Q and A as of 9 Nov.pdf

PDF 121 KB Posted

Attached to
GAOA KNEFF LAKE RECREATION IMPROVEMENTS - Water System
Solicitation number
12445524Q0003
Issued by

About this file

This document contains questions and answers related to federal solicitation number 12445524Q0003 for water system improvements at Kneff Lake Recreation Area. The solicitation is seeking a contractor to install a new wellhouse, water lines, and related infrastructure. While general sketches of a wellhouse design are provided, manufacturers will determine final electrical and plumbing details. The contractor is responsible for electrical system schematics, design, and preinstalled panels. No tree clearing is expected to be required for the project. Start dates are dependent on weather and award timing, with work anticipated to begin by December 1st. Completion dates are included in the specification documents. The soliciting agency is the US Department of Agriculture Forest Service.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GAOA HMF Kneff Lake Water Wastewater 12445524Q0003

Ques ons and Answers As of 11/9/2023

Q1. Please provide electrical details or sketches of the well‐house and related panel. In reference to what is being proposed (new well‐house)

A1. Sketches of general well house provided, details manufacturer dependent. Electrical panel should be pre‐installed, with electrical system schema cs and design data responsibility of the contractor. See specifica on Sec on 260500, 1.2 Submi als. Refer to the project specifica ons and drawings.

Q2. Related to the site conditions of the water lines and access to them, are there any trees to be removed? If so, please specify how many and size. Is it possible to provide some pictures of the route?

A2. No tree clearing is expected to be required for the project. Due to proximity of loca on to personnel, weather condi ons and workload, pictures are not currently available.

Q3. Related to the well site, is there any tree to be removed to access the well and excavate? is there any picture available?

A3. No tree clearing is expected to be required for the project. Due to proximity of loca on to personnel, weather condi ons and workload, pictures are not currently available.

Q4. Please confirm the expected date for starting and completion dates of the project.

A4. Start date on ground is dependent upon weather and capabilities at time of award (anticipated to be by 1 December). Expected start and duration of project are included in Specifications.

File details come from the government source that posted it. Updated .