Amend_0001_Atch_1_Example_Comissioning_0001.pdf
PDF 202 KB Posted
- Attached to
- GPNC Replace Water Heating System Federal contract opportunity
- Solicitation number
- 140F0121R0031
About this file
This submittal package includes commissioning test plans and test and balance reports for the chilled water system replacement at the Great Plains Nature Center. The submittal contains draft commissioning test plans and verification forms for the central plant chilled water equipment, including chilled water pumps, temperature control valves, chillers, and differential pressure and temperature sensors. Test and balance data sheets are also included, reporting pump and chiller data from performance tests. The submittal package was prepared according to specification section 230800 for the chilled water system replacement project at the Great Plains Nature Center in Wichita, Kansas under Solicitation 140F0121R0031 from the Department of the Interior Fish and Wildlife Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140F0121R0031_Amd_0002.pdf | ||
| Sol_140F0121R0031_Amd_0001.pdf | ||
| Atch 4 GPNC Water Heating System DBA Det Wage Rate.pdf | ||
| Sol_140F0121R0031.pdf | ||
| Atch 3 GPNC Water Heating System Submittal List.pdf | ||
| Atch 2 GPNC Heating Water System Drawings.pdf | ||
| Atch 5 GPNC Water Heating System Past Perf Quest.doc | DOC document | |
| Atch 1 GPNC Heating Water System Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. FISH & WILDLIFE SERVICE
Mountain-Prairie Region 6
TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL, SAMPLES,
MANUFACTURER’S CERTIFICATES OF COMPLIANCE FOR REVIEW.
ONLY ONE SPECIFICATION SECTION NUMBER ALLOWED PER SUBMITTAL TRANSMITTAL.
Date Submittal No.
11/11/2020 010
Section I (Contractor) CONTRACTOR SHALL EXPLICITLY INDICATE ANY REQUESTED DEVIATIONS OR SUBSTITUTIONS FROM THE CONTRACT REQUIRMENTS.
To: From:
Previously Submitted on Transmittal No._N/A_________ Ann Erin Mercer
US Fish & Wildlife Service Project Manager Region 6-Division of Engineering 134 Union Blvd., Lakewood, CO P: 303.236.7917
Emilio Gonzalez / Senior Engineer 4600 East Washington Street Suite 600 Phoenix, Arizona P: 480-286-8417 E: Emilio.gonzalez@woodplc.com
Contract No.:
Project and Location:
Chilled Water System Replacement Great Plains Nature Center 6232 East 29th St N #2200 Wichita, KS 67220
It e m
N o
Description (Include Brand or Manufacturer’s Name)
Identify Submittal
No. of Copies
Contract Specification
Para. No.
Contract
Drawing No.
Reg’n Engr Use Only
Action Code*
1 Commissioning Test Plan and TAB Verification Form Draft Forms 1 230800.1.5
Test Reports 1 230800.1.5
Field Reports 1 230800.1.5
Name:
(Contractor Project Manager) Contractor certifies he has reviewed the plans and specifications, the submittal is in accordance with the contract documents or deviations are clearly identified; individual product characteristics and assemblies have been coordinated with actual field conditions; systems are complete; system and system components can be installed and will function as intended.
Comments: Date Received:
Reviewed By: Signature: Approving Authority: COR - COTR Date:
Action Codes:
A - Approved as Submitted B - Approved As Noted -
Resubmission Not Required
C - Revise & Resubmit - See Comments, Resubmission Required.
D – Rejected – See Comments, Resubmission Required
O - Other: __________________________ Distribution: Regional Engineer/Contract File Inspector’s File Contractor
FORM NUMBER R1-67, REVISED 10/93
Tim_Officer Cross-Out
Controls Test Plan
Project Name: Great Plains Nature Center – Chilled Water System Replacement
Wood Project Number: 3720192002
Date:
Time:
Systems Tested: Central Plant - Chilled Water
Equipment Tested: CHWP-1,2 / TCV-CH-1 EWT & LWT / TCV-1 (Bypass) / CH-1 / FMS-1
Test Participants:
Chilled Water Pumps
1. From BAS operator interface, enable CHWP-1 and confirm operation.
2. From BAS operator interface, enable CHWP-2 and confirm operation.
3. From BAS operator interface enable CHWP-1, then physically shut off CHWP-1 and,
a. Verify CHWP-2 starts.
b. Verify alarm at BAS operator interface for CHWP-1 not operational.
4. From BAS operator interface enable CHWP-2, then physically shut off CHWP-2 and,
a. Verify CHWP-1 starts.
b. Verify alarm at BAS operator interface for CHWP-2 not operational.
5. From BAS operator interface, enable CHWP-1, then physically turn on CHWP-1 and,
a. Verify alarm at BAS operator interface for CHWP-1 working in hand only.
6. From BAS operator interface, enable CHWP-2, then physically turn on CHWP-2 and,
a. Verify alarm at BAS operator interface for CHWP-2 working in hand only.
7. From BAS operator interface, enable CHWP-1 and confirm,
a. Maximum speed does not exceed maximum chiller flow rate for CH-1
8. From BAS operator interface, enable CHWP-2 and confirm,
a. Maximum speed does not exceed maximum chiller flow rate for CH-2
9. For CH-1 during scheduled occupancy, a call for cooling & outdoor temperature > 20°F confirm,
a. Minimum speed of CHWP-1 is equal to or greater than 30%.
10. For CH-1 during scheduled occupancy, a call for cooling & outdoor temperature > 20°F confirm,
a. Minimum speed of CHWP-2 is equal to or greater than 30%.
11. Upon CH-1 meeting all site demands confirm,
a. CHWP-1 remains in operation for an additional 5 minutes.
12. Upon CH-1 meeting all site demands confirm,
a. CHWP-2 remains in operation for an additional 5 minutes.
13. Physically (in hand) shut off CHWP-1 VFD and confirm,
a. CHWP-1 VFD fault alarm at BAS operator interface.
14. Physically (in hand) shut off CHWP-2 VFD and confirm,
a. CHWP-2 VFD fault alarm at BAS operator interface.
15. Verify weekly lead/lag rotation of pumps.
Temperature Control Valves
1. From BAS operator interface, enable TCV-1 (by-pass) and confirm operation.
Chiller
1. From BAS operator interface, command CH-1 on and confirm
a. Flow switches prove chilled water flow through chiller.
b. CH-1 operation.
2. From BAS operator interface, command CH-1 on, then physically (in hand) shut off CH-1 and,
a. Verify alarm at BAS operator interface.
3. Add HVAC system load and then confirm,
a. Alarm for +5°F > CH-1 supply temperature set point.
4. Reduce HVAC system load and confirm,
b. Alarm for 4°F < CH-1 supply temperature set point.
2. From BAS operator interface, command CH-1 on, then confirm,
a. Bypass valve is modulating to control the system differential pressure.
b. And maintaining minimum chiller water flow rate for the chiller.
5. Verify CH-1 Points / Alarms are mapped from Chiller Card.
Flow Meter
1. Operate CHWP-1, record flow value from FMS-1.
2. Operate CHWP-2, record flow value from FMS-1.
Verify Temperature Sensors
1. CH-1 inlets measured vs BAS operator interface.
2. CH-1 outlets measured vs BAS operator interface.
3. CH-2 inlets measured vs BAS operator interface.
4. CH-2 outlets measured vs BAS operator interface.
5. Ambient Air relative humidity.
6. Ambient Air temperature.
Differential Pressure Sensor
1. From BAS operator interface, enable CHWP-1 and confirm speed varies to,
a. Maintain system differential pressure (Adj.) so minimum flow is achieved at all equipment.
2. From BAS operator interface, enable CHWP-2 and confirm speed varies to,
a. Maintain system differential pressure (Adj.) so minimum flow is achieved at all equipment.
Issues Found / Resolved
Witnessed by (Print) Witnessed by Signature
Date
Test, Adjust and Balance (TAB)
HYDRONIC PUMP TEST SHEET
LOCATION UNIT NUMBER: CHWP-1
PUMP DATA TEST DATA READING
LOCATION SHUT OFF SUCTION PSI
SERVICE SHUT OFF DISCHARGE PSI
MANUFACTURER SHUT OFF DIFF PSI
MODEL NUMBER SHUT OFF FT HEAD
SERIAL NUMBER WIDE OPEN SUCTION PSI
MOTOR MANUFACTURER WIDE OPEN DISCHARGE PSI
NAME PLATE HP WIDE OPEN DIFF PSI
NAME PLATE MOTOR RPM WIDE OPEN FT HEAD
VOLTAGE / PHASE WIDE OPEN GPM
FL AMPS / SF BALANCED SUCTION PSI
DESIGN GPM BALANCED DISCHARGE PSI
DESIGN FT HEAD DIFFERENTIAL PSI
DESIGN IMPELLER (IN) BALANCED FT HEAD
REQ. NPSH BALANCED GPM
EFF / PF PUMP OFF PRESSURE PSI
FRAME VOLTAGE
AMPS
HERTZ
ACTUAL IMP DIA
HP / BHP
HYDRONIC PUMP TEST SHEET
LOCATION UNIT NUMBER: CHWP-2
PUMP DATA TEST DATA READING
LOCATION SHUT OFF SUCTION PSI
SERVICE SHUT OFF DISCHARGE PSI
MANUFACTURER SHUT OFF DIFF PSI
MODEL NUMBER SHUT OFF FT HEAD
SERIAL NUMBER WIDE OPEN SUCTION PSI
MOTOR MANUFACTURER WIDE OPEN DISCHARGE PSI
NAME PLATE HP WIDE OPEN DIFF PSI
NAME PLATE MOTOR RPM WIDE OPEN FT HEAD
VOLTAGE / PHASE WIDE OPEN GPM
FL AMPS / SF BALANCED SUCTION PSI
DESIGN GPM BALANCED DISCHARGE PSI
DESIGN FT HEAD DIFFERENTIAL PSI
DESIGN IMPELLER (IN) BALANCED FT HEAD
REQ. NPSH BALANCED GPM
EFF / PF PUMP OFF PRESSURE PSI
FRAME VOLTAGE
AMPS
HERTZ
ACTUAL IMP DIA
HP / BHP
CHILLER DATA (CH-1)
UNIT NUMBER
LOCATION
SERVICE
MANUFACTURER
MODEL NUMBER
SERIAL NUMBER
TONS
ELECTRICAL
VOLTAGE
R.L.A.
% LOADED
PERFORMANCE DATA
EVAPORATOR DESIGN ACTUAL
GPM
ΔP FT
ENT WATER TEMP ˚F
LVG WATER TEMP ˚F
CONDITIONS DESIGN ACTUAL
OUTSIDE AIR DB ˚F
OUTSIDE AIR WB ˚F
| Submittal T10 Cover Sheet.pdf (p.1) |
| 1b - Great Plains - Ctrl Plant Crtrls Check.pdf (p.2-3) |
| 1b - Great Plains - Cx - TAB1.pdf (p.4) |
| 1b - Great Plains - Cx - TAB2.pdf (p.5) |
| 1b - Great Plains - Cx - TAB3.pdf (p.6) |