RFIs and Responses 3.docx

DOCX document 29 KB Posted

Attached to
Epoxy Floor Repair, Moore Air Base, TX Federal contract opportunity
Solicitation number
12639525Q0168
Issued by
Department of Agriculture Animal and Plant Health Inspection Service Marketing and Regulatory Programs Business Services

About this file

The document is an RFI (Request for Information) file containing responses to three contractor queries for a USDA epoxy floor repair project at Moore Air Base in Edinburg, Texas. The project, set aside for service-disabled veteran-owned small businesses, involves resurfacing floors in Building 6418, a Mexican Fruit Fly Rearing Facility. The contract is categorized under NAICS code 238330 with a small business size standard of $19 million, and has an estimated project value between $500,000 and $1 million.

The RFI responses address key operational details, confirming that: (1) contractors may propose their own phasing plan for floor installation, subject to operational constraints, (2) work hours can be extended beyond the standard Monday-Friday, 7:00 AM to 3:30 PM schedule with proper coordination and written approval, and (3) on-site power and water utilities are available for construction use. The solicitation is scheduled to be posted on July 22, 2025, with Jim Roloff serving as the contracting officer. A notable requirement is the inclusion of a moisture barrier primer in the quote.

View the file

Other files for this federal contract opportunity

Other files attached to Epoxy Floor Repair, Moore Air Base, TX, newest first.
File Type Posted
RFIs and Responses 2.docx DOCX document
RFIs and Responses.docx DOCX document
Epoxy flooring site visit attendance.pdf PDF
Atch 2_Federal Construction Wage Rates_Hidalgo County.pdf PDF
Atch 1_SOW_B6418 Epoxy Floor Project.docx DOCX document
12639525Q0168.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFIs and Responses

1. Phasing of Work: The Statement of Work mentions the installation will occur one section at a time to allow for relocation of equipment and personnel. Can you confirm how many total phases are anticipated, or should we propose a phasing plan based on our approach?

You may propose a phasing plan and if operations can permit it can be implemented. However, things can change.

1. Work Schedule Flexibility: We understand regular working hours are Monday through Friday, 7:00 AM to 3:30 PM, and that any work beyond that must be pre-approved. Can you confirm whether weekend work is allowed if properly coordinated and approved in writing?

Yes, working hours can be extended with coordination and approval.

1. Utilities On-Site: Is there access to water and power for construction use, or should we plan to bring in temporary sources?

Yes, power and water are available.