Griffin Creek Bridge Project

Questions and Answers

As of 3/21/2018

1. Can the Forest Service verify how the concrete deck is attached to the glulam stringers?

The deck is attached to the glulam stringers by 7/8” X 8” Lag bolts. The short span has a double lag pattern 4” OC. The long span has a single lag pattern 4 ½” OC

2. Does the Forest Service have an approximate weight of the concrete deck and the glulam stringers?

No.

3. Can we get a copy of the As-built drawings from the original installation of the bridge?

There are no as-built drawings on record for this structure.