Amendment 004_Bovee Fire Fence Removal and Reconstruction_CO Signed.pdf
PDF 174 KB Posted
- Attached to
- Bovee Fire Fence Removal & Reconstruction Federal contract opportunity
- Solicitation number
- 12363N23Q4177
- Issued by
- Department of Agriculture Forest Service
About this file
This amendment modifies a federal solicitation for fence removal and reconstruction services. The amendment adds clauses requiring a one-year warranty of construction and performance and payment bonds within 10 days of award. Offerors must acknowledge receipt of the amendment by the closing date of June 30, 2023. The related opportunity is for removing approximately 16 miles of damaged fence following the Bovee wildfire and constructing new fence in the same locations to specifications provided by the Bessey National Forest unit of the U.S. Department of Agriculture Forest Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 003_Bovee Fire Fence Removal and Reconstruction_CO Signed.pdf | ||
| Amendment 002_Bovee Fire Fence Removal and Reconstruction_CO Signed.pdf | ||
| Wage Determination NE20230048.pdf | ||
| 2023 BAR Fence Contract_Boundary Map_BRD.pdf | ||
| Bovee Fire Fence Removal and Reconstruction_12363N23Q4177.doc | DOC document | |
| 2023 BAR Fence Contract Priority Map_BRD.pdf | ||
| 2023 BAR Fence Construction Specifications_BRD.pdf | ||
| Amendment 001_Bovee Fire Fence Removal Reconstruction_Signed.pdf | ||
| 2023 BAR Fence Contract Priority Map_BRD.pdf | ||
| 2023 BAR Fence Contract_Boundary Map_BRD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT CONTRACT ID CODE
363N
PAGE OF PAGES
1 of
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
06/28/2023
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE |______363N_______
National Stewardship IRSC PPS 1400 Independence Ave, SW
MS-1138
Washington, DC 20250
7. ADMINISTERED BY (If other than Item 6) CODE |___________________
Same as block 6.
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State, and ZIP Code)
9A. AMENDMENT OF SOLICITATION NO.
12363N23Q4177 X
9B. DATED (SEE ITEM 11)
05/17/2023 (Solicitation)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[ x ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [ X ] is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning _____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virture of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
x D. OTHER (Specify type of modification and authority) Unilateral Authority. Warrant: Professional B, Dated: 3/3/2023
E. IMPORTANT: Contractor [ ] is not, [ x ] is required to sign this document and return __1___ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this Amendment #003: The purpose of this amendment is to add clauses to clarify in detail and support block 12a. and 12b. for bonding. Section I Add the Following Clauses:
FAR 52.246-21 Warranty of Construction (MAR 1994)
FAR 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) – Note Block 12b. states that within 10 days after acceptance of award, bonding must be submitted. A digital scan copy of the bonding forms, the power of attorney, and assurety bond may be submitted.
The originals are to be mailed to: USDA; Attn: Darren Zychek; 12740 HWY 12, 83544.
See Page 2-4 for full text.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
DARREN M. ZYCHEK
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY: ____________________________________
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070
PREVIOUS EDITION UNUSABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
DARREN ZYCHEK Digitally signed by DARREN ZYCHEK Date: 2023.06.28 09:49:50 -07'00'
Page 2 of 2 for Amendment 004 to 12363N23Q4177 Dated: 06/28/2023
FAR 52.246-21 Warranty of Construction (Mar 1994).
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph
(i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
(c) The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor’s expense any damage to Government-owned or controlled real or personal property, when that damage is the result of-
(1) The Contractor’s failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall-
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
(h) In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor’s, manufacturer’s, or supplier’s warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.
(j) This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.
(End of clause)
Page 3 of 3 for Amendment 004 to 12363N23Q4177 Dated: 06/28/2023
FAR 52.228-15 Performance and Payment Bonds-Construction (Jun 2020)
(a) Definitions. As used in this clause-
Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds ( Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds ( Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of the Treasury, Financial Management, Service Surety Bond Branch, 3700 East West Highway, Room 6 F01, Hyattsville, MD 20782.
Or via the internet at http://www.fms.treas.gov/c570/.
Page 4 of 4 for Amendment 004 to 12363N23Q4177 Dated: 06/28/2023
(e) Notice of subcontractor waiver of protection ( 40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
(End of clause)