Amendment_0001.pdf

PDF 330 KB Posted

Attached to
OMAO Small Boat Recapitalization and Sustainability Plan
Solicitation number
1305M219QNMAN0358
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
Amendment_0002.pdf PDF
Attachment_II_-_Price_Schedule.xlsx XLSX spreadsheet
RFQ.doc DOC document
Attachment_V_-_Wage_Determination.pdf PDF
Attachment_I_-_SOW.docx DOCX document
Attachment_III_-_Past_Performance_Information_Form.xlsx XLSX spreadsheet
Attachment_IV_-_Past_Performance_Questionnaire.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

SF30 (continued)

1305M219QNMAN0358

Amendment 0001

1. QUESTIONS AND ANSWERS:

All questions and responses/clarifications given to date are identified below and, if necessary, have been further addressed in this Amendment and/or Attachments hereto. The following questions and answers are provided for informational purposes only.

A. QUESTION: Can the total estimated hours of the labor on “Attachment 2 – Price Schedule” be adjusted? Up or down.

ANSWER: These hours are only an estimate. If hours need to go above and beyond, written approval from the Contracting Officer is required.

B. QUESTION: Can the split of hours between the labor categories (program director and systems analyst) on “Attachment 2 – Price Schedule” be adjusted? (Resulting in the same total number of hours.)

ANSWER: These hours are only an estimate. If hours need to go above and beyond, written approval from the Contracting Officer is required.

C. QUESTION: If awarded this contract, EthanHarper does not anticipate using W-2 employees on the project. Do the provisions of section (y) Insurance on page 5 of the RFQ still apply?

ANSWER: Yes that section still applies.

2. Except for the changes stated herein, all else remains unchanged.

End of Amendment 0001

Amendment 0001 Pg1
SF30

Amendment_Pg_2_

topmostSubform[0]:
Page1[0]:
AmendmentNo[0]: 0001
Code[0]: AJ930073
Code[1]:
AccountingData[0]: N/A
A13[0]:
C13[0]:
D13[0]:
NameandTitleSigner[0]:
NameandTitleOfficer[0]: Ashley Perry, Contracting Officer
Description[0]: OMAO SMALL BOAT RECAPITALIZATION AND SUSTAINABILITY PLAN

(See continuation on page 2)

FacilityCode[0]:
Code[2]:
IssuedBy[0]: NOAA/ERAD

200 GRANBY STREET

NORFOLK, VA 23510

NameandAddress[0]:
AdministeredBy[0]: See Block 6
ContractIDCode[0]:
ReqNumber[0]:
AmendmentNo[1]: 1305M219QNMAN0358
ModificationNo[0]:
ProjectNo[0]:
Page[0]: 1
Pages[0]: 2
EffectiveDate[0]: 08/26/2019
Dated9B[0]: 08/23/2019
Dated10B[0]:
CheckBox9[0]: 1
CheckBox10[0]: Off
CheckBox11[0]: 1
CheckBox13A[0]: Off
CheckBox13B[0]: Off
CheckBox13C[0]: Off
CheckBox13D[0]: Off
IsNot[0]: Off
Is[0]: Off
Extended[0]: Off
NotExtended[0]: 1
DateSigned[0]:
DateSigned[1]:
Copies[0]: 1
CopiesReturned[0]: