About this file

Amendment 02 - Site Visit Agenda, Questions & Answers

View the file

Other files for this federal contract opportunity

Other files attached to Electrical Upgrade in Building 13, newest first.
File Type Posted
SF-30_Amendment_03.pdf PDF
Amendment_1.pdf PDF
Attachment_I_-_Specifications_for_base.pdf PDF
Attachment_III_-_Option_1_-_SOW_with_photos.pdf PDF
Attachment_IV_-_DBA_Wage_Rates.pdf PDF
Attachment_II_-_Drawings_for_base.pdf PDF
Solicitation_-_1232SDS18JC06.pdf PDF
Attachment_V_-_Payment_and_Performance_Bond_Forms.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or

(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

PREVIOUS EDITION UNUSABLE STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

This form was electronically produced by USDA/ARS/OCIO/ADB.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date,etc.)

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

07/12/2018

06/22/2018

1 7

Amendment No. 02

USDA, ARS, WBSC

1001 HOLLEMAN DRIVE EAST

COLLEGE STATION, TS 77840

Phone: (979) 260-9446 Email: joseph.covarrubio@ars.usda.gov

SAME AS BLOCK 6

ALL PROSPECTIVE BIDDERS 1232SDS18JC06

This solicitation is amended to incorporate the Pre-Bid/Site Visit meeting Q&A's and agenda. No other changes are made.

The bid due date IS extended to July 23, 2018 by close of business 4:30p.m CST.

No other changes are made to the terms and conditions of this solicitation.

BIDDERS MUST ACKNOWLEDGE THIS AMENDMENT BY SIGNING THIS SF-30 AND RETURNING IT WITH YOUR BID.

Joseph Covarrubio, CONTRACT SPECIALIST

07/12/2018

INSTRUCTIONS

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code) . Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effec-tive date shall be the same as the effective date of the initial decision.

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(1) Accounting classification

Net increase $

(2) Accounting classification Net decrease $

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

(1)

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i)

(ii)

(iii)

Total contract price increased by $

Total contract price decreased by $

Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

When the SF 30 is used to reflect a determi-nation by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to -

(i) A reference to the letter determination; and

A statement of the net amount determined to be due in settlement of the contract.

Include subject matter or short title of solicita-tion/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contract-ing officer's signature is normally affixed last on supplemental agreements.

STANDARD FORM 30 BACK (REV. 10-83)

(1)

(a)

(b)

(2)

(3)

(4)

(5)

(c)

(d)

(e)

(f)

Item 9, (Amendment of Solicitation No.--Dated), and 10, (Modification of Contract/Order No.-- Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

(g)

(2)

(3)

(4)

(5)

(6)

(i)

(ii)

(h)

Site Visit/Pre-Bid Agenda 1232SDS18JC06

SITE VISIT/PRE-BID CONFERENCE

RFQ No. 1232SDS18JC06 Date: June 28, 2018 10:00 a.m.

Baton Rouge, LA

AGENDA

Introductions - All

Bid Requirements - Review of Bidding Procedure

Questions and Answers on Contract

Receive Questions for Answers to be distributed as an Amendment to the Solicitation

Visit Project Site

This meeting is the site visit for Request for Quotation (RFQ) No. 1232SDS18JC06 to Replace the main electrical service panels and the branch circuit panel in Bldg. 13 along with an Option 1 for an Electrical Up-Grade in Bldg. 11, at the USDA, ARS, Honey Bee Breeding, Genetics and Physiology Research Unit, in Baton Rouge, LA. No oral remarks or explanations made here today will alter or otherwise qualify the written provisions of the RFQ as it now exists. The minutes will be issued as soon as possible, covering the elements known now and those which may be discovered today. Only a written amendment will officially change or clarify the written provisions of the solicitation package. It is not anticipated that an extension to the bid due date will be issued.

1. Introductions:

Representatives from the Location:

Gail Champagne, Administrative Officer (AO) Josh Wales, Location Site Monitor (LSM)

Representatives not at location:

Brian Dean, Contracting Officer’s Representative (COR) Douglas Stickler, Contracting Officer (CO) Joseph Covarrubio, Contract Specialist (CS)

2. Proposal Requirements:

Bidder is reminded of several important items in preparing bids.

1) You must sign the SF-18 form and acknowledge any amendments to the solicitation. There is one amendment to date.

2) You have completed Blocks 11, 12, 13, & 16 and signed and dated Blocks 14, and 15 of the

SF-18, "Request for Quotation" form and insert DUNS on page 2.

3) No bid bond is required for this acquisition.

4) In the event the successful bid exceeds $35,000, Alternate payment protection will be required for this contract. See FAR Clause 52.228-13 Alternate Payment Protections.

5) The Davis-Bacon wage rates apply to the contract. They are included as Attachment IV to the solicitation.

6) No exemption is granted for state or local taxes. You should include this expense as part of your bid price.

7) Your Proposal is to be emailed (preferred), faxed or mailed to USDA, ARS, WBSC, Joseph

Covarrubio, Contract Specialist, 1001 Holleman Drive East, College Station, Texas 77840.

Email: joseph.covarrubio@ars.usda.gov, Fax: (979) 260-9413. Your BID is due no later than 4:30 p.m. (Central Time) on Friday July 13, 2018.

8) There are no liquidated damages on this contract.

9) There will be no retainage withheld unless there has been no performance.

10) Contractor MUST be registered in the System for Award Management (SAM) prior to the submission of proposal/bid. You can register online at www.sam.gov .

11) Contractor is required to submit their invoices electronically into the government’s Invoicing Processing Platform. You can register online at www.ipp.gov .

3. Utilities:

A reasonable amount of electricity and water, will be provided to the contractor by the Government at no cost. The contractor will be expected to maintain their own work site trailer and/or telephone. Use of restroom facilities by contractor's employees, parking areas, storage areas, etc. will need to be discussed today with representatives from the location.

4. Technical Overview of the Project:

The representatives from the location will provide an overview of the technical aspects of the project.

After Site-Visit Questions and Answers for Solicitation 1232SDS18JC06 Electrical

Upgrade Project – Baton Rouge, LA

Answers in red, two additional notes in red also.

1. Will the existing server in the mezzanine need to be connected to temporary power.

A. No.

2. Is the 400amp feed being replaced for either base option or option 1

A. For Base, per Sheet E100, Keyed Note 2, reuse existing building service. Bldg 13 400 Amp service to be replaced if option 1 awarded.

3. If the option is not performed does the 400 amp feeder have to replaced.

A. No.

4. Will Robroy conduit be required for the project.

A. No.

- Additional note # 1 - Contractor to perform Option # 1 600 amp panel replacement over long weekend to minimize outage duration for Building 11 and buildings other than Building 13.

- Additional note # 2 – In addition to providing temporary power to subzero freezers and exterior packaged AC unit, contractor to provide temporary power to 12 freezers (mixture of chest and upright) which will be located in the hallway of B13. Contactor to verify electrical requirements of freezers.

07/12/2018

SF-30 Amend 07-12-18p
Site Visit Agenda - Electrical Upgrade...
Site Visit Pre Bid Electrical Upgrade Baton Rouge LA 06282018
Questions and Answers

File details come from the government source that posted it.