installed in 2002 and requires full replacement. The modular office building has a leaking metal roof that will receive an overlay. The contractor must remove and dispose of existing roofing materials, inspect for leaks, and install new roofing systems with tapered insulation, cover boards, PVC membranes, edge metal, copings and flashings. The work must be completed within 90 calendar days and is solicited under opportunity number 140G0221R0013 by the U.S. Geological Survey.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Roof_Decks_0003.pdf | ||
| Sol_140G0221R0013_Amd_0003.pdf | ||
| A-4_Detail2_0002.pdf | ||
| A-3_DETAILSwithnewexjoint_0002.pdf | ||
| A-3_DETAILS_0002.pdf | ||
| A2-ROOF_PLAN-July_0002.pdf | ||
| A-5_spec_0002.pdf | ||
| Sol_140G0221R0013_Amd_0002.pdf | ||
| NWHC_Roof_Replacement_Questions_Responses_2_0002.docx | DOCX document | |
| Site_Visit_Sign-In_Sheet_0001.pdf | ||
| Attachment_8_-_Roof_Section_Drawings_0001.pdf | ||
| Sol_140G0221R0013_Amd_0001.pdf | ||
| NWHC_Roof_Replacement_Questions_Responses_0001.docx | DOCX document | |
| Attachment_7_-_COVID19_Non-Employee_Checklist_20200603_v1_LD19.pdf | ||
| Attachment_6_-_SF1413-13e.pdf | ||
| Attachment_5_-_Release_of_Claims.pdf | ||
| Sol_140G0221R0013.pdf | ||
| Attachment_4_-_Certified_Payroll_Form.pdf | ||
| Attachment_2_-_MFB_Roof_Pictures.doc | DOC document | |
| Attachment_3_-_Wage_Determinations_070921.pdf | ||
| Attachment_1_-_NWHC_MFB_Roof_Replacement-SOW-FINAL.docx | DOCX document |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Main Building Roof Replacement and Modular Office Building Roof Overlay
GENERAL: The United States Geological Survey (USGS) has a requirement for roofing services at the National Wildlife Health Center (NWHC) located at 6006 Schroeder Road Madison, WI 53711.
BACKGROUND: The NWHC was established in 1975 to serve the nation and its natural resources by providing sound science and technical support regarding wildlife disease, and to disseminate information to promote science-based decisions affecting wildlife and ecosystem health. NWHC personnel study emerging and resurging diseases, wildlife and ecosystem health, zoonotic diseases, and environmental health and degradation. The NWHC is located on 24 acres and maintains offices and high security disease laboratories in the Main Building (MB) and the Tight Isolation Building (TIB). This request is for replacement of the roof for the Main Building (MB) and overlaying a new roof on the Modular Office Building (MOB).
WORK TO BE PERFORMED BY CONTRACTOR: The contractor shall provide all labor, materials, supervision, supplies, tools, equipment, and transportation, to complete the project.
DESCRIPTION: Contractor shall perform the following:
Roofing The Main Building roof is a single-ply insulated EPDM system with a stone ballast covering. The roof is a replacement system installed in 2002. Roof access is by an internal hatch. Roof drainage is accomplished by tapered insulation sloped towards internal roof drains. There are no overflow scuppers on the high roof, only gravel stops in some areas. The lower roofs over the loading dock area and the incinerator are provided with gravel stop perimeters and scuppers with downspouts as a means of drainage. A small section of roofing membrane has become detached from the substrate along the north side at the gravel stop. This area should be repaired. Concrete paver walkways are installed. A decorative weathering steel screen is installed around the majority of the centrally located mechanical equipment. Contractor shall inspect and repair any leaks that might be coming through the brink at the stack enclosure near the roof hatch. Dark stains have been showing up inside the building on the wall adjacent to the roof ladder at the roof hatch.. The roof contains prefinished coping and edge metal. The paint finish on the incinerator stack at the southeast corner of the roof is faded and the stack is rusting. The Modular Office Building roof has a metal roof which leaks during heavy rain and spring snow melt events.
A. Scope The purpose of this requirement is to remove and replace all the roofs associated with the Main Building (roof estimated area is approximately 33,028 sf) and overlay new roof system on Modular Office Building (roof estimated area is approximately 2,000 sf). The brick section needs partial/full demolition and rebuild to prevent leaking and roof hatch may need replaced. The incinerator stack should have rust removed and repainted with high temperature paint (1000°F) from roof up 6 feet. Contractor shall provide a roofing system diagram that clearly details all products used in the roofing system including product thickness and how the materials are fastened or adhered.
I. Work Requirements
A. Technical Requirements for Main Building work.
Metal Roof Deck Roof Areas
1. Remove existing roof related sheet metal and dispose of off-site.
2. Remove the existing rock ballast and dispose of off-site.
3. Remove any obsolete roof penetrations and install new sheet metal roof decking or sheet metal roof deck patch as required over existing opening.
4. Remove the existing EPDM roof membrane and roof penetration/wall/edge flashings and dispose of off-site.
5. Remove all existing insulation and install new insulation.
6. Main Roof Only - Furnish and install new ½”/ft slope tapered insulation saddle between the roof drains on inside the equipment screens to facilitate drainage from the low roof areas.
7. Furnish and install new mechanically attached ½” high density polyisocyanurate cover board over existing tapered insulation.
8. Furnish and install new fully adhered 60 mil PVC roofing membrane with all associated roof wall/penetration/edge flashings.
9. Furnish and install new pressure sensitive PVC walkway pads to closely match the existing paver configuration.
10. Furnish and install new 24 ga prefinished roof related edge metal, copings, counter flashings as required.
11. Remove existing roof hatch and install new roof hatch to match.
12. Remove roof fans (U-5 and U-14), provide to customer and cap/seal any penetrations (photos attached).
13. Replace 5, JOSAM #21024 cast iron roof drains.
14. Replace rigid roof insulation, follow manufacture's recommendation, and code compliance for thickness and insulation rating.
15. Install fiber recovery board, follow manufacture's recommendation, and code compliance for thickness and insulation rating.
16. Add external roof access (e.g. metal outdoor staircase system).
a. Commercial heavy-duty galvanized outdoor construction
b. Minimum 48” stair width and tread depths are 12" deep diamond plate
c. Minimum landing dimensions 48” x 48”
d. Securable access at the ground level
e. Locate on north side of Main Building
f. Must be OSHA and IBC compliant
17. Includes roof manufacturer’s equal to or greater than a 20-year total system warranty. Includes equal to or greater than 2-year installation and workmanship warranty
Precast Plank Roof Deck Roof Areas
1. Remove existing roof related sheet metal and dispose of off-site.
2. Remove the existing rock ballast and dispose of off-site.
3. Remove any obsolete roof penetrations and install new sheet metal roof decking or sheet metal roof deck patch as required over existing opening.
4. Remove the existing EPDM roof membrane and roof insulation down to the existing roof deck and remove all roof penetration/wall/edge flashings and dispose of off-site.
5. Furnish and install new fully adhered ¼”/ft slope tapered polyisocyanurate insulation (Min R-Value=24) to slope to roof scuppers.
6. Furnish and install new fully adhered 60 mil PVC roofing membrane with all associated roof wall/ penetration/edge flashings.
7. Furnish and install new pressure sensitive PVC walkway pads to closely match the existing paver configuration.
8. Furnish and install new 24 ga prefinished roof related edge metal, copings, counter flashings as required.
9. Includes roof manufacturer’s equal to or greater than a 20-year total system warranty. Includes equal to or greater than a 2-year installation and workmanship warranty.
10. Remove rust from incinerator stack prep and paint with high temperature paint from roof up 6 feet.
MOB metal roof overlay
1. Mechanically fasten 1# density flute fill expanded polystyrene insulation board over the metal roof.
2. Install 1/2" high density insulation board over the metal roof.
3. Install fully adhered 60 mil PVC rubber membrane in accordance with manufacturer's recommendations and specifications.
4. Install new 24 gauge galvanized metal edging.
5. All roof top penetrations to be flashed and sealed as per manufacturer's details.
6. All debris from roofing operation will be removed from owner's premises.
7. Manufacturer’s fifteen-year warranty.
B. Requirements for Pricing:
Contractor shall include a price breakdown into the following categories. USGS may select only part of this requirement based on availability of funds.
Metal Roof Deck Roof Areas
1. Roof system demolition and install on all Metal Roof Deck Roof Areas;
Precast Plank Roof Deck Roof Areas
2. Roof system demolition and install on all Precast Plank Roof Deck Roof Areas;
MOB Metal Roof Overlay
3. Install over existing Metal Roof;
NOTES:
· All local, state, and federal environmental and safety requirements shall be met and are the responsibility of the contractor.
· All outdoor equipment shall be rated for outdoor use.
· All equipment shall be installed in accordance with manufacturer's instructions.
· Contractor shall coordinate the work with the facility to prevent interruption to ongoing research. This will be accomplished through the use and approval of the contractor's work schedule. Gate is the only vehicle access to NWHC property and must allow ingress and egress of staff and deliveries during the work process
TECHNICAL REPRESENTATIVE (TR): Darren Berger (608) 270-2407 or (608) 212-5388
CODE COMPLIANCE: All work shall comply with all current governing specifications, including, but not limited to: NFPA, NEC, BOCA National Building codes, and OSHA standards.
ADMINISTRATIVE PROCEDURES: After award and issuance of the Notice to Proceed, all site visits shall be coordinated through the TR at the NWHC.
Contractor shall not proceed with any work until approval of schedule, process, submittal list and materials are made by the TR and a Notice to Proceed has been issued by the Contracting Officer (CO).
TIME AND PERIOD OF PERFORMANCE: All Contractor employees shall follow the NWHC visitor sign-in procedures. The Contractor shall employ sufficient personnel and equipment to accomplish the work of this contract within (90) thirty calendar days of the Notice to Proceed.
Work shall occur during normal work hours, M-F 7:00 am to 3:30 pm. Requests to work outside normal working hours shall be made in writing. Any work that needs to be performed after hours and during weekends will be done at no additional cost to the government.
SAFETY AND ENVIRONMENTAL:
· On-site personnel shall stop work and notify the TR immediately for any safety or environmental violation.
· Contractor shall have all protective equipment necessary to proceed and shall take all necessary precautions and measures to prevent injuries to anyone working in or entering the facilities.
· Contractor shall take all necessary measures and precautions to control, protect, and avoid damage to or loss of any property on the work site.
· Contractor operations shall be conducted in a safe and professional manner.
· Contractor shall submit immediate notification and information concerning any accidents and incidents to the TR. Detailed reports of all accidents or incidents shall be reported in writing within one week of occurrence to the TR. Contractor shall provide OSHA Form 300, A Summary of Work-Related Injuries and Illnesses pertaining to their work to the TR.
· CDC guidelines and Federal compliance for Covid 19 while on federal property
DEMOLITION: The Contractor shall schedule all demolition with the TR prior to starting. The Contractor shall remove all old material and legally dispose of it. The contractor to provide transportation and disposal documents to the TR.
MECHANICAL: The Contractor shall complete all work to meet Federal, State and Local codes.
ELECTRICAL AND LIGHTING: Contractor shall comply with all applicable Occupational Safety and Health Administration (OSHA) standards, as well as electrical requirements listed in National Fire Protection Association (NFPA) regulations and meet Federal, State and Local codes.
MEASUREMENTS: It is the responsibility of the Contractor to field verify all measurements & quantities. All work listed shall be coordinated with the TR.
PERMISSION FOR WELDING, CUTTING, AND BURNING: Prior to performing any welding, cutting, burning, soldering, or other process using torch or flame, or any type of demolition or construction that may produce sparks or create dust, the Contractor shall obtain written permission from the on-site TR to perform these operations within the NWHC and at location on the NWHC grounds. This work shall meet or exceed OSHA regulations.
OUTAGES AND INTERRUPTIONS: The facility will continue normal operations during the performance of the contract. The Contractor shall notify the TR one week in advance if it becomes necessary to interrupt any function at the NWHC. Any work that requires shutting down of a facility system, such as mechanical, electrical, etc., shall be planned for early morning or late afternoon to the maximum extent possible, to minimize the impact on the facility’s operation. Work shall be performed when the demands on the system best permit, even to the extent of working outside of normal working hours at no additional cost to the government.
ORGANIZATION AT THE SITE: The Contractor shall exercise care and shall perform all work in a diligent and professional manner. The Contractor shall take all necessary measures required to ensure a clean, safe environment for the Contractor’s work force, NWHC personnel and the general public for the duration of this project. Contractor parking will be in the gravel parking lot. The Contractor shall utilize the areas only within the project limits to perform work and for the storage of equipment, materials and trailers during the life of the contract. The contractor shall not stage any materials on any grassed areas. Storage will be confined to areas approved by the TR. The Contractor shall be responsible for the security of all tools, materials and equipment.
The Contractor shall be responsible for making all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or to sign for items delivered to the site.
The TR shall designate areas where the Contractor can store or place materials and equipment for short-term storage. There is limited on-site storage space (both indoor and outdoor) for the Contractor’s equipment and materials. Storage and security of materials and equipment as required for the performance of the contract requirements is the responsibility of the Contractor.
TRANSPORTING OF DEBRIS AND MATERIAL: The Contractor shall provide all equipment necessary for transporting construction debris from the job site for proper disposal that they provide and for the stocking and transporting of materials to the job site. The Contractor shall provide estimates of type and weight of materials recycled or disposed of as trash.
ENVIRONMENTAL PROTECTION: All work shall be accomplished in such a manner that all waste materials, pollutants, and potential pollutants shall be completely retrievable for disposal in a manner suitable to the TR and in accordance with all applicable regulations and laws. At no time shall operations be attempted or permitted where or when such operations present a possibility of fouling the facility with waste materials, pollutants, or potential pollutants.
SITE CLEANLINESS:
· The Contractor shall clean up and dispose of offsite any rubbish and accumulated waste.
· The Contractor shall provide dust protection and shall maintain cleanliness of the work site by promptly removing debris, tools and excess material.
· The Contractor shall remove tools and equipment and leave the premises clean at the completion of the project. The Government will not be responsible for any lost, damaged or broken tools.
· The Contractor shall repair or otherwise return to original condition any parts of the existing facilities or grounds which become damaged as a result of the Contractor’s work, except as otherwise specified, and shall restore the site to its original condition, as approved by the TR and at no additional cost to the Government.
· There shall be no smoking in the NWHC buildings. All personnel that smoke will have to do so in the designated smoking area.
UTILITIES: The Government shall provide electricity and/or water to the contractor, only as a convenience, from existing Government sites. The Government will not provide electrical assistance if Contractor’s equipment does not conform to NWHC’s electrical system. Any long term or large capacity power supply requirements shall be provided by the Contractor. The Government shall not provide equipment (such as flatbed carts, pallet movers, forklifts or vehicles) to the Contractor. The Contractor shall provide portable restroom facilities for workers at the site.