PROJECT STATEMENT OF WORK
1. CONTRACT PROJECT:
A. Project Title: Replace Compressors for Constant Temperature Rooms in the
National Lab for Genetic Resources Preservation, of the Center for
Agricultural Resources Research, ARS, USDA.
B. Project Location: National Laboratory for Genetic Resources Preservation, 1111 South Mason, Fort Collins, CO, 80523.
2. PROJECT CONTACT PERSONS:
A. CONTRACTING OFFICER (CO):
Fred Gifford Tel. No. (510) 790-1284
800 Buchanan Street email: Fred.Gifford@ars.usda.gov
Albany, CA, 94710
B. ADMINISTRATIVE CONTRACTING OFFICER (ACO):
Shannon Colgan Tel. No. (970) 492-7704
USDA, ARS, Center for Agricultural Resources Research (CARR)
2150 Centre Ave., Building D Email: Shannon.Colgan@ars.usda.gov
Fort Collins, CO 80526
C. ENGINEERING PROJECT MANAGER (EPM) and CONTRACT OFFICER’S
REPRESENTATIVE (COR):
Greg Graham Tel. No.: (970) 492-7025
USDA, ARS, WBSC Fax No.: (970) 492-7049
2150 Centre Avenue, Email: Greg.Graham@ars.usda.gov
Building D, Suite 310, D. RESEARCH PROGRAM REPRESENTATIVES (RPR):
Dr. Daren Harmel Tel. No.: (970) 492-7771
Center Director Email: daren.harmel@ars.usda.gov
USDA, ARS, CARR
2150 Centre Ave., Building D
E. ADMINISTRATIVE OFFICERS (AO):
Travis Vagher Tel. No.: (970) 492-7701
Administrative Officer- Acting Email: Travis.Vagher@ars.usda.gov
USDA, ARS, CARR
2150 Centre Ave., Building D, F. LOCATION COORDINATORS (LC):
mailto:Fred.Gifford@ars.usda.gov mailto:Shannon.Colgan@ars.usda.gov mailto:Greg.Graham@ars.usda.gov mailto:daren.harmel@ars.usda.gov mailto:Travis.Vagher@ars.usda.gov
William Prange Tel. No.: (970) 492-7706
Safety and Occupational Health Specialist
USDA, ARS, CARR
2150 Centre Ave., Building D, Email: William.Prange@ars.usda.gov
G. SAFETY AND OCCUPATIONAL HEALTH MANAGER (SOHM):
Phil Smith Tel. No.: (979) 260 - 9449
USDA, ARS, WBSC Email: Phil.Smith@ars.usda.gov
1001 Holleman Drive East
College Station, TX 77840
3. SCOPE OF WORK:
A. Base Bid is to provide a Technical Proposal to replace eleven existing compressors with water cooled tube and bundle condensers with adjacent refrigerant piping in a maintainable arrangement for Constant Temperature Rooms 131, 142, 143, 154, 154A, 156, 156A, 206, 223, 224, 225. Reuse existing evaporators after the installation of new thermal expansion valves compatible to new refrigerant for all rooms, except 131. Provide new evaporator for CT room 131 sized appropriately and equipped with electric defrost.
4. RELEVANT DOCUMENTS
A. Attached Documents: The Consultant shall use all documents marked by an “X” in preparing the required contract documents.
[X] Temperature Control Rooms 20180419v2.pdf
[X] Ground Floor Plan South Revisions 1990 NSSL 0039 (2) 20180417.pdf
[X] Partial 2nd floor Plan HVAC N 1990 NSSL 0154.pdf
[X] Partial Enlarged Mechanical Equipment Room Plan M32 1990 20180417.pdf
[X] Partial Ground Floor Plan North 1990 NSSL 0036 (2) 20180417.pdf
[X] Partial Second Floor Plan N 1990 NSSL 0040 20180417.pdf
[X] Partial Second Floor Plan North 1990 NSSL 0042 (2).pdf
[X] Partial Third Floor Plan N 1990 NSSL 0044 (2) 20180417.pdf
[X] Second Floor Plan South 1990 NSSL 0043 (2) 20180417.pdf
5. PROJECT REQUIREMENTS:
A. Technical Proposals are required to show the new maintainable arrangement for the new compressors with water cooled tube and bundle condensers.
The CONTRACTOR shall do the project in two separate phases, Phase 1 and
Phase 2 as shown on the Temperature Control Rooms 2018-01-30.pdf.
1. Phase one would be for the south rack located in room 301A (6 compressors and associated equipment serving Temperature Control Rooms 142, 143, 154, 154A, 156, and 156A).
mailto:William.Prange@ars.usda.gov mailto:Phil.Smith@ars.usda.gov
2. Phase two is for the remaining rack (5 compressors et al) located in room 301, serving Temperature Control Rooms 131, 206, 223, 224, and 225.
B. The compressors and condensers are to be mounted on a single layer raised “rack” which will be installed to allow for ease of maintenance by positioning the racks away from the walls or other fixed barriers. Housekeeping pads to be installed as needed to support the rack.
C. Contractor is to size the new compressors and evaporator to meet the specified
Control Temperatures.
1. Control Temperatures are to maintain temperatures 1 Celsius of the setpoint, and control accuracy of 0.5 Celsius. Rooms are monitored and controlled by existing Johnson Controls Metasys™ Building Automation
System.
D. Replace existing Evaporator installed in room 131 with unit sized appropriately to room size and temperature requirements. All other evaporators shall be re-used and cleaned as needed with appropriate coil cleaning methods.
E. Replace current evaporator fans with Electrically Commutated Motors (ECM) and controllers.
F. Refrigerant used shall be 507. Existing line sets and evaporators are to be cleaned/ flushed per manufacturer recommendations to remove previous refrigerant oil and contaminants.
G. Rooms with designed working temperatures below freezing shall have KE2
Evaporator Efficiency units installed. (rooms 131, 154, 154A and 225) These units will control defrost and monitor efficiency in rooms and shall report to a central KE2 LDA interface.
H. Install Infrared refrigerant leak detector devices in each room and on compressor racks. These devices shall report to a central monitoring station to alert staff of leaks.
I. Replaceable core inline filter-dryers shall be installed on suction line of all compressors.
J. Isolation valves shall be installed on water lines at appropriate points on each system to allow ease of service and repair.
K. Isolation valves shall be installed on refrigerant lines at evaporator, condenser and compressor.
L. Replace existing room lighting (incandescent or metal halide) with waterproof dimming LED linear fixtures providing 40-50 foot-candles at 3 feet above floor.
M. Testing of installation
1. Charge system with regulated dry nitrogen and the appropriate tracer gas to bring system pressure up to 300 psig minimum. After system has been checked for leaks and all leaks have been repaired and retested, the system must stand, unaltered, for 24 hours with no more than a +/- 1-pound pressure change from 300 psig, using the same gauge.
2. Vacuum test system per refrigeration compressor manufacturer’s recommendation for commissioning. Vacuum test is to be performed in the presence of a Government representative with 200 microns pulled and held for
24 hours. A maximum drift of 100 microns over 24 hours is allowed. See https://www.epa.gov/sites/production/files/documents/leakguidelines.pdf https://www.epa.gov/sites/production/files/documents/leakguidelines.pdf
N. Humidity Control is provided by existing Munters desiccant wheel dehumidifiers.
No modifications to this equipment are covered under this contract.
O. Existing Temperature controlled rooms are constructed with pre-engineered 4” poured-in-place urethane panels (estimated R-28 value).
P. Two access doors allow access into the shaft servicing phase 1 piping connecting the 3rd floor and ground floor walk-in coolers are located at the base of the shaft accessible thru the elevator machine room and at floor level on the third floor.
Q. Condenser water supply Pumps, each rated at 2 horsepower and programmed for lead/lag control), were designed to provide 60 GPM with a 65-foot head. The cooling tower set point is 68°F with an alarm temperature of 80°F.
6. SPECIAL REQUIREMENTS:
A. Coordination of Constant Temperature Room Schedules:
1. Room 206 to be used by Research Program on Dec. 17, 2018, full project completion NLT Dec. 1, 2018.
2. Room 225 to be used by Research Program until July 6, 2018. Edwards
Refrigeration will be installing a dehumidifier in this room July 9 – July 23, 2018. Contractors will not interfere in other ongoing project timelines. Room
225 is available for modifications after dehumidifier project completion, NLT
July 23, 2018 until Dec. 1, 2018. Research Program to use after Dec. 17, 2018.
3. All other rooms to be completed by estimated project completion date of
January 21, 2018.
7. GENERAL REQUIREMENTS:
A. Coordination and Assistance
1. Coordination and Assistance between the Contractor, Contractor's personnel and Sub-Contractors, Contracting Officer, Contracting Officer's
Representative, Location Monitor, and Research Personnel on the following items will keep all appropriate personnel involved to expedite this project for everyone’s benefit.
B. Notice to Proceed
1. Notice to proceed from the Contracting Officer is required before the
Contractor should incur any costs and before any work is performed on site.
C. Correspondence
1. Correspondence between the Contractor, Contracting Officer, and Contracting
Officer’s Representative should be dated, logged, and copies kept at the originator’s office.
D. Progress schedule
1. Progress schedule should be completed and submitted to the Contracting
Officer before the Pre-Construction Conference.
E. Pre-Construction Conference.
1. Schedule: The Pre-construction Conference with the Contracting Officer’s
Representative shall be scheduled for the first day of the awarded POP.
2. Attendees shall include the Contracting Officer's Representative, the
Contractor, Contractor's superintendent, Location Monitor, and others.
3. Agenda shall include the following:
a. Introductions of Attendees, with designation for 24-hour calls, by the
Contracting Officer’s Representative and the Contractor.
b. Facility’s normal working hours are M-F, 0700 to 1630, MT. Excluding
Federal Holidays. No work shall be performed on the premises outside of these working hours.
c. Allowable Contractor’s use of Premises, Office, Work, and Storage areas with safety, housekeeping, and security procedures.
d. Allowable Contractor’s equipment and material deliveries.
e. Contractor’s Progress Schedule and coordination items for any utility outages or hazardous materials.
f. Due to the size of this Project, the Materials, Products, Installation
Procedures, Testing Procedures, etc. shall meet commercial standards and shall be reviewed prior to NTP if requested by the Contractor or the
Contracting Officer’s Representative requests a specific item, otherwise review will be at the Final Inspection.
g. Contractor’s Inspection Procedure, including field testing and approvals with a remedial process for any deficiencies.
h. Government’s Quality Assurance Program of random inspections and notifying the Contractor of any noted deficiencies. This does not relieve the Contractor from requirements of the Contract.
i. Procedures for the Contractor to submit Applications for Payment.
4. Safety.
a. Contractor's OSHA Certified Safety Competent Person designation will be made at the Pre-Construction Conference.
b. Past safety record will be used as an evaluating factor in future contracts.
c. Request a copy of past 3 years OSHA 300A Summary of Work Related
Injuries and Illnesses.
d. Investigate past OSHA safety inspections using the establishment search
(http://www.osha.gov/pls/imis/establishment.html ).
e. Request a copy of any OSHA training course documentation for contractor and his/her employees.
f. Request copy of relevant safety plans.
g. Contractor will be required to hold at least weekly safety meetings during the POP of this awarded contract.
h. Contractor and his employees will be required to follow all requirements of
29 CFR 1926 OSHA Standards for the Construction Industry.
i. All relevant PPE as dictated by the hazards present must be worn by the contractor and all employees working on the job site.
j. Location Monitor will walk the site with an eye to safety.
k. Possible Hazards of this Contract are:
1. Ladder Use.
2. Glass handling.
3. Loading and Hauling.
http://www.osha.gov/pls/imis/establishment.html
F. Operations and Storage Areas
1. Water, gas, and electricity are available on the site.
2. Toilet: Toilet, wash facilities, etc., are available for Contractor to use responsibly. Facilities shall be left in condition as they are found so that no additional work is required by facility staff to maintain.
G. Cleaning Up
1. Debris and rubbish shall be removed from the site daily. Upon the end of the work day, the entire area of the contract work shall be cleaned of all excess materials, dirt, rubbish, and debris.
2. Transportation of debris shall be in a manner as to prevent spillage on street or adjacent areas.
H. Utilities
1. Utilities are to the work site and will be used reasonably.
I. Specifications and Drawings.
1. No scaling. Do not scale drawings for dimensions.
J. Schedules and Coordination.
1. Coordination: Coordinate construction activities with the Contracting
Officer's Representative to be in compliance with the Scheduling
Requirements. Coordination meetings shall be held once a week usually, but the COR can change the time period depending on the amount of activity by the Contractor. The agenda shall include accomplishments, problems, and solutions since the previous meeting. The Contractor shall prepare and distribute minutes of progress meetings. No later than 3 days after each meeting, the Contractor shall provide a copy of the minutes to the COR.
2. Monitoring the Progress Schedule: The Contractor or the COR shall inform the CO and ACO if the Contractor is behind on the schedule, why and what is planned to get back on schedule, so the CO can take appropriate action if needed.
K. Quality Assurance.
1. Required Submittals will be noted in the Statement of Work or in the
Specification section that is applicable. Contracting Officer may request additional submittals on contract items when needed. A submittal form in
Word format, will be provided upon request after contract award.
2. Construction Inspector’s Daily Reports are recommended with the
Contractor’s standard form. The Contractor shall complete and submit the daily reports to the COR weekly, on the first working day of the following week. The COR may waive the requirement for daily reports, at their discretion.
L. Protection of Existing Equipment, Utilities, and Improvements.
1. Contractor is responsible for protection and restoration if damage occurs. See
Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (FAR 52.236-9) (APR 1984) in Section H - Special Contract
Requirements.