Sol_140FS325Q0119_Amd_0001.pdf
PDF 154 KB Posted
- Attached to
- Fire Panel Replacement, Rhode Island Wildlife Refu Federal contract opportunity
- Solicitation number
- 140FS325Q0119
About this file
This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a fire alarm control panel replacement project at the RI FWS RI NWR (Rhode Island Fish and Wildlife Service National Wildlife Refuge). Amendment 0001 addresses industry concerns while maintaining the original solicitation closing date of 19 August 2025 at 2pm. The project involves replacing the existing fire alarm control panel, with flexibility for vendors to use alternative manufacturers like Fire Lite, Edwards, or Kidde, provided they are compatible with existing devices.
Key details from the Questions and Answers section include: the contractor is responsible for ensuring proper connection and testing of all building systems impacted by the fire alarm panel installation, including HVAC, elevator, and fire sprinkler systems; no government personnel will be provided to support system connections. The vendor must handle federal background clearance for building access, and while alternate work hours may be considered, government staff must be present. A new radio communicator requiring cellular communication service is part of the project, with the government willing to work with existing communication providers to add cellular communications as needed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_6-_Images_0001.pdf | ||
| Attachment_2-_Quote_Schedule.docx | DOCX document | |
| Attachment_5-_Past_Performance_Data_Document.docx | DOCX document | |
| Attachment_4-_SCA_Wage_Determintion.pdf | ||
| Attachment_1-_Performance_Work_Statement.pdf | ||
| Sol_140FS325Q0119.pdf | ||
| Attachment_3-_Fire_Inspection_Certificate.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140FS325Q0119
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
FS3
Falls Church VA 22041 5275 Leesburg Pike FWS SAT Team 3 FWS SAT Team 3
08/05/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/05/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 0001 is necessary to address concerns posed from industry. Closing remains 19
August 2025 at 2pm.
All other terms and conditions remain unchanged.
RI FWS RI NWR -Replace existing fire alarm control panel
Tech POC Brian Waz (413) 253-8605
Alt POC Karrie Schwaab (401) 782-5373
Contract POC: Fred Riley, fred_riley@fws.gov
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Fred Riley
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Questions and Answers
Question 1: There are other building systems which will be impacted by this project. We will provide the complete installation of the fire alarm system; to do so we’ll need support from your current maintenance providers of these other building systems so not to void any warranties you may have on their service work. Will you be providing your current HVAC, elevator, and fire sprinkler maintenance personnel to be on site for the final connections to their systems and test accordingly to ensure proper operation?
Answers 1: The contract is to ensure proper function and full restoration of all building functions connected to the fire panel/alarm system. The government will not be providing HVAC, elevator, or fire sprinkler personnel. Awardee will be responsible for ensuring these systems are properly connected and tested to ensure full and proper operation.
Question 2: In the scope of work document, it states to provide a Gamewell/FCI retrofit fire alarm control panel. Will you accept an alternate fire alarm system manufacturer such as Fire Lite, Edwards, or Kidde, which provides equal or greater capabilities to the Gamewell/FCI?
Answers 2: Yes, as long as it is compatible with existing devices listed in the proposal.
Question 3: Can you please provide the existing fire alarm design drawings?
Answers 3: See Attachment 6- Images
Question 4: Would the government accept performing work outside normal duty hours if it benefits the timeline of completion?
Answers 4: TBD with awardee. Federal background clearance is required for building access. If my staff can accommodate other hours we will but we will not give the vendor access to the building without staff present
Question 5: If a fire watch is required due to the building not being protected with an active fire alarm system, would the government provide the personnel to perform the fire watch?
Answers 5: Fire watch is not required.
Question 6: The new radio communicator being requested will require a cellular communication service (Verizon, At&t, or the like) plus a monitoring service. These are monthly subscription cost. How would the government like this to be priced as this solicitation is not for recurring monthly services.
Answers 6: Vendor should provide recommendations for the monitoring service if they do not provide the service and provide typical monthly cost for the subscription. The government will work with existing communication provider and IRTM department to add cellular communications as needed.
File details come from the government source that posted it. Updated .