About this file

This document appears to be a solicitation notice for a federal contract opportunity. The Centers for Disease Control and Prevention (CDC), National Institute for Occupational Safety & Health (NIOSH) is seeking to procure facilities operations and maintenance support services through a single award contract with a period of performance up to 60 months. The contract will be a time and materials type, and the work will be performed at NIOSH campuses in Pittsburgh, PA; Spokane, WA; Morgantown, WV; and Cincinnati, OH. The solicitation is limited to eligible 8(a) participants under NAICS code 561210 - Facilities Support Services, with a small business size standard of $47M. Site visits are scheduled for potential offerors prior to the solicitation closing date in May 2024. Any questions regarding this opportunity should be submitted in writing to the specified contracting officer.

View the file

Other files for this federal contract opportunity

Other files attached to NIOSH Facilities Operations and Maintenance Support Solicitation Notice, newest first.
File Type Posted
75D30124R72963 Revised by Amendment 0002.pdf PDF
Amendment 0002 Submitted Questions and Answers.xlsx XLSX spreadsheet
75D301-24-R-72963 - Amendment 0002.pdf PDF
75D301-24-R-72963 - Amendment 0001.pdf PDF
75D30124R72963 Revised by Amendment 0001.pdf PDF
Amendment 0001 Submitted Questions and Answers.xlsx XLSX spreadsheet
1. Campus Map - Pittsburgh.pdf PDF
2. Campus Map - Morgantown.pdf PDF
5. Building Gross Square Footage for all Campuses.pdf PDF
15. AssetsEquipment-Morgantown.xlsx XLSX spreadsheet
20. CBA Pittsburgh & Morgantown -1.3.2024.pdf PDF
24. Davis Bacon Act- WV-WD-WV20240042 Mod. 2.pdf PDF
75D30124R72963-FINAL.pdf PDF
3. Campus Map - Cincinnati.pdf PDF
4. Campus Map - Spokane.pdf PDF
12. PMs-Morgantown.xlsx XLSX spreadsheet
17. AssetsEquipment-Spokane.xlsx XLSX spreadsheet
21. CBA Cincinnati.pdf PDF
23. Davis Bacon Act- PA- WD PA-20240001 Mod. 2.pdf PDF
25. Davis Bacon Act- OH-WD- OH20240082 Mod. 2.pdf PDF
6. Floor plans-Pittsburgh.pdf PDF
7. Floor plans-Morgantown.pdf PDF
9. Floor plans-Spokane.pdf PDF
14. AssetsEquipment-Pittsburgh.xlsx XLSX spreadsheet
18. Government Furnished Equipment_Pittsburgh.pdf PDF
19. Historical Positions Data.pdf PDF
26. Davis Bacon Act-WA- WD- WA20240017 Mod. 2.pdf PDF
8. Floor plans-Cincinnati.pdf PDF
11. PMs-Cincinnati.xlsx XLSX spreadsheet
16. AssetsEquipment-Cincinnati.xlsx XLSX spreadsheet
22. SCA WD 2015-5537 Rev. 21- Spokane Campus.pdf PDF
10. PMs-Pittsburgh.docx DOCX document
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAME

SHOP
SERVICE/DESCRIPTION
ASSET/LOCATION
ESTIMATE
IS ACTIVE
LAST COMPLETED DATE

PM-1247

WEEKLY SHIPPING AND RECIEVING

1 Task

GMW - Spokane
ADMIN

SPOKANE WEEKLY SHIPPING AND RECIEVING

Main Main

WEEKLY FLEET SERVICES

GMW - Spokane
ADMIN

SPOKANE WEEKLY FLEET SERVICES

Main

PMI 536 AIR COMPRESSOR #4 BIANNUAL PM SSR-EP15

GMW - Spokane
PM

PMI 536 AIR COMPRESSOR #4 BIANNUAL PM SSR-EP15

BA 1. Replace ultra-coolant.

BA 2. Replace shaft seal B098

SEMI ANNUAL SECURITY CAMERA

GMW - Spokane
PM

SEMI ANNUAL SECURITY CAMERA

CLEAN LENS OF SITE SECURITY CAMERAS

B098 B098

ANNUAL SPOKANE WATER FOUNTAIN FILTER CHANGE

GMW - Spokane
PM

ANNUAL SPOKANE WATER FOUNTAIN FILTER CHANGE:

CHANGE SITE WATER FOUNTAIN FILTERS

B098

PMI 539 FLAIR HDR COMPRESSED AIR DRYER ANNUAL PM

GMW - Spokane
PM

PMI 539 FLAIR HDR COMPRESSED AIR DRYER ANNUAL PM

Flair HDR Series Compressed Air Dryer Model: HDR200 Serial: 99MHRD0435

Inspect desiccant

Replace solenoid and butterfly valve diaphragm...

B098

PMI 539 FLAIR HDR COMPRESSED AIR DRYER MONTHLY PM

GMW - Spokane
PM

PMI 539 FLAIR HDR COMPRESSED AIR DRYER MONTHLY PM

Flair HDR Series Compressed Air Dryer Model: HDR200 Serial: 99MHRD0435

M 1. Check automatic drain valve.

M 2. Check system monitor light...

B098

PMI 537 AIR COMPRESSOR #3 TWO YEAR PM SSR-EP50SE

GMW - Spokane
PM

PMI 537 AIR COMPRESSOR #3 TWO YEAR PM

Ingersoll Rand Compressor SSR-EP50SE

Replace ultra-coolant

Replace shaft seal B098

PMI 537 AIR COMPRESSOR #3 ANNUAL PM SSR-EP50SE

GMW - Spokane
PM

PMI 537 AIR COMPRESSOR #3 ANNUAL PM

Clean separator scavenge screen and orifice

Replace air filter

Inspect starter contactors

B098

PMI 537 AIR COMPRESSOR #3 SEMI ANNUAL PM SSR-EP50SE

GMW - Spokane
PM

PMI 537 AIR COMPRESSOR #3 SEMI ANNUAL PM

Ingersoll Rand Compressor SSR-EP50SE

Replace coolant filters

Clean cooler cores

B098

PMI 537 AIR COMPRESSOR #3 MONTHLY PM SSR-EP50SE

GMW - Spokane
PM

PM 537 AIR COMPRESSOR #3 MONTHLY PM

M 1. Inspect coolant level visible in the fill port (when cold).

M 2. Inspect discharge temperature (air).

M ...

B098

AIR COMPRESSOR #4 TWO YEAR PM

GMW - Spokane
PM

AIR COMPRESSOR #4 TWO YEAR PM

INGERSOLL RAND COMPRESSOR SR EP-15

Replace ultra-coolant Replace shaft seal B098

PMI 538 ZEKS HYDRONICIX AIR DRYER 3 YEAR PM

GMW - Spokane
PM

PMI 538 ZEKS HYDRONICIX AIR DRYER 3 YEAR PM

Replace desiccant.

Replace Check Valves (Preventative)

COMS-09

PMI 538 ZEKS HYDRONICIX AIR DRYER ANNUAL PM

GMW - Spokane
PM

PMI 538 ZEKS HYDRONICIX AIR DRYER ANNUAL PM

Check desiccant and replace if necessary.

Inspect and clean solenoid valves, check valves and purge lines.

For dryers equipped with Inlet and Pu...

COMS-09

PMI 538 ZEKS HYDRONICIX AIR DRYER SEMI ANNUAL PM

GMW - Spokane
PM

PMI 538 ZEKS HYDRONICIX AIR DRYER SEMI ANNUAL PM

Check outlet dew point.

Blow-down relief valves.

Replace prefilter and afterfilter elements and/or cartridges.

COMS-09

PMI 538 ZEKS HYDRONICIX AIR DRYER DAILY PM

2 Tasks

GMW - Spokane
Rounds,PM

PMI 538 ZEKS HYDRONICIX AIR DRYER DAILY PM

Check and record inlet pressure, temperature and flow. Verify that it is within specifications.

Check tower pressure gauge readings within operatin...

COMS-09

ANNUAL SPRING DAYLIGHT SAVINGS TIME CLOCK CHANGE

PM

ANNUAL SPRING DAYLIGHT SAVINGS TIME CLOCK CHANGE

Main,B098 Main; B098

WEEKLY BUILDING EXTERIOR AND GROUNDS INSPECTIONS

GMW - Spokane
Rounds

WEEKLY BUILDING EXTERIOR AND GROUNDS INSPECTIONS

ANNUAL FALL DAYLIGHT SAVINGS TIME CLOCK CHANGE

Electrical - Spokane
PM

ANNUAL FALL DAYLIGHT SAVINGS TIME CLOCK CHANGE

B098

Daily Rounds

GMW - Spokane
Rounds

Any regularly pre-scheduled rounds style inspection, use this work order to capture daily rounds for the month.

Main

Monthly Snow Removal and Deice PM

Laborer - Spokane
PM

SAFETY INSTRUCTIONS

1. Notify Building Supervisor prior to commencing work

2. Inspectors shall observe all safety procedures.

INSTRUCTIONS

1. Check to verify that all machinery is in proper wor...

R - Grounds,Main - Grounds Main - Grounds; Reardan

Annual Cub Cadet Tractor PM 4 Tasks

Landscaping-Spokane
PM

Annual Cub Cadet Tractor PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as n...

SNWS-02,SNWS-01,FUVS-03,FUVS-01

B098 - L1; B098 - L1; Main - Grounds; Main - Groun...

Annual Boiler PM

Mechanic - Spokane
PM

Annual Boiler PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as needed to re...

BLRS-01

Main - B - R3

Annual refrigerator water filter replacement PM 6 Tasks

Plumbing - Spokane
PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as needed to restrict work area acc...

RFGS-06,RFGS-05,RFGS-04,RFGS-03,RFGS-02,RFGS-01

Main - L2 - R232; Main - L2 - R232; Main - L1 - R1...

6 month automatic door inspection PM

GMW - Spokane
PM

6 Month Automatic Door Inspection PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barric...

ADRS-04,ADRS-03,ADRS-02,ADRS-01

Main - L1 - R100; Main - L1 - R170; Main - L1 - R1...

Quarterly PMI 011 GFCI Testing PM

Electrical
PM

Quarterly PMI 011 GFCI Testing PM Main,B098 - L1 B098 - L1; Main

Annual Fire Extinguisher test and inspection PM 77 Tasks

Safety-Spokane
PM

Annual Fire Extinguisher Test and Inspection PM

Annual Testing is done by a certified 3rd Party in accordance with NFPA Standards.

CO2 UNITS

A 1. Check weight of unit with approved type scale EXVS-08, EXVS-07 +75 other(s) Main - B - R3; Main - B - R4; Main - B - R8; Main ...

Facility Ground Care by Outside Contractor PM

Landscaping-Spokane
Grounds

This PM is generated for onsite contractor to schedule various outside contractors to complete lawn and tree care. It will generate monthly from April to October. The monthly work request by month ...

R - Grounds,Main - Grounds

Monthly PA System Test PM

Safety-Spokane
PM

Monthly PA System Test PM

Main - L2,Main - L1 Main - L1 ; Main - L2

Annual Sprinkler Winterizing PM

Landscaping-Spokane
PM

SAFETY INSTRUCTIONS

1. Notify Building Supervisor prior to commencing work. Verify that the valve will not interrupt service to on-going CDC/NIOSH projects. Post warning signs or barricades as nee...

Main - Grounds Main - Grounds

Annual Pallet Rack inspection PM

Warehouse - Spokane
PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as needed to restrict work area acc...

R - Hill Building,B098 - L1 B098 - L1; Reardan

Annual Water Filter PM 3 Tasks

Plumbing - Spokane
PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as needed to restrict work area acc...

WFLS-03,WFLS-02,WFLS-01

Main - B - R3; Main - L2 - R232; Main - L2 - R232

Annual Smoke Detector Alarm Testing PM

Safety-Spokane
PM

SAFETY INSTRUCTIONS

1. Notify building Supervisor and personnel prior to testing alarm. Post warning signs or barricades if safety concerns exist. At the completion of work, notify Supervisors and...

FSAS-02,FSAS-01,FAPS-03,FAPS-02

Main - L1-R169; B098-L1; Main - L1 - R185; Main - ...

6 month Fence and Gate Inspection PM

Laborer - Spokane
PM

6 Month Fence and Gate Inspection PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

INSTRUCTIONS

S 1. Make sure that you use the proper PPE (Personal Protection Equipm...

Main - Grounds,AGRS-03,AGRS-02,AGRS-01 Main - Grounds; Main - Grounds; Main - Grounds; Ma...

Annual Ladder Inspection PM 5 Tasks

Laborer - Spokane
PM

SAFETY INSTRUCTIONS

1. Safety administrator or inspector should only inspect ladders when they are not in use.

2. Inspectors shall observe all safety procedures.

3. Notify Building Supervisor pr...

R - Upper Missle Bay, R - Hill Building +3 other(s) B098 - L1 - R1; Main - L1 - R100 ; Main - L2 - R20...

Annual Extension and tool Cord Inspection PM

Electrical - Spokane
PM

Annual Extension and tool Cord Inspection PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs o...

Main - L2 - R200 ,Main - L1 - R100 ,B098 - L1 - R1 B098 - L1 - R1; Main - L1 - R100 ; Main - L2 - R20...

6 month AC Unit PM 15 Tasks

HVAC - Spokane
PM

6 Month AC Unit PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as needed to ...

SCUS-11, SCUS-07 +13 other(s) Main - East Roof; Main - West Roof; Main - West Ro...

Monthly Drain Flushing PM 19 Tasks

Plumbing - Spokane
PM

SAFETY INSTRUCTIONS

1. Notify Building Supervisor prior to commencing work. Verify that the valve will not interrupt service to on-going CDC/NIOSH projects. Post warning signs or barricades as nee...

Main - L2 - R254, Main - L2 - R242A +17 other(s) Main - L1 - R132; Main - L1 - R134; Main - L1 - R1...

Monthly Landscaping PM

Landscaping-Spokane
PM

SAFETY INSTRUCTIONS

1. Notify Building Supervisor prior to commencing work

2. Inspectors shall observe all safety procedures.

INSTRUCTIONS

1. Check to verify that all machinery is in proper wor...

R - Grounds,Main - Grounds

6 month Carbon Monoxide Detectors PM

Safety-Spokane
PM

6 Month Carbon Monoxide Detectors PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barric...

CODS-02,CODS-01

Main-B-R3; B098-Mezz

Monthly Eye Wash Station PM

Safety-Spokane
PM

GENERAL REMARKS

1. Inspector shall inform the building or area supervisor of his/her activities.

2. Inspector shall report any corrective action recommended on the unit which is outside the scope...

EWSS-03,EWSS-02,EWSS-01

Main - L2 - R254; MAIN - L1 - R129; MAIN - L1 - R1...

Monthly Fire Extinguisher PM 77 Tasks

PM

Monthly Fire Extinguisher PM

GENERAL REMARKS

1. The approved inspector RWD shall perform all inspections in accordance with NFPA codes and standards and OSH...

EXVS-08, EXVS-07 +75 other(s) Main - B - R3; Main - B - R4; Main - B - R8; Main ...

Annual Forklift Inspection PM

Heavy Equipment - Spokane
PM

Annual Forklift Inspection PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

Annual Inspection is done by a certified 3rd party in accordance OSHA standards

INSTRUCTIO...

LFTS-01,FKLS-03,FKLS-02,FKLS-01

Main - L1 - R145; Main - L1 - R145; R - Hill Build...

Annual Washer and Dryer PM

Mechanic - Spokane
PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as needed to restrict work area acc...

WASS-01,CDRS-01

Main - L1 - R140; Main - L1 - R140

6 month Computer Room HVAC PM

HVAC - Spokane
PM

6 Month Computer Room HVAC PM

SAFETY INSTRUCTIONS

1. Notify Building Supervisor prior to commencing work. Verify that the valve will not interrupt service to on-going projects. Post warning sig...

ACUS-10A,ACUS-10

Main - L2 - R227B; Main - L2 - R227B

6 Month Air Dryer PM

Mechanic - Spokane
PM

6 Month Air Dryer PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as needed t...

ACFS-05 (Inactive),ADRS-05 B098 - Mezz; B098 - Mezz

6 month Circulating and Sump Pump PM 16 Tasks

Plumbing - Spokane
PM

6 Month Circulating and Sump Pump PM

SAFETY INSTRUCTIONS

1. Notify the Supervisor prior to commencing work, post warning signs or barricades, as needed to restrict work areas access if work req...

PMPS-16, PMPS-15 +14 other(s) Main - B - R3; Main - High Roof; Main - B - R3; Ma...

6 month Variable Air Volume Box PM 18 Tasks

HVAC - Spokane
PM

6 Month Variable Air Volume Box PM

SAFETY INSTRUCTIONS:

1. Notify Building Supervisor of your intent to perform servicing. Prior to commencing work, post warning signs or barricades as needed t...

VAVS-18, VAVS-17 +16 other(s) Main - L1 - R127; Main - L1 - R127; Main - L1 - R1...

Annual FIre Protection Sprinkler Systems PM 9 Tasks

Safety-Spokane
PM

Annual fire Protection Sprinkler Systems PM

GENERAL REMARKS

1. Coordinate the P.M. work with the E.H.& S. Group (Environmental Health and Safety) and supervisory personnel for the building. Ale...

FSVS-05, FSVS-04 +7 other(s) Main - L1 - R113; Main - L1 - R172; Main - L1 - R1...

NAME
SHOP
SERVICE/DESCRIPTION
ASSET/LOCATION
ESTIMATE
IS ACTIVE
LAST COMPLETED DATE

Annual Hot Water Heater PM 8 Tasks

Plumbing - Spokane
PM

Annual Hot Water Heater PM

SAFETY REMARKS

1. Contact building supervisor before inspecting heaters.

2. Do not turn on any heater before contacting building supervisor. Some heaters are located...

PRVS-04, PRVS-03 +6 other(s) Main - B - R3; B098 - Mezz; R - Lower Missle Bay; ...

Monthly Air Compressor inspection PM 10 Tasks

Mechanic - Spokane
PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as needed to restrict work area acc...

ACFS-05 (Inactive), ACFS-02 (Inactive) +8 other(s) Main - B - R9; Main_B - R9; B098 - Mezz; Main - B ...

Annual Emergency Lighting PM 66 Tasks

Electrical - Spokane
PM

Annual Emergency Lighting PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing work, post warning signs or barricades as ...

EXLS-29, EXLS-28 +64 other(s) Main - B - R4; Main - B - R3; Main - B - R3; Main ...

Annual Overhead Door inspection PM 18 Tasks

Mechanic - Spokane
PM

Annual Overhead Door Inspection PM

Annual Overhead Door inspection PM

SAFETY INSTRUCTIONS

1. Inspectors shall observe all safety procedures.

2. Notify Building Supervisor prior to commencing ...

ODOS-18, ODOS-17 +16 other(s) Main - L1 - R185; Main - L1 - R129; Main - L1 - R1...

Annual Overhead Crane inspection PM 9 Tasks

Heavy Equipment - Spokane
PM

Annual Overhead Crane Inspection PM

SAFETY INSTRUCTIONS

1. Inspectors shall perform all work in accordance with OSHA regulations for frequent inspection on overhead and gantry cranes (1910.179)...

HOIS-07, HOIS-06 +7 other(s) Main - L1 - R185; B098 - Mezz; Main - L1 - R192; M...

Annual Building Exterior Inspection PM

GMW - Spokane
PM

Annual Building Exterior Inspection PM

BUILDING EXTERIOR INSPECTION

STEPS, PORCHES, RAMPS, LOADING PLATFORMS, WALKWAYS,

DRIVEWAYS, COLUMNS, FACADE MOUNTED ITEMS.

1. Does water drain away fr...

Main,B098 Main; B098

6 month Exhaust Fan inspection PM 28 Tasks

HVAC - Spokane
PM

6 Month Exhaust Fan Inspection PM

EXHAUST FAN

1. Turn fan ON and check for unusual vibrations and noises. If these conditions exist, try to identify their source and make field corrections if...

REFS-04 (Inactive), REFS-28 +26 other(s) Main - High Roof; Main - High Roof; Main - High Ro...

Annual Building Roof Inspection

GMW - Spokane
PM

Annual Building Roof Inspection

BUILDING ROOF INSPECTION

1. Examine roofing material for physical damage.

2. Examine roof surface for deterioration conditions.

3. Check roof for spongine...

Main - High Roof ,Main - East Roof Main - East Roof; Main - High Roof

Annual Backflow Preventer Test

Plumbing - Spokane
PM

Annual Backflow Preventer Test

PREVENTIVE MAINTENANCE – Self explanatory

BFPVS-04,BFPVS-03,BFPVS-02,BFPVS-01

Main - B - R3; Main - Grounds; Main - Grounds; Mai...

Annual Elevator Inspection PM

GMW - Spokane
PM

Annual elevator Inspection PM

1. To be completed by a certified third-party company.

2. Will meet all applicable standards.

3. Report sent to RWD for record keeping purposes.

PELS-01

Main - L1 - R100

Monthly Boiler PM

HVAC - Spokane
PM

Lockinvar Knight XL Monthly Maintenance PM

1. Inspect vent and air piping

2. Check air and vent screens

3. Check relief valve

4. Check condensate drain system

5. Check boiler gas and water pip...

BLRS-01

Main - B - R3