Margaret Creek Phase II - Additions
Margaret Creek – Draft Machine Placement Sites
Conceptual Drawings
Plan View
•NF-A
•NF-B
Stump
Buried to scour (4’)
5 Trees
• 4 whole
• 2 half
10 Trees
• 8 whole
• 4 half
= Vegetation
= Existing Log
= Gravel Bar
= Log with rootwad
= Piling
= Cut Log with branches
Scale is Approximate
N
Stump Stump
Stump
Stump
Gravel Bar
Site Goals NF-A: Armor north bank, narrow channel, maintain pool & gravel bar, & wet side channel at high flows.
NF-B: Maintain gravel bar and downstream pool. Narrow & constrict channel to historic width (refer to stumps downstream); construct bar buddy on gravel bar to stabilize and build up bar on north side; key wood into existing wood on upstream end of site.
Pool
•NF-C
Margaret Creek – Draft Machine Placement Sites
Conceptual Drawings
Plan View
Side Channel
= Vegetation
= Existing Log
= Gravel Bar
= Log with rootwad
= Piling
= Cut Log with branches
Buried to scour (4’) Gravel Bar
6 Trees
• 4 whole
• 4 half
3 Trees
• 1 whole
• 4 half
Scale is Approximate
N
Stream Crossing
Site Goals NF-C: Key wood into north bank to maintain lateral scour pool, armor north bank; construct bar buddy on south gravel bar to maintain and build up south side gravel bar.
Note: access to upstream sites from this site, cross stream to access spur road.
Pool
Plan View
Stump
Old Side Channel
•NF-D
Margaret Creek – Draft Machine Placement Sites
Conceptual Drawings
Stump
Buried to scour (4’)5 Trees
• 3 Whole
• 4 Half
6 Trees
• 3 Whole
• 6 Half
7 Trees
• 4 Whole
• 6 Half
8 Trees
• 6 Whole
• 4 Half
= Vegetation
= Existing Log
= Gravel Bar
= Log with rootwad
= Piling
= Cut Log with branches
Scale is Approximate
N
•NF-E
Site Goals NF-D: Key wood into south bank to stabilize stream bank.
NF-E: Key wood into south bank to stabilize stream bank and maintain pool;
construct bar buddy on north bar to build up bar and narrow channel, key wood into floodplain on north side.
Site NF-A Downstream
Site NF-A North Side View
Site NF-B Looking Upstream From NF-A
Site NF-B Looking Downstream
Site NF-B Upstream
Site NF-C
Site NF-D
Site NF-E
File details come from the government source that posted it. Updated .