B01a_Snaggletooth_IRSC_Appendix_A.docx

DOCX document 32 KB Posted

Attached to
San Juan National Forest Snaggletooth Stewardship
Solicitation number
1282CS19Q4003
Issued by

About this file

Appendix A

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sol 1282CS19Q4003Snaggletooth IRSCAppendix A
Contract: Assigned at awardPage: 7 of 7

STATEMENT OF WORK

SECTION I – GENERAL

1.1 SCOPE OF WORK

This statement of work consists of conducting fuels reduction activities to include but not limited to Pre-commercial Thinning, Commercial Timber Harvest, Processing/Decking, Road Maintenance, Erosion Control, and Slash Treatments. The contractor shall provide any and all labor, equipment, supplies, (except those listed in C.5; Government Furnished Property) services, permits, supervision, workman’s compensation, unemployment, and transportation to accomplish projects within the Snaggletooth Stewardship Contract. This statement of work consists of completing tasks in accordance with Section V, and performance requirements in Section VII.

SECTION II – DEFINITIONS

2.1 STANDARD DEFINITIONS

2.1.1 CAMPING: Will be allowed.

2.1.2 DEFECTIVE SERVICE: A unit of service, which contains one or more defects, or nonconformance with specified requirements.

2.1.3 FIRE PLAN EQUIPMENT: To make available for Forest Service rental at fire fighting equipment rates common in the area or at prior agreed rates any or all of Contractor’s equipment suitable for fire fighting and currently engaged in Contractor’s operations within the distance on Contract Area.

2.1.4 FIRE PRECAUTIONARY PERIOD: Will be specified at the contract order.

2.1.5 PERFORMANCE REQUIREMENTS SUMMARY (PRS): Identifies the key service outputs of the contract that will be evaluated by the Government to assure contract performance standards are met by the contractor.

2.1.6 PROTECTION OF IMPROVEMENTS: The protection of known improvements. Costs to replace or repair damage are the contractor’s responsibility (see table; pages 6,7 and 8).

2.1.7 TEMPORARY ROADS: Roads other than specified roads that are constructed by contractor for the purpose of harvesting and removal of timber. The location and clearing widths shall be designated or agreed to by Forest Service prior to construction. Temporary roads will obliterated and closed at the end use unless indicated on contract area/slash/activity map.

2.2 TECHNICAL DEFINITIONS

2.2.1 CIRCULAR PLOT: A sample plot within a thinning unit that is used to determine the number of desirable trees left in a plot in accordance with the task order.

2.2.2 CUT TREES: Trees that do not possess the characteristics of desirable leave trees, and are required to be cut. As described by Designation by damage class or otherwise marked to be cut or not marked to be leaved.

2.2.3 CUTTING UNIT: see Treatment Unit.

2.2.4 DAMAGED TREES: Damage to trees in excess of 5% of the number of leave trees will be considered excessive, and the Contractor will be charged $10.00 per damaged leave tree beyond 5%. As determined by expansion of plot data or individual tree count, which ever method the Forest Service determines to use.

2.2.5 DBH: Diameter at breast height, measured at a point of 4 ½ feet above the ground level on the uphill side of the tree.

2.2.6 DECKING: Stockpiling of trees in a designated area, minimum size is 6’ face length and at least 4’ tall.

2.2.7 DEAD/DYING TREES: Trees with the crown foliage changing from green to red or needleless. Any tree that has pitch tubes indicating beetle infestation.

2.2.8 DIB: Diameter of the stem inside the bark

2.2.9 HANG-UP TREE: Any cut tree suspended above ground level.

2.2.10 NON-SAWTIMBER TREE: Bole material that does not meet utilization standards set forth in this specific service contract standards, Non saw timber also referred to as “Product Other Than Log” falls within sizes 5.0 DBH and 9.9 DBH.

2.2.11 PROGRESSION OF WORK: Work conducted in a progressive, workmanlike and orderly manner by the contractor.

2.2.12 RESERVE CLUMPS: Groups of trees within a treatment area that the contract or COR designates are reserved for treatment.

2.2.13 SAWTIMBER TREE: Bole material that meets forest sawtimber utilization standards. (10” DBH +)

2.2.14 TREATMENT UNIT: An individual area on the ground in which activities will be performed and which may appear as a separate pay item in the Schedule of Items.

2.2.15 TREE QUALITY: Trees left to meet stocking levels specified in thinning guides and task order.

2.2.16 WILDLIFE TREE: Standing dead and/or dying trees. Used by birds and small mammals for shelter, nesting, perching, etc..

2.2.17 OPEN AREAS: As it relates to location of slash piles; areas that are at least twice their diameter from residual timber so that burning of piles will not result in damage to residual timber

SECTION III

3.1 Service Work

SECTION IV

Technical Specifications and Treatment Descriptions

1. Cutting and slash processing specification Units: 1, 2, 3, & 4 All trees are designated for cutting when meeting the minimum specifications for cutting as shown on the table below:

Units
Cutting Designation
Requirements
1 & 2
All Ponderosa Pine dead with no foliage or 100% red or brown needles or marked with orange cut tree mark
All Ponderosa Pine marked with orange tracer paint (cut tree mark) or dead with no foliage or 100% red or brown needles is to be cut (felled)
1, 2, 3 & 4
75% of Contractor generated slash.
Slash shall be piled in open areas so that when piles are burned the fire will not scorch residual trees. Piles shall be constructed with an even mixture of fine and heavy fuels; a preference of the largest diameter material to be placed on top of the pile in order to facilitate consumption. Piles will need to be compact with minimal air space within the pile (mechanical means used to “smash” the piles to achieve minimal air space is recommended). Piles shall be free of debris and dirt, and at least an average size of 20’ diameter up to 40’ diameter. Piles may be located within unit or at COR designated landing sites
3 & 4
All Ponderosa Pine dead with no foliage or 100% red or brown needles or all trees NOT marked with orange Leave Tree Mark (LTM)
All Ponderosa Pine NOT marked with orange tracer paint (leave tree mark-LTM) greater than 5” DBH or dead with no foliage or 100% red or brown needles is to be cut (felled)

2. Yarding and Decking Specification (Service Timber)

Units
Designation
Service Requirements
3 & 4
All Felled Designated Timber
Process felled logs by cutting bole at a 3-4” top, remove all live and dead branches from the bole, leave no raised edges - nubs after branch removal (smooth edge)- branches should be cut as close to bole as possible.
3 & 4
Post processed logs
Yard post process logs to designated decking area and deck – decks can be made on either side of designated area, no decking in roads, minimum size of deck is (face length) 8’ x 4’ height, all butt ends shall be facing one direction

3. Road maintenance specifications are located in appendix C

CRITERIA

SECTION V – PERFORMANCE REQUIREMENTS SUMMARY

Task
Performance Standard
Acceptable Quality Level (AQL)
Monitoring Method
*Felling
Cut all trees identified in the statement of work
90% Acceptable Level of performance, unless otherwise permitted by contract requirements.
Contractor’s written record of plot inspection.

Regular onsite visual review of specification compliance.

Periodic verification of compliance with the use of walk through and 1/20 acre inspection Plots.

*Skidding/Yarding/Decking
Skidding, yarding and decking of all service designated trees/material to designated location;
90% Acceptable level of performance, unless otherwise permitted by contract requirements.
Contractor’s written record of plot inspection.

Regular onsite visual review of specification compliance.

Periodic verification of compliance with the use of walk through

*Processing of Material
Service designated timber processed prior to decking to contract specifications;
90% Acceptable level of Performance, unless otherwise permitted by contract requirements.
Regular onsite visual review of specification compliance.

Written documentation of visual inspection

*Slash Treatment
Treatment of slash to contract specifications
90% Acceptable level of Performance, unless otherwise permitted by contract requirements.
Contractor’s written record of plot inspection.

Regular onsite visual review of specification compliance.

Periodic verification of compliance with the use of walk through and 1/20 acre inspection Plots.

*Road Maintenance
Per Contract Specifications
90% Acceptable level of Performance, unless otherwise permitted by contract requirements.
Written documentation of visual inspection

Regular onsite review of specification compliance.

*Disincentives for failure to meet the above standards may be as follows:

· Rework will be completed at contractor’s expense.

· If re-work is not physically possible, payment deductions will be made for work falling below AQL (see Section G.3.1 Payment Reductions).

· Damage to the residual stand or infrastructure will be assessed against the contractor.

· Government re-inspection charges may apply.

· Poor Performance Rating will be given.

SECTION VI – QUALITY ASSURANCE INSPECTIONS

The Government will complete inspections as stated below for all work included in the contract.

The Government will use fixed radius plot sizes ranging from 1/5th acre (52.7’ radius) to 1/100th acre (11.8’ radius). A minimum of one percent of the treatment unit will be sampled. The Contractor will be provided information on the sampling methods applied by the Government to measure quality assurance. The Contractor shall maintain a plot system that provides an unbiased sample of thinning quality and slash treatment which represents the entire treated area. At least one percent of the treated area shall be sampled. The Government may observe or re-inspect the Contractor’s plots at any time. Prior to final inspection, all plot locations shall be identified on the ground by sketch map and flagging, unless by alternative method approved by the CO.

7.2 Each inspection plot will be subdivided into four (4) quadrants based on cardinal directions.

Each quadrant will be evaluated for compliance with all contract specifications as stated in section IV that pertains to that individual treatment. If two (2) or more quadrants fail to comply, the plot will fail.

7.3 Work Quality Percentage: Work quality percentages are derived from data developed from inspection plots. The total number of satisfactory plots divided by the number of plots inspected determines the quality rate. The rate multiplied by 100 provides the work quality percentage.

Example: Number of plots inspected 25 Number of satisfactory plots 23 23 divided by 25 .92 Work Quality Percentage 92%

7.4 Government will pay 100% of line item price if work quality of all plots is at 90% or greater. If below, the government will issue a letter of non-compliance. Contractor will be permitted to bring work quality to an acceptable standard. If the Contractor is unable to bring the work to an acceptable standard, then line item pricing will be reduced to the work quality percentage rate.

File details come from the government source that posted it.