Text version
IFB 12569R19B0003
Submitted Questions and Answers
1. Will alternate proposals be considered?
a. Yes, provided that they are submitted in accordance with FAR 52.204-22, and that they do not negatively impact the current WI DNR permit.
2. Can work on this project begin after Nov. 1, 2019.
a. The period of performance can be negotiated with engineering approval.