Attachment #1 Performance Work Statement and Quality Assurance Plan: Roads Maintenance, Wayne National Forest
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2015-4365.pdf | ||
| OH180002.pdf | ||
| 1255N918R0002.pdf | ||
| 2015-4765.pdf | ||
| Attachment_8.pdf | ||
| 2015-4729.pdf | ||
| Attachment4.pdf | ||
| Attachment_11.pdf | ||
| Attachment_7.pdf | ||
| Attachment6.pdf | ||
| 2015-4771.pdf | ||
| 2015-5785.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 1 - Performance Work Statement and Quality Assurance Plan
REQUIREMENT TASKS/CRITICAL
SUB-TASKS
QUALITY
STANDARDS
AQL RELATED
DRAWING
MONITOR
METHOD
INCENTIVE/
DISINCENTIVE
1. Roadway 1.a.1 Corridor vegetation and debris removal - Mowing Machinery
Maintain as shown in WNF-1 drawing.
All areas as described on drawing are free of vegetation and debris.
99% to standard drawing and as per FP-14 Section 201, clearing & grubbing
WNF 1 Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
1.a.2 Open Area vegetation and debris removal – Mowing Machinery
Mow all vegetation and remove all debris as specified in the TO.
All areas are free of vegetation and debris.
100% N/A Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
1.a.3 Corridor Mowing – Hand Tools
Cut all vegetation and remove all debris as specified in the
TO.
All areas are free of vegetation and debris.
100% N/A Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
1.a.4 Open Area Mowing – Hand Tools
Cut all vegetation and remove all debris as specified in the
TO.
All areas are free of vegetation and debris.
100% N/A Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
1.a.5 Seeding and Mulch
Revegetate disturbed or eroded areas as specified in the TO.
Seed is distributed at the rate of 100#/Ac; See Attachment #5 WNF Seed Mixtures & Mulch or FS Botanist approved substitute
80 % germination with no bare spots in excess of one square foot. Straw to have 90% coverage by area.
N/A Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
SUB-TASKS
QUALITY
STANDARDS
AQL RELATED
DRAWING
MONITOR
METHOD
INCENTIVE/
DISINCENTIVE
1.b.1 Signs & 1.b.2 Carsonite Sign Posts
Repair/Replace traffic control, route marker, and roadside info signs, FS will provide panels, contractor required to provide hardware, post and all labor.
USFS Sign Installation Guide
100%
USFS Sign Installation Guide, DWGS WNF-
5, 6, 7, & 8 and FP-14, 633 & 718- 5,6,7 & 8
Visual 100%
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
1.c.1 – 1.c.5 Gates Build & Install or repair gates including markers, hardware, gate posts
Maintain per gate typical drawings
100% WNF 5, 6, &
7 and FP-14, Sections 619 and 718
Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
2. Road Surface 2.a.1 & 2.a.2 Grading Surface: Provide a safe, smooth, drained surface free of potholes, ruts, berms, washboard and organic soil and debris while recovering any useable existing aggregate. This work also includes the reconditioning of drainage dips, turn-outs, and turnarounds.
Base: All potholes and washboard areas will be scarified and repaired to produce a smooth uniform surface free of debris and soil.
Water, if needed to prevent heavy dusting and/or to allow the aggregates to bind, will be applied as needed.
Maintain per road surface typical and as per FP-14 Section 303, road reconditioning
a. Safe = 100%
b. Smooth Surface 95%
c. Potholes, Ruts, Washboard = 95% d.
Berms/organic soil = 95%
WNF 1,2,& 3 Drivability on 100% of the road
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
QUALITY
STANDARDS
AQL RELATED
DRAWING
MONITOR
METHOD
INCENTIVE/
DISINCENTIVE
2.a.3 – Pavement Pothole Repair
Prepare the repair area by removing damaged pavement, base, subgrade.
Apply tack coat. Apply new pavement and compact.
Work Area Management – Traffic control, safety.
Gradation and quality meets FP- 14 Sect. 401.
Proper preparation of repair area.
Finished elevation to match adjoining surfaces. Patch material adheres to adjoining surfaces.
In accordance with FP-14 and accepted industry practice 100%
WNF-2 and
TO.
Certification of Quality of AC mix one sample per lot.
Visual 100%
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
2.a.4 – Pavement Crack Patching
Prepare cracks > ¼” wide by removing all debris. Clean adjacent surface. Apply crack filler in accordance with manufacturer’s recommendations. Work Area Management – Traffic control, safety.
Crack preparation meets standards.
Crack patch material adheres to adjoining surface.
In accordance with FP-14 and accepted industry practice 100%
Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
2.a.5 – Pavement Sealing
Prepare the surface by cleaning and removing loose pavement and debris. Apply sealer in accordance with manufacturer’s recommendations. Work Area Management – Traffic control, safety.
Surface preparation meets standards. Sealant material adheres to surface. Proper coverage and thickness.
In accordance with FP-14 and accepted industry practice 100%
Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
2.a.6 – Pavement Striping
Prepare the surface by cleaning and removing loose pavement and debris. Apply traffic paint in accordance with manufacturer’s recommendations. Work Area Management – Traffic control, safety.
Paint meets FP-14 standards. Line locations, colors, widths, and lengths are in accordance with
TO.
In accordance with FP-14 and accepted industry practice 100%
Visual 100% • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
QUALITY
STANDARDS
AQL RELATED
DRAWING
MONITOR
METHOD
INCENTIVE/
DISINCENTIVE
2.c.1 – 2.c.3 RipRap Provide and Place as required in task order, will require machine placement.
Gradation/quality meets ODOT Standards for gradation and for rock materials placement in accordance with culvert typicals
In accordance with State Standards and accepted industry practice 100%
WNF: 4 and T.O.
Certification of Quality of rock -one sample per lot.
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
2.g - Geotextile Smooth ground and remove debris and rocks. Install in accordance with manufacturer’s recommendations.
Geotextile meets FP-14 standards.
Location of installation are in accordance with
TO.
In accordance with FP-14 and accepted industry practice 100%
Certification of geotextile by shipping tag.
Visual 100%.
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
2.h – Silt Fence Prepare ground and installation trench. Install in accordance with manufacturer’s recommendations.
Silt Fence meets FP-14 standards.
Location of installation are in accordance with
TO.
In accordance with FP-14 and accepted industry practice 100%
Certification of silt fence by shipping tag. Visual 100%.
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
3. Drainage 3.a - Dips (install) Install drainage dip in locations as directed by TO Install as per typical
100% install to typical
WNF: 3 Visual/drivability • Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
3.b - Culvert (clean) Clean culvert to maintain free flow
Removal of blockages, debris, and obstructions including barrel, inlet/outlet basins
Free flowing to maximum attainable flow.
WNF: 4 Visual random sample
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
QUALITY
STANDARDS
AQL RELATED
DRAWING
MONITOR
METHOD
INCENTIVE/
DISINCENTIVE
3.c.1 – 3.c.4 Culvert (replacement)
Replace culverts in locations as directed by TO.
(compaction of backfill included)
Install per FP-14 Sect. 602 and as shown on TO and drawings.
100% compliance with FP-14, section 602.
WNF: 4 Compliance with FP-14, section 602.
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
3.d – Clean Ditches Clean ditches to maintain free flow in an environmentally sound manner.
Maintain original ditch shape for free flow
Free flowing WNF: 1 & 4 Visual random sample
• Positive/Negative performance to be reported to CPARS.
• Exercise of potential option years will be considered.
• Reasonable attempts to rework sites will be allowed.
3.e – Construct Ditches
Construct ditches as specified in the TO.
Install to drawing standards.
Free Flowing WNF-1 &
WNF-4
Visual 100% • Positive/Negative performance to be reported to CPARS.