SECTION C – STATEMENT OF WORK

C.1 PURPOSE

This is a new project for construction services for the Brush Creek/Hayden Ranger District located on the Medicine Bow-Routt National Forest and Thunder Basin National Grassland (MBRTB). The purpose of this contract is to perform sewer and water line construction work at the Brush Creek/Hayden Ranger District compound located in Saratoga, Wyoming. The work shall consist of all necessary labor, supervision, equipment, tools, and materials to connect the District compound to the Town of Saratoga’s municipal utilities.

The sanitary sewer construction will require the installation of a duplex grinder pump lift station, and the construction of approximately 160 lineal feet of 1 ¼” sanitary sewer force main, 210 lineal feet of 4” gravity sanitary sewer, and 980 lineal feet of 6” gravity sanitary sewer from the existing Town of Saratoga 8” gravity sanitary sewer. The existing onsite wastewater disposal system will be abandoned in accordance with WYDEQ regulations once the new sanitary sewer is connected to the Town of Saratoga.

In addition, the project includes construction of approximately 630 lineal feet of 12” water main, 710 lineal feet of 8” water main, 760 lineal feet of 4” fire service line, and 760 lineal feet of 1-1/2” domestic services to three buildings onsite, three fire hydrants, and all taps, valves, meters, fittings, thrust blocks, and other appurtenances to connect the Forest Service site to the Town of Saratoga’s water distribution system.

All work shall adhere to industry standards, local building code requirements, and manufacturer installation recommendations.

452.211-72 Statement of Work/Specifications. (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

(End of Clause)

452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

(End of Clause)

C.2 SITE DESCRIPTION AND LOCATION

2171 Highway 130 PO Box 249 Saratoga, WY 82331

Latitude 41.437808° Longitude -106.803759°

C.3 AGAR 452.211-74 Period of Performance. (FEB 1988) The period of performance of this contract is from September 1, 2017 through March 1, 2018

(End of Clause)

C.4 SUBMITTALS

Prepare submittals as required by the Specifications.

C.5 USE OF PREMISES

A. Storage of materials and supplies will be confined to areas as approved by the Contracting Officer. All construction waste shall be properly disposed of in accordance with County and Wyoming State Laws.

B. Lodging and meals are available in Saratoga, Wyoming. Public restrooms are not available on-site.

C. Work hours shall be limited to 0700-1700 Monday through Friday, unless approved by the Contracting

Officer.

C.6 CONSTRUCTION SEQUENCE

There is no specified construction sequence for this project. However, the connection of the existing compound facilities to the municipal utilities must be done in a manner that will limit the disruption of water and sewer service to essential outages required to connect the new service to the existing water and sewer lines.

C.7 QUANTITY DETERMINATION

Quantities shall be confirmed by the Contractor prior to bid.

C.8 BIOBASED PRODUCTS

The Contractor must comply with Section 9002 of the Farm Security and Rural Investment Act of 2002 (FSRIA), Executive Order (EO) 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” and the Federal Acquisition Regulation to provide biobased products.

The Contractor shall utilize products and material made from biobased materials (e.g., insulating foam, composite panels, and concrete and asphalt release fluids) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).

The following is an example list of products that may be used in this contract for minor construction for which biobased products are available. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

Adhesive and mastic removers, Roof coatings, Hydraulic fluid, Equipment Lubricants, Hydraulic Fluids, Fuel Additives, Engine Oils, Office Products (Ink, paper, cleaning products).

Biobased products that are designated for preferred procurement under USDA’s BioPreferred program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material (i.e. particular crop or livestock). In addition to the biobased products designated by the U.S. Department of Agriculture in the BioPreferred Program, the Contractor is encouraged to use other commercially available biobased products.

For more information regarding the Department of Agriculture Biobased Program go to:

http://www.biopreferred.gov.

http://www.biopreferred.gov/ http://www.biopreferred.gov/

SECTION C – STATEMENT OF WORK
C.1 PURPOSE
C.2 SITE DESCRIPTION AND LOCATION
C.3 AGAR 452.211-74 Period of Performance. (FEB 1988)
C.4 SUBMITTALS
C.5 USE OF PREMISES
C.6 CONSTRUCTION SEQUENCE
C.7 QUANTITY DETERMINATION
C.8 BIOBASED PRODUCTS