This document is a Material Approval Submittal form related to a federal contract opportunity for the modernization of a passenger elevator located at the National Laboratory for Agriculture and Environment (NLAE) in Ames, Iowa.
The key details are:
- The contract opportunity is a 100% small business set-aside with a NAICS code of 238290 and a $22 million size standard.
- The estimated magnitude of construction is between $100,000 and $250,000 with a 450-day period of performance.
- Site visits are scheduled for April 10 and April 11, 2024, and questions are due by April 18, 2024.
- The solicitation is a Request for Proposals and will be awarded as a firm-fixed price contract.
- The Material Approval Submittal form is used by the contractor to get approval for materials to be used on the project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12505B24Q0116 -0001.pdf | ||
| 8. Site Visit Sign-in.pdf | ||
| 1. SF 1442 - 12505B24Q0116.pdf | ||
| 3. Wage Determination IA20240074 03-01-2024.pdf | ||
| 2. SOW-Q0116.pdf | ||
| 7. Past Performance Questionnaire.pdf | ||
| 5. ARS-371.pdf | ||
| 6. ARS-372.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MATERIAL APPROVAL SUBMITTAL
TO: USDA/ARS
CO CC: Technical
POC
FROM: (Contractor) PROJECT TITLE: CONTRACT NUMBER:
(To be completed by the Contractor) Government Use Only
SUBMITTAL
NUMBER:
PREVIOUS SUBMITTAL NUMBER
(only if items listed were submitted previously):
Technical POC
Recommendation
Contracting Officer Approval/Disapproval
Line
No.
Specification Sect.
Para No., Draw No.
Description of Material
(Include type, model, mfg) APP DISAP
See
Comments on Reverse APP DISAP
See
Comments on
Reverse
If an item is disapproved, a resubmittal is due within ________ calendar days of the Contracting Officer’s signature below.
Contractor Technical POC Contracting Officer TYPE or PRINT NAME & TITLE TYPE or PRINT NAME & TITLE TYPE or PRINT NAME & TITLE
SIGNATURE: SIGNATURE: SIGNATURE:
DATE: DATE: DATE:
By completing this form, the above signed contractor certifies that the material complies with all specifications of the subject contract.
DATE RECEIVED FROM Contractor: DATE RECEIVED FROM COR:
Material Approval Submittal Cover Sheet (11/2016)
CONTRACT #: SUBMITTAL #:
COMMENTS
Instructions: Enter the initials of the individual making the comment, the Line Number of the item for which the comment is being made, and the comment.
Material Approval Submittal Cover Sheet (11/2016) (Reverse)
File details come from the government source that posted it. Updated .