124d9018B0003_Attachment_2.pdf
PDF 575 KB Posted
- Attached to
- WRP ACEP Fence Construction Calhoun County, TX Federal contract opportunity
- Solicitation number
- 124D9018B0003
About this file
124D9018B0003 Attachment 2
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BID_OPENING_RESULTS.pdf | ||
| 124D9018B0003_Amendment_0002.pdf | ||
| 124D9018B0003_Amendment_0001.pdf | ||
| 124D9018B0003_Attachment_5.pdf | ||
| 124D9018B0003_Attachment_4.pdf | ||
| 124D9018B0003_Attachment_7.pdf | ||
| 124D9018B0003_Attachment_6.pdf | ||
| 124D9018B0003_Attachment_3.pdf | ||
| 124D9018B0003_Attachment_1.pdf | ||
| 124D9018B0003.pdf | ||
| 124D9018B0003_Pre-Solicitation_Notice_WRP_ACEP_Fence.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Natural Resources Conservation Service
STATEMENT OF WORK
FENCE (382)
Texas
May 2010 1
These deliverables apply to this individual practice. For other planned practice deliverables refer to those specific Statements of Work.
INSTALLATION
Deliverables
1. Pre Installation conference with client and contractor.
2. Verification that client has obtained required permits.
a. Prior to construction of fence, a utility check sheet must be completed to make sure all underground utilities are avoided. The producer/contractor must call 1-800-344-8377
(1-800-DIGTESS).
3. Staking and layout according to plans and specifications including applicable layout notes.
4. Installation inspection (according to inspection plan as appropriate).
a. Actual materials used (Part 512, Subchapter D Quality Assurance Activities, 512.33)
b. Inspection records
5. Facilitate and implement required design modifications with client and original designer.
6. Advise client/NRCS on compliance issues with all federal, state, tribal, and local laws, regulations and NRCS policies during installation.
7. Certification that the installation process and materials meets design and permit requirements.
CHECK OUT
Deliverables
1. As-Built documentation.
a. Extent of practice units applied
2. Certification that the installation meets NRCS standards and specifications and is in compliance with permits (NEM Subpart A, 505.03 (c) (1)).
3. Exit conference with client and contractor.
REFERENCES
• NRCS Field Office Technical Guide (eFOTG), Section IV, Conservation Practice Standard - Fence,
• NRCS National Engineering Manual (NEM).
• NRCS National Environmental Compliance Handbook
• NRCS Cultural Resources Handbook