Main Engine Exhaust Repair aboard NOAA ship RAINI
Solicitation number
1333MK26Q0064
Issued by

About this file

This is a Statement of Work (SOW) for main engine exhaust repair services on the NOAA Ship Rainier, contract number 140802-26-0342.

The scope of work encompasses the replacement of port and starboard main engine exhaust expansion joint gaskets and insulation. For the port main engine, the contractor must install scaffolding, disconnect inlet and outlet flanges of the expansion joint, remove and inspect gaskets and sealing surfaces, reassemble joints with new gaskets (14-inch nominal pipe size), and fabricate and install new exhaust blankets from the expansion inlet joint to the first 90-degree elbow using ASTM F683 or equivalent fire blanket material with stainless steel wire and hooks. For the starboard main engine, similar work applies with the additional requirement to disconnect and reassemble the 90-degree elbow and expansion joints, with exhaust blankets extending from the 90-degree elbow on top of the engine to the outlet side expansion joint elbow. The contractor must have access or temporary access eligibility to the NOAA Marine Center – Pacific Islands at Pearl Harbor Naval Base, coordinating with the Joint Base Pearl Harbor Hickam Pass & ID office. Quality assurance requires coordinating engine operation to verify no exhaust leaks at disturbed joints and providing insulation manufacturer product data sheets to the port engineer. The period of performance begins April 29, 2026 with an end date to be determined. Work will be performed at Marine Operations Center – Pacific Islands, NOAA Ship Rainier, 1897 Ranger Loop, Ford Island, Honolulu, Hawaii 96818. The point of contact is Dale Morrison, Port Engineer, reachable at (541) 351-4634 office or (757) 777-5448 cell.

View the file

Other files

File Type Posted
Sol_1333MK26Q0064.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Main Engine Exhaust Repair – NOAA Ship Rainier

140802-26-0342

1. Main Engine Exhaust Repair

1.1. Scope:

1.1.1. Replace port main engine exhaust expansion joint gaskets and insulation.

1.1.2. Replace starboard main engine exhaust expansion joint

gaskets and insulation.

1.2. Requirements:

1.2.1. Contractor must have access or is eligible for temporary access to NOAA Marine Center – Pacific Islands @ Pearl Harbor Naval Base.

a. If access is required coordinate time and date with the Port Engineer access at the Joint Base Pearl Harbor Hickam Joint Base Pass & ID office.

1.2.2. Provide labor and materials to repair the following:

a. Port Main Engine Exhaust (see Figure 1):

1. Install scaffolding as necessary to access the expansion joint.

2. Disconnect the inlet and outlet flanges of the expansion joint.

3. Remove the gaskets and inspect the sealing surfaces.

4. Reassemble the expansion inlet and outlet joints with new gaskets. Flange nominal pipe size is 14”

5. Fabricate and install new exhaust blankets from the expansion inlet joint to the 1st 90o elbow. Insulation to be ASTM F683 or equivalent fire blanket with stainless steel wire & hooks. Nominal pipe size is 14”.

b. Starboard Main Engine Exhaust (see Figure 2):

1. Install scaffolding as necessary to access the expansion joint.

2. Disconnect the inlet and outlet flanges of the 90o elbow and the expansion joint.

3. Remove the gaskets and inspect the sealing surfaces.

4. Reassemble the elbow and expansion inlet and outlet joints with new gaskets. Flange nominal pipe size is 14”

140802-26-0342

5. Fabricate and install new exhaust blankets from the

90o elbow on top of the engine to the 90o elbow on the outlet side of the expansion joint. Insulation to be ASTM F683 or equivalent fire blanket with stainless steel wire & hooks. Nominal pipe size is 14”.

1.3. Quality Assurance:

1.3.1. Coordinate running the engines to verify no exhaust leaks at the disturbed joints.

1.3.2. Provide insulation manufacturer’s product data sheets to the port engineer.

1.4. Period of Performance:

4/29/2026 - TBD

1.5. Place of Performance:

Marine Operations Center - Pacific Islands NOAA ship RAINER 1897 Ranger Loop Ford Island Honolulu, HI 96818

1.6. Point of Contact:

Dale Morrison Port Engineer NOAA ship RAINIER Office: (541) 351-4634 Cell: (757) 777-5448

End of Item

140802-26-0342

Figure 1: Port Main Engine

Figure 2: Starboard Main Engine